1 Prototype Interoperation Coordination
4th.Oct.2007 Katsuji Miyashita SMWG CCSDS Meetings Oct. 2007

2 1.1 SLE Service Management
Status of JAXA 1.1 SLE Service Management Development of prototype system in JAXA --> Just finished the development. (Except specific schema of “Modulation Type Option”.) Security method --> Use only XML encryption. --> Need to exchange the Public Key with X.509 Certification by means of . JAXA will provide it by Oct 12. Modulation Type Option --> We agreed in September telecon that the modulation type PCM/PSK-PM is added specially and the new schema is provided by JPL. But JAXA thinks now that the additional specific parameters for ALOS is necessary into the schema, so JAXA will coordinate with JPL about it. SMWG CCSDS Meetings Oct. 2007

3 1.1 SLE Service Management (Cont.)
Exchange ServiceAgreement --> The parameters of Return and Forward will be exchanged by operations of Service Management, though the transfer service is performed only RAF service. --> At this meeting, we would like to coordinate the uncertain items which of JPL/JAXA provide in service agreement. The items (included JAXA proposal) to be provided by JAXA is shown by Oct 12, and the items by JPL is expected by Oct 19. SMWG CCSDS Meetings Oct. 2007

4 1.1 SLE Service Management (Cont.)
Samples --> We will send a actual OEM of ALOS by on Oct 12(TBD), which was generated by Flight Dynamic. Please check its’ contents. --> The following XML samples generated by JAXA/UMR-1 will be sent by on Oct 12, but they are not encrypted. Please check them. ATP-I, ACP-I, CSP-I Requirement --> After all parameters are fixed, we would like JPL to set up the CSSXP by the parameters by around Oct 26. SMWG CCSDS Meetings Oct. 2007

5 -->JAXA proposal is provided on Oct 4.
1.2 SLE Transfer Service The Version of Transfer Service [ B-1 vs R-2(2000) ] --> Agreed to perform only RAF service in Interoperability test and Shadow track test between JAXA/TKSC and JPL/DSN. Communication for the Transfer Service --> Scheduled Line Check on Nov 6. Network Configuration --> JAXA would like to coordinate with JPL directly. ex.) ISDN parameters, IP address, Port Number, etc. -->JAXA proposal is provided on Oct 4. JPL response is expected by Oct 19. SMWG CCSDS Meetings Oct. 2007

6 1.2 SLE Transfer Service (Cont.)
Parameters of RAF service --> We sent the parameter sheet for RAF service to JPL on Oct 4, and it includes the parameters which does not appear in service agreement. --> The parameters is necessary to be fixed before the Interoperability Test. Requirement --> We would like JPL to decide the above parameters of both network and RAF service, and inform to us by Oct 19. SMWG CCSDS Meetings Oct. 2007

7 Table 2-1 Test Schedule (Proposal)
2. Interoperability Test Plan 1) Schedule Table 2-1 Test Schedule (Proposal) SLE Service Management Test Prime UT Oct 30, 2007 (TBD) Backup UT Nov 6, 2007 SLE Transfer Service Test Nov 13, 2007 Nov 20, 2007 NOTE: The working day time is around as follows; JAXA UT JPL UT 2) Confirmation Is it possible to generate the simulated telemetry data (VCDU) at JPL ? Which equipment generate ? (Ref. Figure 2-1) SMWG CCSDS Meetings Oct. 2007

8 2. Interoperability Test Plan (Cont.)
JPL JAXA/TKSC SLE Fwd Service Provider (CCP) Router Router Test Mod ISDN Circuit SLE UGW (TSX-UGW) Voice System Voice System SLE Rtn Service Provider(T DS) End User Simulator SLE SM/CM (CCSXP) SLE SM/UM (Red-1) (UMR-1) Internet CM-TH Figure TEST CONFIGURATION SMWG CCSDS Meetings Oct. 2007

9 3. Schedule JAXA will provide new schedule.
According to set shadow track testing on Jan 2008 by 17th Oct. SMWG CCSDS Meetings Oct. 2007