Cypress Manufacturing
Quick Presentation: Cypress Manufacturing Multiple Sources, Surge Capacity and Process Automation Reduce Manufacturing Cycle Time and Guarantee Your Supply
2
Cypress Wafer Fabs: Multiple Sources, Surge Capacity Enable Assured Supply
Qualified sources for high-volume products + 50% surge capacity1 enable Cypress assured supply Cypress Minnesota Inc. Products 64k sq ft, 200-mm wafers 0.35- to 0.09-µm production processes 14k wafers per month TrueTouch®: Cypress’s capacitive touch-screen controller CapSense®: Cypress's capacitive-sensing technology for touch and proximity sensing PSoC®: Cypress’s Programmable System-on-Chip USB SRAM HHGRACE (Shanghai) Products Subcontracted partner 240k sq ft, 200-mm wafers 0.35-µm/0.13-µm/0.09-µm processes 100k wafers per month TrueTouch CapSense PSoC USB UMC (Taiwan) Products Subcontracted partner 200-mm and 300-mm wafers 65-nm and 0.13-µm processes TrueTouch USB SRAM 1 Capacity above current Cypress forecast
3
Cypress Turnkey Assembly & Test: Co-Location Reduces Cycle Time
Assembly and test in the same site reduce manufacturing cycle time Every high-volume product has two qualified back-end sources, enabling assured supply Cypress Manufacturing Ltd. (Philippines) Assembly Test Opened 1996 230k sq ft Packages: QFN1, LF2, BGA3 Turnkey from assembly through shipment to customer in 3 days CML: Cypress Philippines ASE (Taiwan) Assembly Test The world’s No. 1 assembly subcontractor 4.7 million sq ft Packages: QFN1, LF2, BGA3 Turnkey from assembly through shipment to customer in 10 days ASEKH :Taiwan JCET (China) Assembly Test Automotive qualified 1.3 million sq ft Packages: LF2, BGA3 Turnkey from assembly through shipment to customer in 10 days JCET: China 1 Quad Flat No-Lead 2 Lead Frame 3 Ball Grid Array
4
Integrated Autoline™ Assembly, Test And Finish Cuts Cycle Time to <2 Days
Autoline Integrated Manufacturing Flow Automated Visual Inspection Points Wafer Input Cell Controller Die Attach Wire Bonders Wafers Mold Die in Tape & Reel Vision Tape & Reel Test Laser Mark Saw Cypress’s integrated manufacturing delivers best-in-class cycle time The world-class Autoline cycle time, less than 2 days, enables Cypress to support a stable 4-week lead time The Autoline flow also supports expedites with very short lead times of no more than 1 week Full automation ensures excellent quality Hardware integration: No human handling and movement from wafer input to tape & reel output Software integration: No human inspection needed to monitor and track at the unit level Process simplification: Improved cycle time and quality
5
Cypress’s Fully Automated Autoline: Exceptional Quality and Delivery
6
Best-in-Class Delivery:
Cypress Delivers > 99% On Time with Lead Time < 5 Weeks On-Time Delivery (OS1) Lead Time 1 Original schedule