1 Outotec GIW Pumps and Pumping Solutions Astana Mining and Metallurgy 15.06.2016
Janne Turunen

2 Astana Mining and Metallurgy
Agenda General introduction Outotec – GIW product portfolio Case Studies Phosphate mine in Finland Copper mine in Chile Try & Buy Concept for selected applications 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

3 Outotec - GIW cooperation
Outotec Minerals Processing product portfolio extended with GIW® slurry pumps. World leading slurry solutions for mining companies. GIW’s hard iron manufacturing experience and slurry pumping knowledge is put together the minerals processing capability of Outotec. Combined resources ensure best technology with life cycle services and local support. Enables optimization of total lifetime costs (TCO) of pumping and concentrator solution 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

4 Outotec GIW slurry pump product families
Pumps for thickening Pumps for tailings Pumps for filtration Pumps for grinding Pumps for flotation 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

5 GIW Industries, Inc. (Georgian Iron Works)
1891 in Georgia, USA Supplying slurry pumps to mining industry for over 100 years from own factory and foundry. Leading supplier of slurry pumps in American continent Strong focus on pump hydraulic design and material technology development 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

6 Outotec GIW Slurry Pumps Brief product portfolio
Astana Mining and Metallurgy Outotec GIW Slurry Pumps Brief product portfolio 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

7 MDX Series pumps LSA Series pumps
MDX for the most difficult and abrasive conditions. MDX maximizes productivity and minimizes costs by matching operating cycle times of grinding section Heavy grinding feed application LSA Series pumps High-performance, low-maintenance slurry pumps designed for severe duties over wide range of operating flows Cyclone feed or tailings transfer applications 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

8 LCC Series pumps ZW Series pumps
Horizontal end suction modified volute casing pump. Superior characteristics over wide operating range flotation, gravity concentration, thickening, filtration pumping duties Vertical sump pump. Rugged hard metal with top and bottom suction, open impeller and heavy duty bearing assembly with no submerged bearings. 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

9 HVF Series pumps Patented design to remove air from slurry enabling reduced froth factor in pumping engineering Provides continuous operation without humping slurry throughput. Hydraulic design removes air from the impeller eye while the pump is running. 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

10 Success Story examples
Astana Mining and Metallurgy Success Story examples Section should be the same as in content 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

11 GIW HVF froth pump in Apatite concentrator, Finland
Plant decided to process fine and coarse fractions separately to improve total recovery and grade Fine fraction to be processed separately in Outotec flotation circuit, coarse fraction to be processed in hydrosizer circuit Immediately after start up problems with high froth at fines processing area. Pumpability was disappearing. Air up to 70% of total pulp volume Pumping fluctuates between 50 – 200 m3/h based to flowmeters. In practice fluctuation higher – air disturbed flow meter readings. Pump was competitor’s 8/6 Solution hunting include First: Chemical changes: pine fatty acids, water glass and/or arab gum to kill the froth. Results were encouraging but reagent dosages too high. Second: Mechanical changes to sump design to feed slurry in axial direction and increasing sump wall height. 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

12 GIW HVF froth pump in Apatite concentrator, Finland
Astana Mining and Metallurgy GIW HVF froth pump in Apatite concentrator, Finland Third: Different pump, two size larger pump or air removing pump. Conventional air removal pump from paper industry tested first but maintenance cycle only a week. GIW introduced new patented HVF slurry pump. Installation after plant made modifications to pump base plate and motor connections. Pump was started January 2011 and was immediate success Competitor’s pump was installed at same sump for comparison purpose. After few minutes sump was overflowing when competitor’s pumps was started. After starting GIW pump again, during 10 minutes sump level was stabilized and no overflowing. OT – GIW Froth pumps are now invited to all severe frothy locations in the Finnish phosphate mine. Slides 11 and 12 – should be divided in another way 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

13 BHB Escondida copper mine in Chile
Astana Mining and Metallurgy BHB Escondida copper mine in Chile 2 concentrator plants: Laguna Seca and Los Colorados. Total capacity tpd The problem: Cyclone feed pumps did not achieve maintenance break interval which grinding mills were achieving. Suction liners life <1000 hours Impeller life 1800 hours BHP Escondida wanted solution: 1) meet high safety standard, 2) maintain mill outage schedule and 3) minimize costs GIW responded: Suggestion: GIW suction liner and Impeller was installed to replace competitor parts. Careful part optimization and material selection lead to good results. Suction Liner lifetime improved to 1300 hours and impeller improves also. After first pump was running, BHP was confirmed about GIW quality. Wanted to replace rest of competitor’s cyclone feed pumps After replacements and further improvements, lifetime for pump wear parts currently > 2000 hours (same than mill’s outage) GIW has been provided further expansions since then for Cyclone feed pumping duties in BHP Escondida. Case structure Customer problem \ description Our solution Result for the client 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

14 BHB Escondida copper mine in Chile
Astana Mining and Metallurgy BHB Escondida copper mine in Chile SUMMARY GIW pumps were able to reduce concentrator stoppages and spare part usage. Biggest portion of savings coming from higher availability of plant Smaller part of savings coming from less spare part consumption Total TCO savings above USD per year. Clarification of the bullet points 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

15 Try & Buy campaign to acquire Outotec pumps
Astana Mining and Metallurgy Try & Buy campaign to acquire Outotec pumps Should be the same as in table of content 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

16 Try & Buy for Grinding applications
If plant has shorter maintenance break intervals for cyclone feed pump (or tailings line pumps) compared to concentrator maintenance breaks, Try & Buy campaign can be considered. Typically maintenance break intervals between 2- 4 months in demanding grinding feed application If plant has problem with high spare part consumption, try & buy campaign can be considered. Success / Fail criteria very important to agree, typically 10-50% longer wear parts life time is targeted for GIW pump. 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

17 Try & Buy for Grinding applications
Astana Mining and Metallurgy Try & Buy for Grinding applications For fare situation, the plant and Outotec must agree Limitations from concentrator and from Outotec Scope of Outotec supply Success criteria Fail criteria Future purchases if successful Compensation if fail Commitments between the Plant and Outotec ‘’Boots on the ground’’; ie. deep involvement needed from both parties Regular discussions between the plant and Outotec during testing period, as well as conclusion made together. Allow strong Outotec presence in the plant during campaign. Open information sharing between the Plant and Outotec. Commitments between the Plant and Outotec – customer??? 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions

18 References in Eurasia area
Astana Mining and Metallurgy References in Eurasia area Currently more than 200 pumps running Russia, Mongolia, Ukraine Biggest pumps in tailings line application Mining Companies as: Kovdorsky GOK Erdenet Eurochem Mikhailovsky GOK Metinvest GOK’s Severalmaz And some others… Commitments between the Plant and Outotec – customer??? 6/15/2016 Janne Turunen, M.Sc, Outotec GIW Pumps and Pumping solutions