He Plant, LN2 Systems and Commissioing
Güney Korkmaz 7th Machine Advisory Committee Meeting of TARLA SEPTEMBER Ankara University
2
CONTENT Introduction TARLA’s scope He Plant comissioning plan
Warm piping He Plant comissioning plan
3
He Plant : Layout & Piping
50 m3 He Buffer Phase Seperator 500 L Dewar Cold Box 2 Compressor Station Vaporizer Cold Box 1 Warm Vacuum Pumps 10 m3 LN2 Buffer LN2 Vaporizer Oil Removal System Cooling Power at 1.8 K 210 W Outlet temperature 1.8 – 2.1 K Liquid He pressure stability ± 0.2 mbar Flow rate of 1.8 K liquid He 0 – 10.7 g/s
4
He Plant : Basic P&ID
5
TARLA’s scope Infrastructure (done) UPS (done)
Unboxing and positioning (done) Instrument Air (done) Cooling Water (done) He gas & LN2 purchase (done) Signal and Electricity Cables (WIP) Warm piping (WIP)
6
Issues with warm piping
Contract made in Dec. 2014 Late delivery (June 2015) of equipment Poor welding quality Equipment cleanliness issues
7
Warm Piping Acceptance tests Radiographic inspection of weldings
To see penetration of weldings Pressure test 15 bar Helium Leak test ≤ 10-5 mbarl/s Cleanliness inspection
8
CB 2 & Test Module : Basic P&ID
9
Tests of Helium Plant Commissioning will finish in Jan. 2016
Cooldown mode (300 K to 4.5 K) Stand-by mode (4.5 K) Operation mode (1.8 K – 2.1 K) Warm up mode (1.8 K to 300 K) Acceptance criteria ±0.2 mbar pressure stability and temperature between 1.8 – 2.1 K for 2 hours
10
Conclusion Cabling and warm piping will be completed in Sep. 2015
Tests of warm piping will be completed in Oct. 2015 If the tests are succesful we will be ready for final stage of comissioning