Download presentation
Presentation is loading. Please wait.
Published byStella Sherman Modified over 6 years ago
2
Owen Hayford Senior Associate Clayton Utz 18 November
AusRail Plus Alliance and Relationship Contracting to Deliver Better Procurement Outcomes Owen Hayford Senior Associate Clayton Utz 18 November
3
Introduction Traditional lump sum construction contract adversarial relationships between Owners and Contractors Relationship contracting has evolved out of a desire to get away from these adversarial relationships
4
Alliances - Core features
Most Alliance Contracts have 2 core features: Radical new approach to remuneration and risk allocation No blame, no disputes
5
Project Alliances vs. Strategic Alliances
Common fundamental characteristic (eg: risk/reward model) Project alliances = one-off, project specific arrangements Strategic alliances = long term relationships which endure beyond any one project
6
Radical new approach to remuneration and risk allocation
Owner pays all direct costs, even if budget is exceeded Owner also pays Gainshare Payment – covers Contractor’s profit and contribution to overheads Gainshare Payment affected by performance against KPIs Share of any cost savings may be added to Gainshare Payment if other KPIs are met
7
Sharing of risks Owner pays direct costs incurred by other participants (even if Target Cost exceeded) But – increased/unforseen costs will cause Final Cost to exceed Target Cost, resulting in reduction in Gainshare Payment
8
Potential cost savings for owners
Internal contract Potential Cost administration Reduced because Savings of non-adversarial expenses nature of contract Internal Profit margin contract and contribution administration to corporate Converted expenses overheads Total Costs Contingency for risks Gainshare Eliminated Total Lump Costs Sum Potentially reduced because Direct Costs of increased innovation Direct Costs Owner's costs under a traditional lump sum contract Owner's costs under a project alliance contract
9
Potential cost savings (cont)
But: No guarantee of lower project cost Owner pays for Contractor’s mistakes
10
Potential cost blowouts
Internal Potential Additional Costs contract administration expenses Internal contract administration Gainshare expenses Profit Margin and contribution to corporate Total overheads Costs Total Contingency for risks Contingency Costs for risks Lump Direct Costs Sum Direct Costs Owner's costs under a Owner's costs under a traditional lump sum contract project alliance contract
11
No blame, no disputes No claims except for wilful default
Ramifications far reaching If one participants fails all participants suffer Owner has no remedy for negligence or poor work practices of other participants Consider variations to no blame, no disputes approach
12
Conclusion Potential benefits/cost savings
Suited to rail sector projects Potential pitfalls need to be considered
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.