SM18 RF M7 Bunker Project Status 14th July 2017

Similar presentations


Presentation on theme: "SM18 RF M7 Bunker Project Status 14th July 2017"— Presentation transcript:

1

2 SM18 RF M7 Bunker Project Status 14th July 2017

3 M7 Bunker M7 Valve Box and Transfer Lines:
Contract placed with Cryo Diffusion – Delivery Sept 2017. Engineering completed and approved Delay expected with manufacturing. Interconnection – VB to Service Module: Material ready Installation of Valve Box: M7 valve box and interconnection to Service Module to be installed during SM18 shut down 2017 (End of Sept). Service Box: Contract placed with AS Scientific - Delivery Sept 2017. Delivery 15-Oct-2017 Installation and TL1/TL2 connection -> end Oct 2017 TL1 & TL2 CCCM : Connection to service box: Duration 2 weeks.

4 M7 Bunker Planning: New organigram to present the fellow K Andersen who will joint the technical support of the section

5 RF Tests Issues in SM18 Ph.Gayet (TE-TM 22-Jun-2017)
5: The refrigerator shall exceptionally remain in 80K standby mode during Christmas CV maintenance to be anticipated in SD No EL AUG test in January Additional workload during Christmas break One week stop for Coldbox regeneration during spring 3 : Crab cavity module connection & cryo preparation without contingency before Christmas 4: The module shall leave SM to be installed in BA6 before closing Conflict with magnet and M9 tests NO ROOM FOR RF TESTS 1: No vertical test planned yet 2: One month shift in HIE-Isolde module delivery in M9 > Cold standby of the module during Christmas