1 Drive-Laser Commissioning Status and Plans
Requirements Where do we stand today? Laser Acceptance Status Laser Commissioning UV on cathode – Injector Commissioning

2 Gun Design for Normal Incidence
Layout of Laser from Injection Mirror to Cathode gun solenoid cathode laser injection cross vacuum valve drawing compliments of R.F. Boyce & T. Osier

3 UV pulse goals IR to UV conversion efficiency > 10 %, 2.5 mJ 255 nm nm, < 2% energy stability 120 Hz, MTBF > 5000 hours Spatial Profile FWHM = 1.2 – 3.0 mm Temporal Profile FWHM = 10 ps (5-20 ps) 90-10 rise and fall times < 1 ps flat-top, < 8% peak-to peak

4 Challenges Hardest Temporal Shape UV conversion Spatial Shape 120 Hz
Synchronization Reliability Characterization Transport Not part of Thales contract

5 Spatial Beam Shaping – Newport Shaper
Converts Gaussian beam input to flat top output High energy conversion - accepts 99.7% of input energy High profile uniformity - 78% of input power is directed into the flat top with 15% RMS power variation Collimated output beam allows use of conventional optics after beam shaping Provides performance over large wavelength ranges GBS-UV H

6 Testing of the Newport Shaper
Input beam Image of the aperture after the shaper Courtesy of John Castro

7 Transport

8 Active Steering Stabilization
F1=200 F2=120 F3=-150 F4=F5=5000 F6=1500 Layout Vacuum cell Zoom L4 Beam shaper L3 L1 L2 Transport tube Table in the tunnel Virtual Cathode Powermeter Steering system L5 Camera Polarizer Photocathode Waveplate Shutter Active Steering Stabilization L6

9 Beam Profile on the Cathode ZEMAX Modeling
Bandwidth 3nm Beam Radius = 1.56mm Side - 4mm

10 Where are we now? - Recent Milestones
July 14 – Laser Tables Installed

11 Where are we now? - Recent Milestones
July 21 – Laser Arrives at Sector 20

12 Where are we now? - Recent Milestones
July 24 – Complete system on table

13 Where are we now? - Today Infrastructure Complete Laser Work
Complete LSS Move laser supplies into rack Setup streak camera Setup cross-correlator Setup UV-FROG Setup spatial diagnostics Infrastructure Complete

14 Where are we now? - Today Streak Camera installed and working

15 Where are we now? - Today Cross-Correlator working

16 Where are we now? - Today TG-FROG working

17 This week and next… Thales working on pulse shape

18 What's Next - Laser Commissioning
LSC Review of Final SOP Oct. 10. Committee approved SOP with very minor changes LSS hardware installed and certified Oct. 26 LSO walkthrough Oct. 27 Thales engineer here for next 2 weeks for temporal shaping As we expected, they are struggling with temporal shaping. We will be deciding how to proceed during conference calls this and next week.

19 What's Next - Laser Commissioning
LSC Review of Final SOP Oct. 10. Committee approved SOP with very minor changes LSS hardware installed and certified Oct. 26 LSO walkthrough Oct. 27 Thales engineer here for next 2 weeks for temporal shaping As we expected, they are struggling with temporal shaping. We will be deciding how to proceed during conference calls this and next week.

20 What's Next - Laser Commissioning
Installation of shaping and transport to begin late-Oct or early-Nov One week down for electrical and cable plant Spatial shaper is in hand Pointing stability lock system has been tested and is ready for installation All other components are in hand Laser table and LSS in Vault Laser door installed prior to transport – Nov 20 Components will be installed and tested in laser bay prior to table moving to vault Support for laser table should be ready for table installation on Nov 28th

21 What's Next - Laser Commissioning
Installation of shaping and transport to begin late-Oct or early-Nov One week down for electrical and cable plant Spatial shaper is in hand Pointing stability lock system has been tested and is ready for installation All other components are in hand Laser table and LSS in Vault Laser door installed prior to transport – Nov 20 Components will be installed and tested in laser bay prior to table moving to vault Support for laser table should be ready for table installation on Nov 28th

22 What's Next - Laser Commissioning
Virtual cathode work requires GTL. UV on cathode two weeks after virtual cathode Laser optimization (temporal profile, stability, etc) will continue until GTL is installed.

23 What's Next - Laser Commissioning
Virtual cathode work requires GTL. Gun can be installed two weeks after GTL installation UV on cathode one week later. Laser optimization (temporal profile, stability, automation, etc) will continue until GTL is installed.

24 End