1 HNC_D Project Management
Resources and Scheduling

2 Project Management Limitations of Schedule Two extreme situations
Time limited scheduling Resource limited scheduling (reference book Denis Lock’s – Project Management)

3 Time Limited Scheduling
Resource levelling or Resource smoothing Earliest and Latest dates ES EF LS LF Duration Total Float Description of Activity

4 Time Limited Scheduling

5 Time Limited Scheduling
Initial Resource Loading Chart

6 Time Limited Scheduling
Serial Scheduling Parallel Scheduling

7 Time Limited Scheduling
Revised Resource Scheduling

8 Time Limited Scheduling
Produce the activity network diagram. Draw the corresponding bar chart or time-scaled network. List the activities in order of increasing float. Draw an initial resource loading chart with each activity scheduled at its earliest start time, building it up serially in the order of the list produced in step 3. Rearrange the activities within their float to achieve a profile which is as level as possible. (This may require a systematic procedure if there are many activities.) Use judgement to interpret and improve on the loading by changing the activities themselves.

9 Resource Limited Scheduling
Parallel Scheduling Activities that can be started

10 Resource Limited Scheduling
Rule 1. Always continue with an activity that has been started until it has been completed, i.e. activities are to be continuous. Rule 2. From among the eligible activities select first the activity that has the earliest date for the latest start time. If several of these activities have the same latest start time then select first the one having the shortest duration. Other finer distinctions may follow this. Rule 3. Never allow a resource to stand idle if there is an activity that could be started. Rule 4. An activity cannot make use of partial resources.

11 Resource Limited Scheduling

12 Resource Limited Scheduling
Activities Scheduled at project start

13 Resource Limited Scheduling
The Resource Limited Schedule

14 Resource Limited Schedule
Produce the activity network and calculate all event times. Tabulate activity data (in any convenient order). For each time period in succession: Find the eligible set of activities Select successively using the rules