1 Memorial Hospital Miramar
Bret King Construction Management Spring 2005

2 Project Overview Building Name: Memorial Hospital Miramar
Location: Miramar, Fl (Broward County) Size: Approximately 275,000 Sq. Ft. Project Cost: Approximately $65 million Type: Medical Facility Construction Dates: March 2003 – March 2005

3 Project Overview Primary Project Team Owner: Architect:
Memorial Healthcare Services Architect: Gresham, Smith, and Partners Construction Manager: Centex Construction, Inc Engineers: Smith, Seckman, Reid, Inc. Consulting Engineers

4 Project Overview Key Attributes Mediterranean Architecture
Serene Tropical Landscape Very Large Site Proposed 3-4 Story Expansion All Private Rooms

5 Project Overview Site Plan

6 Agenda Analysis 1 – Insurance Policies
Analysis 2 – Water-Mist Fire Suppression System Analysis 3 – Flexible Building Design

7 Analysis 1 Insurance Policies in the Construction Industry:
Contractor Controlled Insurance Policies (CCIP)

8 Analysis 1 Advantages of using a CCIP:
Broader coverage and higher limits for contractors

9 Analysis 1 Advantages of using a CCIP:
Broader coverage and higher limits for contractors Potential cost savings

10 Analysis 1 Advantages of using a CCIP:
Broader coverage and higher limits for contractors Potential cost savings More comprehensive safety and loss control programs

11 Analysis 1 Disadvantages of using a CCIP:
Additional administrative duties

12 Analysis 1 Disadvantages of using a CCIP:
Additional administrative duties Increased responsibility to ensure jobsite safety

13 Analysis 1 Keys to success Safety!

14 Analysis 1 Keys to success Safety! Experienced CCIP manager

15 Analysis 1 Keys to success Safety! Experienced CCIP manager
Contractor cooperation

16 Analysis 1 Problems/Issues Mechanical Contractor
Did not agree to terms of CCIP Led to…

17 Analysis 1 Problems/Issues Mechanical Contractor
Did not agree to terms of CCIP Led to… Approximately 2 month delay in schedule $750,000 in overtime work to get project back on schedule

18 Analysis 1 Results CCIP Administration Costs: $196,000
Cost savings from elimination of mark-ups: $500,000 Schedule Impact: 2 month delay Overtime Work: $750,000 Total Cost Savings: $-446,000

19 Analysis 1 Solutions Traditional Insurance Program

20 Analysis 1 Solutions Traditional Insurance Program Pre-Bid Meetings

21 Analysis 1 Solutions Traditional Insurance Program Pre-Bid Meetings
Pre-Construction Meetings

22 Water-Mist Fire Suppression System
Analysis 2 Water-Mist Fire Suppression System

23 Water-Mist Background
Analysis 2 Water-Mist Background Originally developed for protection of lumber drying kilns and ships Gained popularity when Halon was deemed environmentally unsafe Used today to protect gas turbines, machine rooms, and ships Also used in computer rooms and laboratories Recently used in the National Gallery of Art in Washington, DC

24 Analysis 2 How It Works Highly pressurized nozzles release water droplets of varying size Mist surrounds the fire and vaporizes, absorbing energy and removing heat from the source Mist expands greatly, forcing oxygen away from the flame

25 Analysis 2 Goal: To determine whether or not it would be advantageous to implement a water-mist system in the computer/data rooms and laboratories in the Memorial Hospital Miramar

26 Analysis 2 Existing System: Traditional pre-action fire suppression system Disadvantages Large amount of water used to suppress fire Larger piping needed to hold water Little smoke control

27 Analysis 2 Proposed System: HI-FOG water-mist system with smoke scrubbing Incorporates sub-floor piping and ceiling piping Sub-floor piping discharges mist in opposite directions causing the smoke to be sucked in and scrubbed Ceiling mounted pipes discharge mist directly into room

28 Analysis 2 HI-FOG System Advantages
Uses only 10-20% of water used in pre-action system Smaller stainless steel piping Smoke scrubbing element Radiant heat blocking

29 Water-Mist vs. Traditional Sprinkler Systems
Analysis 2 Water-Mist vs. Traditional Sprinkler Systems Property Sprinkler Water-Mist Extinguishing No Yes Gas Cooling Radiant Heat Blocking Smoke Scrubbing Safe for People Safe for Equipment

30 Analysis 2 Initial Installation Costs Pre-action: $810,500
Water-mist: $912,000

31 Analysis 2 Initial Installation Costs Maintenance Costs
Pre-action: $810,500 Water-mist: $912,000 Maintenance Costs Pre-action: $ per year Water-mist: $ per year

32 Analysis 2 Conclusion: Due to higher first costs and higher maintenance costs of the water-mist system, the existing pre-action system should be used

33 Flexible Building Design
Analysis 3 Flexible Building Design

34 Analysis 3 Flexibility in building design needed due to:
Rapid Population Growth Emerging Technologies

35 Analysis 3 Goal: To increase the flexibility of the Memorial Hospital Miramar to enable the building to efficiently adapt to the changing needs of the user

36 Analysis 3 Structural Redesign
Existing System: CIP Beams and Pre-cast Soffits Proposed: Flat Slab System with Shear Walls 10” slabs with 3” drop panels at columns 8” shear walls around stairs and elevators

37 Analysis 3 Advantages: Simplified Formwork Added plenum space
Height Reduction Unrestricted placing of partitions

38 Analysis 3 Cost Analysis Existing Structure: $11,121,278
Flat Slab System: $8,221,602

39 Analysis 3 Schedule Analysis Existing System: 26 weeks
Flat Slab System: 23 weeks

40 Analysis 3 Panel Partition Walls Advantages Quick and easy assembly
Reusable Can be taken down and reassembled in other locations Dust free renovations

41 Analysis 3 Cost Analysis Existing Walls: $593,000
Panel System: $566,250

42 Analysis 3 Panel Walls can cut erection time by approximately 13 days
Walls can be taken down and reassembled nearly 2x as fast as the regular wall system

43 Analysis 3 Conclusion Both the flat slab system and panel partition walls can not only save time and money on the project, but also give the building more flexibility to adapt to changing user needs

44 Questions/Comments????