Download presentation
Presentation is loading. Please wait.
Published byBenjamin Gilbert Modified over 6 years ago
1
PWWA Conference NRW Project – Salelologa, Savaii Progress Presentation
Seugamaalii Jammie Saena, SWA Managing Director Carlos Mustoni, WLPM Director Tonga, August xxth 2016
2
Introduction Project area water source based in the Palauli Faleata District consisting of 3 villages unmetered since system was built more than a decade ago There was a need to look at the consumption Provide evidence of the amount of water utilised by these villages Evidence used to argue the case with the District and Government that metering was necessary The was a need to extend the coverage area of the source so we could shut down our borehole supplies further down the line.
3
Original Condition
4
First steps
5
First steps: PRV assessment and repair
PRV pressures reduced from 86 to 43m Faleata WTP Daily Flow reduced from 9,304 to 7,456m3 (-20%)
6
First steps: Palaluli villages consumption
FMs were installed in all the villages submains. Villages consumption assessed: it represents 44% of Faleata WTP daily flow
7
Some delays…but keep working
A storm burned out two bore pumps. The IVs were opened until July 2013. System returned to previous configuration (Puapua, Lano, Sapapalii and Lalomalava bores working through a floating valve) Loggers purchased and installed. High pressures in all the North area. Pumping hours started to be reduced to 12hours and later 10h/day.
8
PRV relocation The pressure upstream was 140m and the pressure downstream was set at 89m. It impact in the whole area, from Faleata up to Iva.
9
PRV relocation impact The reduction since July 2012 was +/- 4,170m3/day, 45% of the WTP original flow. Status MNF (12 to 4am, l/s) Daily production (m3) Reduction (%) Original (13-20/7/12)(1) 83 9,304 - Tafua PRV (20-27/7/12) 72 7,456 20 Tafua PRV adj (28/3/14) 60 6,372 14.6 Faleata PRV (3/6/14) 48.5 5,134 19.5
10
Faleata new supply area: from Iva to Lalomalava
11
Faleata 2nd extension until Tuasivi
12
Works and impacts All the extensions demanded big operational and improvement works (new valves, interconnections, service connections improvement, etc.) New PRVs were installed at Tafua and Wharf to reduce the leaks on the area and to allow the extension of the area supplied by Faleata. Lalomalava and Sapapali bores were stopped. Just two bores remain in use: Puapua (8h/day) and Lano activated with a floating valve.
13
Tafua and Wharf PRV impact
PRV reduced to 30m (Ups 50m) flow reduced from 187m3/d to 100m3/d, representing a 46%. Wharf flow reduced from 900m3/day, to 648 and finally to 500m3/day, representing a saving of 44%.
14
Palauli Villages New FMs were installed in all the villages submain as they started to be blocked. The relocation of the PRV had an impact in their daily flow but each one has different extension and CPP, so it was decided to install PRVs in each submain and conduct an individual pressure reduction in each area. All the customers at all the villages started to be metered. The actual supply of 995m3/day represents a reduction of 70% since July 2013. Palauli villages supply represents now 18% of Faleata production (in 2013 it was 50%). Village Average 29/6-13/7/13 Average 20-21/10/15 Average 21-22/10/15 Average 1-2/3/16 WTP Submain 235 108 102 103 Maorist 526 114 94 88 Vailoa 3 120 44 31 35 Vailoa 4 323 173 137 87 Vailoa 5 45 32 22 Vaitoomuli 1 186 89 90 58 Vaitoomuli 2 941 430 345 255 Vaitoomuli 3 126 69 59 53 Faala 1 231 55 49 47 Faala 2 263 128 80 Faala 3 324 217 181 167 Total 3,310 1,472 1,234 995
15
Faleata supply area last extension(until Faga)
16
Faleata 1st Water Balance
The water supply to all the customers (outside Palauli, Tafua, Wharf, and Salelavalu) from Faleata until Sapapalii is 2,358m3/day. It represents 43% of the water produced by Faleata.
17
Following steps Assign the customers from each village to the water supply areas to allow a better NRW study and to identify areas with higher leaks. Replace the existing old PRV at Faleata for a timer PRV to be set in three different downstream pressures: 80m to cover morning and evening peak hours 60m from 10am to 5pm 45m from 10pm to 6am to cover night low consumption
18
Conclusion All villages within this district now metered and billed Success of these works show the importance of pressure management, leak detection, capacity building of staff, political buying and public consultation no matter how unwelcome and unpopular your works are perceived
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.