Estimating and Scheduling CEE 492
Lecture 9 Factors That Determine Variation In Estimates © Awad S. Hanna, PhD, P.E. 1
2
Owner's Purpose of Estimate
Making investment decision in the conceptual stage Negotiate and finalize the contract at the implementation phase To implement cost control measures Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
3
Contractor’s Purpose of Estimate
Determine project cost and profit To Implement cost control measure To develop database that can be used for future project Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
4
Engineer’s Purpose of Estimate
Provide the owner with probable estimate Evaluate alternatives Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
5
Comparison of Contractor’s and Engineer’s Estimator
Contractor’s Estimator Determines actual cost of project for bidding purposes Has detailed company cost data for labor and equipment Knows which construction methods are to be used Has knowledge of actual materials, suppliers to be used and quantity discount prices Engineer’s Estimator Determines expected cost Does not know who will receive award, therefore does not know contractor’s exact resource costs Does not know actual labor rates Must assume probable construction methods to be used Does not know who project supplier will be. Must use local list prices Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
6
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
7
Variation Factors in Estimating
Time We base our estimate on the cost of existing projects that were built in the past Price-level changes over time We need to project costs of future projects Many organizations publish construction cost data on regular basis: US Department of Commerce US Department of Labor ENR Turner Construction Company Handy-Whitman Utilities Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
8
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
9
Variation Factors in Estimating
Time (continued) Cost Indices Published by R.S. Means and ENR Used to update old cost information Uses To update known historical costs for new estimates To estimate replacement cost for specific assets To provide for contract escalation Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
10
Variation Factors in Estimating
Time (continued) Limitations They represent composite data, average of many projects. They fail to recognize technological changes. There is a reporting time lag. Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
11
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
12
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Ⓒ Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
13
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Ⓒ Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
14
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Procedure How to update old cost information to current date cost of new facility = cost of old facility x To predict future cost F = P (1 + i) F = future cost P = present cost i = predicted rate of cost escalation per period n = number of periods (years) new cost index old cost index n Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
15
Variation Factors in Estimating
Location Some factors affecting cost in different locations are: Transport cost Taxes Labor supply and local productivity Codes and local inspection ENR and Means publishes periodically the indices of local construction costs in the major cities Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
16
Variation Factors in Estimating
Location (continued) ENR Regional Index City Cost Index Boston 1120 Chicago 1400 New York 1700 Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
17
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Ⓒ Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
18
Variation Factors in Estimating
Size As the quantity built increases, the unit cost decreases Size Factor = UCM = Unit Cost Multiplier UCM = SF Proposed Size Comparison Size E - 1 Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
19
Table for Unit and Total Cost Multipliers
Table 2.1 Cost Multipliers Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
20
Chart to Convert Unit Prices
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
21
Chart to Convert Total Project Cost
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
22
Variation Factors in Estimating
Shape Bldg B Area =1500ft2 Perimeter = 180ft 40’ 10’ 15’ Bldg A Area = 1500ft2 Perimeter = 160ft 30’ 50’ Wall height = $10 x 160 x 10 = $16,000 = $10.00 of floor area Bldg. A Wall cost = $10 x 160 x 10 = $16,000 Bldg B Wall cost = $10 x 180 x 10 = $18,000 = $11.25 of floor area Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
23
Variation Factors in Estimating
“Learning Effect” Increased productivity by doing repeated work Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
24
Variation Factors in Estimating
Other Factors Hard to quantify but should be evaluated: Quality Soil condition Weather Condition Competition Productivity Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
25
Exercise 2: Student Residence
New Project Desired Capacity = 750,000 sq. ft Expected Completion = End of 2010 Location = St. Louis, Missouri Determine Cost Similar Project Capacity = 360,000 sq. ft Completion Date = Jan 1, 2005 Location = New York, NY Cost = $23,000,000 Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
26
Exercise 2: Student Residence
Cost Index New York Jan 2005 = 2603 Cost Index New York Jan 2009 = 3076 Cost Index St. Louis Jan 2009 = 2390 What is the expected cost in St. Louis? Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
27
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Solution to Exercise 2 Cost Area 1. Unit Cost of NY Bldg (UP1) = = = $63.89/sq. ft. 2. Time Adjustment New York Ratio = = 1.18 Assuming escalation rate at 3% / year Project unit cost at the end of 2006 = F = P (1 + i)n x Time Adjustment Factor = $63.89 (1+0.03)2 x 1.18 = $79.98 $23,000,000 360,000 SF 3076 2603 Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
28
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Solution to Exercise 2 3. Location Jan 2005 Cost Index for NY = 3076 Jan 2005 Cost Index for St. Louis = 2390 Ratio = = 0.78 Base Unit Cost (St. Louis) = $79.98 x 0.78 = $62.38 2390 3076 Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
29
Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
Solution 4. Cost Multiplier (Table 2.1, slide 51) Size Factor = = =2.08 Unit Cost Multiplier = 0.928 Adjusted Unit Cost ($/sq.ft) = $62.38 * 0.928 = $57.89/SF Total Cost = 750,000 SF x $57.89/SF = $43,417,500 Proposed size Comparison size 750,000SF 360,000SF Awad S. Hanna, Ph.D., P.E., University of Wisconsin-Madison
30
Conclusion Questions Questions and Open Discussion ©