Bond Oversight Committee
2015 Bond Program December 15, 2016
2
Reunion Elementary School
December 5, 2016 2015 School Bond Construction Program Thank you for supporting our students!
3
Reunion Elementary Team
Owner’s Rep Wember, Inc. Architect Hord Coplan Macht Architects Contractor FCI Constructors 2015 School Bond Construction Program Thank you for supporting our students!
4
Schedule Overview Construction Phase July 25, 2016 – June 20, 2017
Temporary Certificate of Occupancy June 21, 2017 Punchlist June/July, 2017 District Move-In July/August, 2017 First Day of School August 21, 2017* estimated date School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
5
Current/Upcoming Project Activities
30 Day Look-Ahead: Construction: Curb & Gutter and Sidewalk Installation Retaining Wall Installation Landscape & Irrigation Rough In Site Electrical Asphalt Paving Light Pole Installation Structural Steel Detailing Exterior Wall Framing Spray Foam Installation Interior Wall Framing Interior MEP Rough-ins School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
6
Current/Upcoming Project Activities
30 Day Look-Ahead, continued: FF&E Selection Process Xcel Gas Coordination Coordination Efforts with Reunion (on-going) School District 27J 2015 School Bond Construction Program Thank you for supporting our students!
7
Interior Framing on 1st Floor
8
Exterior Wall Board