GENESYS Redevelopment Strawman Proposal
March 17th, 2016
2
What are the Questions? What is the probability that the region will have to take an emergency action to keep the lights on in 5 years? Do we have enough resources? Are they sufficiently flexible? What actions or decisions impact the probability that the region will have to take emergency actions?
3
What are the Challenges?
Long-term and Short-term Load Forecast Error Water Run-off Forecasts Error Demand Response Energy Storage Potential Coordinated Hydro Capacity Thermal Operating Reserves Dynamic Hydro Reserves Automated Markets
4
Power System Planning What is an adequate system?
What is an economic solution? Are these confounded?
5
Proposal – Coordinated Resource Dispatch
Value of stored water – price of changing hydro operations Extra-regional market impacts on regional dispatched resources Variable generation and must-run impacts on regional dispatched resources
6
Proposal – Multi-stage Unit Commitment
Complete integration of an hourly water-based hydro dispatch and variable generation forecasts with thermal market-based unit commitment
7
Proposal – Multi-stage Unit Commitment
Monthly Expected Operation Weekly Forecast / Initial Unit Commitment Day-Ahead Forecast / Unit Commitment Hour-Ahead Forecast / Dispatch Schedule After the Hour True-up on Fuel and Reserve Deployment
8
Basic Production Cost Model
Monthly Expected Operation Weekly Forecast / Initial Unit Commitment Day-Ahead Forecast / Unit Commitment Hour-Ahead Forecast / Dispatch Schedule After the Hour True-up on Fuel and Reserve Deployment
9
Advanced Production Cost Model
Monthly Expected Operation Weekly Forecast / Initial Unit Commitment Day-Ahead Forecast / Unit Commitment Hour-Ahead Forecast / Dispatch Schedule After the Hour True-up on Fuel and Reserve Deployment
10
Proposal – Hydro Supply Forecast Error
Operate consistent with forecast hydro rather than observed hydro Capture impacts of water run-off uncertainty in volume and timing
11
Proposal – Hourly Hydro Dispatch by Project
Improve hydro capacity contribution estimates by including hourly water routing logic
12
Proposal – Integrated Storage into Dispatch
Include storage into dispatch model with decisions on when to store, generate or take no action
13
Proposal – Simulated Load and Renewable Forecast Error
Simulate operations based on forecast and correct for error in subsequent commitment stages
14
Proposal – Incorporate Reserve Requirements
Simulate allocation and deployment of reserves on resources including hydro, thermal, demand response, etc.
15
Proposal – Direct Conservation Input
Integrate uncertainty of conservation achievement into long-term load forecast and error estimation