Download presentation
Presentation is loading. Please wait.
1
EWG Study Tour, Galway, 18/09/2006
Cost Benefit Analysis EWG Study Tour, Galway, 18/09/2006
2
Structure What is Cost Benefit Analysis (CBA)? Process Issues in CBA
Some key features Where is it used? Process Issues in CBA When is it done? Who does it? Identification of costs and benefits externalities
3
Structure (continued)
CBA in different sectors Transport (worked example) Environment Productive investment Risk and uncertainty Discount rate Measures of project benefit Conclusions Group exercise
4
What is CBA? A project appraisal technique
Used to assess net value of project to society And/or to rank competing projects within programme The cost-benefit analysis question Would society be better-off? Do economic benefits exceed cost of resources?
5
CBA: Key Features Scope: all costs and benefits Option analysis
Quantification and monetization Technique of choice for appraisal of large public investment projects But other techniques often necessary Financial analysis, CEA, MCA
6
Where is it used? Policies, programmes or projects (UK Green Book)
Project level is main use Mandatory for EU projects >€50 mn. Infrastructure Large productive investment Often used in conjunction with other techniques
7
Process Issues: Timing
CBA should support decision making Do CBA before political commitments made! But not before project specification is clear May need to re-do as more information becomes available or if costs increase
8
Who does the CBA? Should not be project sponsor
Ideally commissioner should be independent of project sponsor Or CBA methodology should be subject of external review CBA can be manipulated!
9
Identification of Costs and Benefits
First step is to identify costs and benefits Should be based on programme or project objectives/rationale Only include those arising as a consequence of project proceeding Include costs associated with any benefits Key issues in estimation Base cba on realistic, not optimistic, projections Don’t take project sponsors view at face value Consider possibility of displacement Consider likelihood of cost overruns
10
Externalities Externality?
A benefit which third party does not pay for Or a cost for which they are not compensated Often provide justification for public investment Examples Spillover effects Congestion or pollution effects Significant for transport + environment projects time savings for transport projects pollution reductions
11
CBA in Transport Sector
Main benefits Time savings (based on wage rates) Accident savings (insurance and police costs) Vehicle operating cost savings Emission reductions Costs Land acquisition Construction Maintenance
12
CBA in Environmental Sector
Investments are EU directive-driven Difficult to put monetary value on benefits Cleaner water? Less pollution of rivers and lakes? Willingness to pay concept Can estimate value from behaviour Based on data from other countries In practice, CEA or basic CBA models used
13
CBA for Productive Investment
Benefits include additional employment and incomes Direct Indirect Induced But labour resources have a cost Concept of shadow or opportunity cost of labour Value of resource in next best alternative use Market prices normally the best measure of opportunity cost
14
Productive Investment: Treatment of Employment
Shadow cost depends on were resources previously unemployed? regional unemployment rate skill levels etc. International evidence would suggest minimum of 50% shadow cost i.e. net benefit only 50 per cent of gross benefit 80% minimum now used in Ireland Shadow wage rate for Romania?
15
Risk and Uncertainty Project outturns always differ from ex-ante estimates Optimism bias Risks Uncertainties Need to address these factors in appraisal At preliminary appraisal stage Need to adjust costs and benefit assumptions On basis of experience with comparable projects
16
Discount Rate Use to convert future values into present value terms
Equivalent to social time preference rate Don’t use to take account of risk and uncertainty Currently 4% (real) in Ireland 3.5% in UK Romania?
17
Measure of Project Benefit
Need summary measures of project benefit Net Present Value (NPV) Internal Rate of Return (IRR) Benefit-Cost ratio (BCR) No one right answer Sensitivity analysis Check impact of changes in key assumptions Identify “switching values”
18
Concluding Comments CBA an important decision making tool
Properly used can help ensure better use of EU funds But cba technique can be abused national guidelines needed shadow wage discount rate And possibly central source of expertise
19
Group Exercise Suppose Tourism Ministry is sponsoring a proposal to allocate structural funds to the construction of a new international Conference Centre in Bucharest What would be the likely benefits and costs of such a proposal? How might these be estimated in general? In reviewing the appraisal, what should the Ministry for Finance be looking out for?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.