1
The Logical Framework as an Implementation and Monitoring Tool
RBEC Environment & Energy Practice Workshop Almaty, Kazakhstan October 2004 John Hough, UNDP GEF BD PTA
2
Reminder: The LogFrame is an Approach not a Matrix
Methodology -including a set of tools- to structure and facilitate: project planning project design project management project performance assessment
3
Benefits LFA contributes to:
structured project design process- logical sequence transparency- clear objectives, side effects participation- ownership, sustainability consistent project strategy assessment of performance- indicators (ex-post & during implementation)
4
Basic Steps and Elements
Problem Analysis Stakeholder Analysis Objectives Analysis Analysis of Alternatives Project Planning Project Planning Matrix (PPM) (the “logframe”)
5
Problem Analysis Establishing “cause and effect” relationships – a “problem tree” “lack of the solution is not the root cause of the problem”! Identifying “lack of knowledge” as the problem means that the solution is already pre-determined: ie. “provide knowledge” Getting people to focus on what they need to do vs. what they want to do is often the biggest challenge in project development Solution Driven Analysis often leads to solving the wrong problem
6
2. “Seeing the wood for the trees”
Lessons learned 1. Doing “good work” or “achieving impact”? 2. “Seeing the wood for the trees”
7
Problem Analysis Stakeholder Analysis
8
Stakeholder Analysis Problem Analysis cannot be done without Stakeholder Consultation. Every stakeholder views the problem from a different angle. Problem analysis and stakeholder identification and analysis are iterative processes, progress in one almost always means returning to the other.
9
Problem Analysis Stakeholder Analysis Objectives Analysis
10
Objectives Analysis What is the project “going after”?
What are the indicators?
11
Alternative Analysis Problem Analysis Stakeholder Analysis
Objectives Analysis Alternative Analysis
12
Alternative Analysis Systematic search for the best project approach.
What outcomes are required to reach the objective? How best to reach each outcome? What outputs are required to reach each outcome? What activities are required to achieve each output? Set up criteria for assessment of alternatives, such as: resources available political feasibility social impact
13
Writing the Objective Tree
14
Fundamental Project Design
Outcome 1 + Outcome 2 + Outcome 3 = Objective
15
Lesson Learned there should be no spare outcomes
nor should there be any outcomes that are not essential for the achievement of the objective
16
In the logical logframe matrix we simply list the outcomes vertically
Objective = Outcome 1 + Outcome 2 + Outcome 3
17
Assumptions Conditions that are necessary for the success of the project, but which are not under the direct influence of the project. Assess conditions according to importance and probability Need to be monitored / risks Pay attention to “killer assumptions” (= need to re-design project)
18
Assumptions vs. Risks Assumptions tend to be positive
eg. “a supportive piece of legislation is passed” Risks tend to negative eg. “increased pressure on a protected area as a consequence of a resettlement programme” Assumptions can be formulated negatively as risks, and vice versa – risks as assumptions Assumptions are generally identified during project design Risks often appear during project implementation
20
Converting Assumptions to Outcomes through Cofinancing
If a condition required through an assumption can be brought under the influence of the project, then it becomes a project outcome. The costs of achieving that outcome would count as co-financing
21
Combining Outcomes and Assumptions leads to the Objective
22
Listing these vertically in a logical logframe matrix we get:
Objective = Outcome 1 + Outcome 2 + Outcome 3 + Assumption 1 + Assumption 2
23
From Objectives to Outcomes to Outputs
24
Similarly these are written vertically:
Outcome 1 = Output 1 + Output 2 + Output 3 + there may be assumptions at this level too!
25
From Objectives to Outcomes to Outputs to Activities
26
3. Basic Steps and Elements Planning Phase Project Planning Matrix (PPM)
27
ie. the logframe matrix combines the vertical and horizontal logic
Objective = Outcomes Assumptions = Outputs Assumptions = Activities Assumptions
28
3. Basic Steps and Elements Planning Phase Project Planning Matrix (PPM)
29
Project Planning Matrix (PPM) Reading /Interpreting the PPM
30
Project Planning or “LogFrame” Matrix is a “Summary” of the Project
WHY the project is carried out (development objective, immediate objectives) WHAT the project is supposed to produce (outputs) HOW the project is going to achieve the outputs (activities) HOW the success of the project can be measured (indicators) WHERE the data can be found (means of verification) WHICH external factors influence the project (assumptions) WHICH inputs are required for the project (inputs/budget)
31
In a logframe we are not very interested in activities
Activities are the means to an end We are interested in “ends” or “impacts” Summarize the activities in the logframe Overloading the logframe with activities is confusing, and also a waste of effort since they are likely to change in the light of project circumstances Activities are detailed in a project management annual activity workplan
32
GEF Projects tend to be “overdesigned”
Lesson learned GEF Projects tend to be “overdesigned” They place far too much emphasis on “activities” There is too much emphasis on measuring or counting outputs and activities
33
GEF Strategic Business Plan Directions and Targets (GEF/C.21/ Inf.11)
The SP’s are what we are “going after” GEF Strategic Priority / Target Project Objective / Target Project Outcomes / sub-Targets Review the impact indicators associated with these
34
The sum of the project outcomes = the project objective
