1 TSC Update at December Board Meeting

2 TSC Update Colorado 2.0 & 3.0 Colorado 2.0: Release slipped from October 27 to Nov 10 to accommodate resolution of a problem with the Fuel installer Release contents: 2 scenarios TripleO ISO Fuel ISO (x86) Joid repo (git clone command) Documentation No changes to Compass ISO or Fuel ISO for ARM Colorado 3.0: Software download page will be updated today Release contents: 19 scenarios Includes previously unreleased fd.io scenarios TripleO ISO Fuel ISO (x86) Fuel ISO (ARM) Compass ISO No updates to the Joid repo OPNFV Confidential

3 Danube Release Scheduled for release March 27, 2017
41 projects have expressed intent to participate and have submitted release plans (MS1) 58 scenarios have been declared Risks New installer, Daisy4NFV, has not yet met MS3 (integration with OpenStack on OPNFV CI) This has also created a risk for the Escalator project, which is exclusively dependent on Daisy for deployment The Movie, Orchestra, and Opera projects have not yet met MS2 (test requirements) OPNFV Confidential 3

4 TSC action point #1: OPNFV architecture
From board minutes: “There was a consensus that the TSC should develop an architectural framework and map OPNFV release scenarios to the framework. This artifact could be a vehicle for communicating OPNFV’s value and progress to the industry and also as an internal tool to measure against goals. Mr. Tallgren took an action item to provide an update on this artifact during the December Board meeting.” OPNFV Confidential 4

5 Status of OPNFV architecture
Initial draft exists Next steps discussed in TSC meeting on December 6th Link here (to be updated) OPNFV Confidential 5

6 TSC action point #2: Danube priorities
From Board meeting minutes: Mr. Richomme thought that it is important to provide a technical vision and priorities for future releases to the technical community via a whitepaper. This would also be a good way to communicate planned activates from Infrastructure and Testing Working Groups, and Mr. Degirmenci added that this could be a good vehicle to highlight resource/support needs to TSC & Board. OPNFV Confidential 6

7 Status of Danube priorities
Priorities have been discussed in Infra and Testing working groups This has also been discussed in the technical call and TSC call Responses from the working groups and feature projects are in the Etherpad and in edited form in the OPNFV wiki page OPNFV Confidential 7

8 New projects Rescuer was discussed in technical community call on Nov. 3rd, no updates OpenRetrieve was announced on Nov. 21; discussed on technical community call on Dec. 1 Not yet ready for approval Focus on containers OPNFV Confidential 8

9 Other technical activities
Common naming strategy for scenarios and common installer format proposals exist and have been discussed Discussions will continue in the Plugfest/Hackfest Common installer format would allow to describe a POD in a single configuration file and then use any installer OPNFV Confidential 9