1 IceCube Construction Endgame
Jim Yeck IceCube Project Director University of Wisconsin May 5, 2008 IceCube SAC Meeting May 2008

2 IceCube Construction and Operations Organization
National Science Foundation International Oversight & Finance Group IceCube Collaboration & Collaboration Board Spokesperson, T. Gaisser Analysis Coordinator, G. Hill Executive Committee Science Advisory Committee Chair, M. Shaevitz UW Leadership Team Chair, J. Wiley IceCube Neutrino Observatory Principal Investigator, F. Halzen Director, J. Yeck Associate Director, A. Karle Associate Director, R. Paulos Software Coordinator, M. Merck Safety & QA Manager, M. Zernick UW IceCube Center Support Accounting & Purchasing Services (shared with KRC), R. Paulos (A) Education & Outreach, E. Malkus Human Resources, T. Wipperfurth Information Technology, M. Mueller Resource Coordinator, D. Laitsch Trigger, Filter, Transmit Board Chair, E. Blaufuss Project Controls, Engineering & Polar Support R. Paulos Drilling & String Installation T. Hutchings Instrumentation J. Haugen Data Infrastructure Construction G. Sullivan Detector Operations & Maintenance K. Hanson Computing Technology & Support D. Schneider Software & Data Processing M. Merck (A) Project Controls A. Peles Engineering R. Paulos Raytheon Polar Services Company S. Clapp Drill A. Elcheick String Installation T. Ham Logistics T. Hannaford Optical Modules J. Haugen IceTop T. Gaisser Cables/Special Devices J. Baccus Data Acquisition System K. Hanson Data Systems G. Sullivan Verification & Commissioning D. Cowen Pre-Operations J. Yeck Run Coordination A. Goldschmidt Operations & Maintenance M. Krasberg DAQ/Online Processing J. Jacobsen Monitoring I. Taboada Northern Data Center J. Richards Network Security P. Wisniewski Tier 0 (NPX) 2 S. Barnet South Pole System & Test System Maintenance K. Soundarapandian Data Transfer C. McKenzie Filtering & Software E. Blaufuss Primary Data Processing M. Merck (A) Data Integrity C. Rott Monte Carlo Production K. Hultqvist Calibration K. Woschnagg Legend Direction and Reporting Advice and Recommendations Project Support (A) Acting April 1, 2008

3 Original Detector Baseline
70 vertical strings plus surface stations 4,480 Digital Optical Modules (DOM) 60 DOM/string spaced between 1450 and 2450 meters 2 DOM/surface tank and 2 tanks at each surface location Integrate AMANDA Instrumented volume of ≤1 km3 of ice Software and computing required to commission and operate the detector May 5, 2008 IceCube SAC Meeting May 2008

4 Cost & Schedule Baseline
Baseline (Hartill 02/04) Current (04/08) Cost: TPC $271.8 million $276.6 million NSF $242.1 million $242.1 million unchanged Foreign $ million $ million Earned Value: $220.0 million (83%) Contingency: $ 40 million (22%) $ million (24%) Most of the Technical Risk Retired Schedule: 4th Quarter, nd Quarter, 2011 May 5, 2008 IceCube SAC Meeting May 2008

5 2007/08 Season Excellent planning, shared commitment, and consistent positive results Solid basis for future planning 50% of total instrumentation installed M&O mode of operations Safety must continue to be the highest priority Opportunities for improvement will be pursued May 5, 2008 IceCube SAC Meeting May 2008

6 Installation Status & Plans
AMANDA 21 30 29 40 50 39 38 49 59 46 47 48 58 57 66 67 74 65 73 78 56 72 40 strings IceCube string deployed 01/05 IceCube string deployed 12/05 – 01/06 IceCube string and IceTop station deployed 12/06 – 01/07 IceCube string deployed 12/07 – 01/08 IceCube Lab commissioned Planning for at least 16 strings in 2008/09 ( )

7 Drilling/Deployment Performance

8 String Installation Actuals & Plans
IceCube Strings* 04/05 05/06 06/07 07/08 08/09 09/10 10/11 Annual Baseline 1 8 13 18 16 12 Cumulative Baseline 9 22 40 56 68 80 Annual Goal 19 15 6 Cumulative Goal 59 74 Inner Core (AMANDA) Annual Baseline (Proposed) 1 5 Cumulative Baseline 6 * IceTop installation coupled to string installation plans

9 Cost & Schedule Performance

10 Contingency (% of Work-to-Go)
May 5, 2008 IceCube SAC Meeting May 2008

11 Projected Contingency

12 M&O Funding & Tracking

13 Summary Construction project is ~83% complete (earned value)
Confident in the quality of completion plans Conservative baseline plan for additional drilling years Materials and labor costs are well understood Continuous attention to safety and technical performance Operations formally underway Restoring strings as originally planned Plans in place for 80 Strings/IceTop Stations Plan to replace AMANDA with 6+ Strings May 5, 2008 IceCube SAC Meeting May 2008