A word on terminology Development Goal = what the project contributes to, but does not on its own achieve Project Objective = what the project is accountable for delivering Project Outcomes = the constituent elements of a project. The sum of the project outcomes = the project objective
35
Project targets are rolled up to achieve the SP targets
x (y%) countries show improvements in management effectiveness (policy, legislation, capacity, budgets) = Improvements in country 1 + Improvements in country 2 etc
36
Putting it all together
MDG 7 GEF Achievements Convention Goals UNDAF Outcomes GEF 3 Outcomes SRF/MYFF Outcomes Strategic Priority Targets = (Development Goal) = SRF/MYFF Outputs CP / CPAP Outputs Project Objective Project Outcomes Project Outputs Project Activities
37
Traditional Logframe Table
Goals/Objectives/Outcomes Key Performance Indicator Verification Means/Data Collection Strategy Assumptions or Risks Increase protected areas of biodiversity in target region from X% in Year 1 to Y% by Year 2 % of target region protected Reduce CO2 emissions from X in Year 1 to Y by Year 2 Reduction in CO2 emissions
38
Results Measurement Framework
Goals/Objectives/Outcomes Key Performance Indicator Baseline (Year 1) Target (Year 2) Target (Year 3) Target (end of project) Verification Means/Data Collection Strategy Assumptions or Risks
39
Goals/Objectives/Outcomes Verification Means/Data Collection Strategy
ie. the Traditional Logframe Matrix and the Results Measurement Framework are easily combined Goals/Objectives/Outcomes Key Performance Indicator Baseline (Year 1) Target (Year 2) Target (Year 3) Verification Means/Data Collection Strategy Assumptions or Risks Increase protected areas of biodiversity in target region from X% in Year 1 to Y% by Year 2 % of target region protected X% Y% Reduce CO2 emissions from X in Year 1 to Y by Year 2 Reduction in CO2 emissions X Y
40
A more objective PIR / APR?
Goals/ Objectives/ Outcomes/ Assumptions & Risks Key Performance Indicator Baseline (Year 1) Target (Year 2) Actual Level Achieved (Year 2) Target (Year x) (Year x) Rating (HS, S, PS, U) Excuses offered Increase protected areas of biodiversity in target region from X% in Year 1 to Y% by Year 2 % of target region protected X% Y% Z% ? Reduce CO2 emissions from X in Year 1 to Y by Year 2 Reduction in CO2 emissions X Y Z
41
Using the logframe as an implementation and monitoring tool
“Seeing the forest for the trees” Focuses on targets and impacts, not activities or outputs Enables us to revisit the “alternatives” and adjust the activities or outputs on a regular basis Adaptive management
42
Putting it all together
MDG 7 GEF Achievements Convention Outcomes UNDAF Outcomes GEF 3 Outcomes CP/SRF/MYFF Outcomes Strategic Priority Targets = (Development Goal) = CP/SRF/MYFF Outputs Project Objective Project Outcomes Project Outputs Project Activities Project Inputs
43
Indicators of What? Level of Objective What it is Examples Indicators
Changes / Impacts Biodiversity conserved Impact Outcomes Attitudes changed Institutions changed Outputs Products / Processes Capacitated people Products / Process Activities Workshops held People trained Inputs $ spent Dollars spent Eguipment supplied Delivery
44
Convergence: outcomes and indicators
State Pressure Response Output Activities Development Goal Marine Biodiversity in Chile Fish Populations Fishing Intensity Area of MUMPA’s RegulationsDemarcationStaffing Decision Making Financial Tools Workshops Training Disbursement Rates Project Objective Increased Fish Populations Project Outcomes Reduced Fishing Intensity Outputs MUMPA’s Regulations Demarcation Staffing
45
Chile Marine Biodiversity Legal Gazettement of MUMPA’s
Scaling Objectives Chile Marine Biodiversity Development Goal MUMPA’s Project Objective Legal Gazettement of MUMPA’s Outcome Legislation Output Legal Drafting Activity Train lawyers Input
46
Objectives of Alternative Projects:
Reduced Fishing Intensity Increased Fish Populations MUMPA’s Regulations Demarcation Staffing Decision Making Financial Tools
47
Indicators of What? Level of Objective What it is Examples Indicators
Changes / Impacts Biodiversity conserved Impact Outcomes Attitudes changed Institutions changed Outputs Products / Processes Capacitated people Products / Process Activities Workshops held People trained Inputs $ spent Dollars spent Eguipment supplied Delivery
48
Good Indicators Indicator is a quantitative or qualitative variable or parameter that provides a simple and reliable basis for assessing change or performance (the objective or outcome). Verifier. Variable or parameter that retains the essential meaning of the objective and that can be measured on the ground. Qualifier. Contribute to describe the verifier allowing to respond to: what, when, where, who Targets/ Baseline - values associated to the verifiers that define how much the objective is planned/expected to be achieved compared to the situation prior to project start. Intermediate targets (milestones) allow assessment of progress.
49
Example of a Good Indicator
Objective: “Conservation of keystone species” Indicator: At the end of the fifth year (qualifier: when) the population sizes (qualifier: what) of species A, B and C (verifier) within the boundaries of the park (qualifier: where) have remained constant (target) compared to X number at project-start level (baseline)
50
Lesson Learned - Procrastination
Project designers defer measuring indicators to the inception phase The inception phase defers measuring indicators to project implementation Project implementation defers measuring indicators to the mid-term evaluation The mid-term evaluation defers measuring indicators to the second half of project implementation Project implementation defers measuring indicators to the final evaluation The final evaluators say “we cannot prove this project has achieved anything”