C-51 Reservoir ERP/CUP Permitting Status
2
Issued to PBA with operations by SFWMD
DEP Environmental Resource Permit Issued to PBA with operations by SFWMD Permit Issued in April 2014
3
CUP Application Submitted to DEP - September 5, 2014 Review by DEP Joint Permit PBA/SFWMD
4
Interconnected Reservoir and FEB
5
Permit Request 50 year Permit Certainty for PWS 35 MGD Offset Credits Service Area Inflow Allocation
6
Rainfall Period Of Record for Permit
7
Offsets based on 1 in 10 Drought Scenario
Consistent with PWS CUP Process
8
12 month duration beginning in June
1 in 10 year Drought Event 12 month duration beginning in June
9
Consistency with CERP/Regional Availability/Restoration Strategies
SFWMD
10
C-51 Reservoir Sources - L8 excess - M1 Basin
Consistent with: -CERP -Regional Availability -Restoration Strategies SFWMD
11
Assurance – Water Availability for 1 in 10 Year Drought as Alternative Water Supply
12
Water Availability from C-51 Reservoir in 1 in 10 year Drought
13
POR - Water Availability from C-51 Reservoir
14
35 MGD Demand Delivery
15
35 MGD as Regional Availability Offset
42% Reduction in flow to Lagoon
16
Eastern Conveyance Route To Lower East Coast
- No expected Conveyance losses through LWDD
17
Working with Broward County/SFWMD on
Conveyance in Broward County
18
Monitoring/Calibration
Status - Request for Additional Information Monitoring/Calibration Participating Utilities - Letter of Intent/Permit Mod End User Discussions with WMD Impact assessment for Surficial Use WMD will entertain the issuance of long term permits for the baseline/alternative water supplies for participating utilities Long Term Permits > 35years Based on Projected Demands
19
Questions ?