SPS LS1 Planning meeting (N019) 04/09/13
David Mcfarlane
2
Topics Lifts and Monte-charges. Removal of equipment in LSS1+
TT10 update Works around the CCC (Surface) Planning. False floors open in the BAs E.C.Rs. Access rights and safety equipment Important Information. A.O.B
3
Lift Maintenance Sept/Oct
4
Removal of equipment in LSS1+
The works are pretty much complete! (on schedule!!!!) A HUGE “well done” and “Thank you” to all teams involved.
5
Works still to do before EL start the cable campaign on the 8th October
Scaffolding for Fibre Optic and CV works Fibre Optic campaign starts next Monday. CV works starts next Monday. Labelling and identifying of cables continues Not to be done between the 9th and 23rd September due to fibre Optic works.
6
TT10 update
7
Planning for the next few months around the CCC
9
SPS LS1 schedule Beam on EPC Commissioning tests
Beam off : 16/02/13 Beam on: 13/10/14 Open Access : 27/03/13 Close Access : 27/06/14 Beam on Cool down/RP survey and Magnet tests Cool down NO ACCESS Fibres 18 KV Kicker Survey Civil Engineering in TT10 RF upgrade works Survey RF upgrade works EPC works Cables Survey Survey Kicker Cables Survey EPC works Survey Survey Maintenance General Maintenance General Magnets Magnets Magnets Magnets Kicker Magnets Magnets Cables Magnets 18 KV Magnets General maintenance General maintenance Crab Cavities General Maintenance Cooling tower 863 General Maintenance Survey Vacuum Ring-main Ring-main Ring-main Vacuum Ring-main Septa works Ring-main Vacuum Ring-main Fibres Septa works Ring-main Prep work in LSS1 18 KV General Maintenance Maintenance General Vacuum Vacuum RF Upgrade works Cables Survey Horizontal Vertical smoothing Cool down Limited ACCESS Fibres TT20 pipework 18 KV CV maintenance CV maintenance UA works Civil Engineering Irradiated Cables 18 KV Fibres CV maintenance Fibres Cables Cables Cables 18 KV Cables EL Studies Civil Engineering TT10 Consolidation Cables replacement Septa Civil Engineering Civil Engineering CV studies RF Upgrade works Crab Cavities Civil Engineering Civil Engineering RF Upgrade works Re-install equipment removed for cable works RAL Magnets CV works Fibres Cables Magnets Magnets Magnets Magnets Magnets Magnets Magnets EPC Commissioning tests Vacuum Cold check out & Start-up DSO tests/HV tests Protons to the North Area Protons to LHC Ions to NA61 CV Controls upgrade Re-route Cabling
10
False floors lifted in Surface BAs
Below is a table showing the dates that EL will be pulling cables at each point of the SPS. During these periods large sections of the false floor in these surface buildings will be lifted. Any works in the BA’s that involve lifting of the false floors MUST be reported to the Coordination team BAs Cabling pulling start Cable pulling end BA1 (TS1- works) BA1 (Irradiated cable works) BA1 (Fibre Optics) 29/04/2013 08/10/2013 08/04/2013 02/08/2013 14/02/2014 24/04/2013 BA2 06/01/2014 11/03/2014 BA3 BA3 (Fibre Optics) 27/03/2013 22/04/2014 31/05/2013 06/05/2014 BA4 27/05/2013 12/07/2013 BA5 BA5 (Fibre Optics) 30/09/2013 24/05/3013 11/10/2013 BA6 BA6 (Fibre Optics) 13/5/2013 18/10/2013 24/05/2013 BA7 16/10/2013 07/11/2013 If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first.
11
Engineering Change Requests
Templates and Guidelines for Engineering Change Requests: EDMS: SPS ECR template (in DFS):
12
Current ECR’s for LS1 Removal of AEWB Pick-up from position to 31502 (EDMS No ) RELEASED Removal of a BPWA Pick-up from position to 31101 (EDMS No ) RELEASED Installation of a new Wideband Kickers system in position 32173 (EDMS No ) RELEASED Installation of a new HBW Damper Pick-up in place of BPWA & AEWB 31932 (EDMS No ) RELEASED Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2 (EDMS No ) RELEASED Reinstallation of pump and gauges (Pirani + Penning) in (vacuum sector 150) (EDMS No ) RELEASED Modification LSS1 sectorization (new VVSF + displacement VVSB 11772) (EDMS No v.2) RELEASED Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS. (EDMS No ) UNDER IMPLEMENTATION
13
Current ECR’s for LS1 Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5. (EDMS No ) RELEASED SPS Beam Position Monitoring Prototyping Setup in LSS4. (EDMS No ) RELEASED Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper. (EDMS No ) RELEASED Installation d'un nouveau moniteur de position de type BPCR en LSS2 au (EDMS No ) RELEASED Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel. (EDMS No ) RELEASED Interlocking of Injection Tunnel upstream areas with LHC powering. (EDMS No ) RELEASED Move of BPH to BPH (EDMS No ) RELEASED Optical Fibre Racks. (EDMS No ) RELEASED
14
Current ECR’s for LS1 Removal of old fixed TMP vacuum groups in (EDMS No ) RELEASED BYBPM racks under the SPS dipole magnets as part of the Upgrade of Beam Position Monitors electronics (MOPOS). (EDMS No ) UNDER IMPLEMENTATION Installation de Coffrets d'Alimentation en LSS1 et TT10. (EDMS No ) RELEASED Installation d'un rack de jonction RX11695=TS1 au BA1, afin de limiter les longueurs des câbles à changer lors d'un futur remplacement. (EDMS No ) RELEASED Installation de nouveaux chemins de câbles en LSS1+ et LSS2- du SPS. (EDMS No v.2) IN WORK TPSN replacement in LSS2 of SPS. (EDMS No v.1) UNDER APPROVAL
15
Access rights and safety equipment
Everyone who enters the SPS MUST have the following: Completed the correct courses. Safety course levels 1,2 and 3. Habilitation Electrique. Radiological Protection. Self Rescue Mask Training. The correct access authorisation (via EDH). A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. Helmet plus Light. Please note that the medical service no longer contact you when your medical is about to expire!!!!!!! You will receive an 2 months before informing you that some of your access rights will soon expire. It is up to you to contact the medical service to arrange a medical.
16
Important information
Useful Contact Numbers SPS Coordination Team David MCFARLANE Franck BAIS – James RIDEWOOD Control Room SPS CCC – 77500 TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Elodie Aubert Kurt Weiss (BA1) Coordination Safety Emmanuel Paulat – John Etheridge
17
A.O.B. Don’t forget that Franck and myself have moved office. We are now in B10 (same phone numbers) There are currently 46 IMPACTs that are “LATE”. If you have completed your work then you need to close the related IMPACT. 6 new chariots have been ordered to replace the old ones. Please ensure that you look after these chariots!!! LS2!!!!!! Work has already begun on the planning for LS2. If you are planning on doing any major works in LS2 for consolidation then we need to know about it now.
18
SPS coordination website
\\cernhomeJ.cern.ch\J\jocksoft\Public\LS1 Next meeting 18/09/2013 892-1-B09