Download presentation
Presentation is loading. Please wait.
Published byAmberly Evans Modified over 6 years ago
1
Status and plans for the 3.9 GHz section of XFEL
Redefine “Large Production” here 1 Module 8 Cavities Paolo Pierini, INFN
2
Based on FNAL FLASH ACC39 developments
XFEL 3° Harmonic System 3.9 GHz RF system is right after injector module, before first bunch compressor Based on FNAL FLASH ACC39 developments Max 40 MV required in a 8 cavity module Gradients are well within achieved FNAL cavity/module performances cavity active length m i.e. standard BCP treatment is sufficient for performance P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
3
XFEL Cavity string layout: Coupler kicks
M. Dohlus, DESY Analysis of coupler kicks: one string configuration leads to compensation of offset independent kicks every 2° cavity rotated around longitudinal axis Used in XFEL String Quad at module entrance control both planes P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
4
Status of cavity components
Mockups + 3 Cavity prototypes To develop fabrication/processing capabilities starting from FNAL experience RF design unaltered small variations (flanges/cones, ...) Built, tuned, BCP treated since mid 2009 Waiting testing capabilities in LASA since then... P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
5
Tuning BCP etching parameters with Nb mockup
A factor of 2 between iris and equator material removal accounts for the change of frequencies and coupling Before etch After etch Slater perturbation on the single cell profile that reproduces the 240 um average material removal suggests 180 um at equator and 355 um at iris, factor of 2 confirmed 5.3 MHz/100 um average rate, after optimizing pump pressure P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
6
Field Flatness tuning after fabrication
FF (>90%) within 1 mm length After fabrication (and 800°C) Frequencies (no fms wire) Frequency MHZ Length mm 3HZ01 (+0.7) 3HZ02 (+0.9) 3HZ03 (+0.4) P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
7
Main etch of 3HZ502: Etching Sheet
Three treatments with RF monitoring, for an average removal of 137 um (goal was 3x50 um=150 um) Confirmed etch rate -5.3 MHz/100 um P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
8
Existing 500-700 MHz Vertical Test Facility Cryogenic refurbishment
VT area LASA Existing MHz Vertical Test Facility Cryogenic refurbishment 18 2 K / K less than 1 W in static conditions Adapted VT insert to 1.3 GHz single cells and 3.9 GHz cavities New RF hardware 100 W at 1.3 GHz 200 W at 3.9 GHz Still, clean room, UPW plant and HPR to be qualified for operation P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
9
Qualification of test stand /1
One single cell, 1.3 GHz cavity (1DE15) has been prepared by DESY, to re-measure in LASA, for calibration purposes “as-received”, without opening it, for the VT debugging Eaccmax = 34.7 MV/m Eaccmax = Test at LASA Eaccmax = 38 MV/m Eaccmax = Completed P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
10
Qualification of test stand /2
The next stage, in the following weeks, is to re-assemble cavity 1DE15 in the clean handling area in Milano, verifying all needed tooling and training people Enter in clean room Dismount antennas Perform HPR, dry under laminar flow Reassemble everything Mount on VT and re-test When second test gives similar results than obtained from the cavity “as-received”, we can start testing the 3.9 GHz cavities Expect 3.9 GHz results by spring Ongoing P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
11
Dressed cavity package(s)
Due to alternating couplers requirement and to the position of the 2-phase pipe there are two dressed cavity configurations (left and right) Blade tuner is of the “slim” type, concept derived from all ILC tuner work. Lighter, motor to the side. Beam direction ZROT P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
12
XFEL Cryomodule: transverse layout
Design is “Plug compatible” with Type III+/XFEL modules Identical transverse X-section for all cryo piping Adapts at longitudinal interfaces of standard cryo components Shorter module and string lengths Module part of the same cryo line with the injector module All cryo piping in the same relative position with respect to beam axis Cavity package and support to HeGRP are different P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
13
Longitudinal interfaces preserved
XFEL 1.3 GHz P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
14
Schedule for XFEL 3H cavity/module activities
Test prototypes in VT spring 2011 Procurement of prototype He Vessels and Tuners for the three structures start horizontal tests of prototypes Launch the cavity procurement (including tanks) summer 2011 Complete the module design and launch procurement end 2011 P. Pierini, TTC Meeting, Milano, 28/2-3/3 2011
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.