Download presentation
Presentation is loading. Please wait.
Published byUrsula Johns Modified over 6 years ago
1
EFFECTIVE EROSION AND SEDIMENTATION CONTROLS FOR IN-CHANNEL PROJECTS
Written By: RICHARD L. SNYDER, CPESC RESOURCE CONSERVATIONIST DAUPHIN COUNTY CONSERVATION DISTRICT
2
“Financial and Other Support for this Project is Provided by the Pennsylvania Association of Conservation Districts, Inc. Through a Grant from the Pennsylvania Department of Environmental Protection Under Section 319 of the Clean Water Act, Administered by the U.S. Environmental Protection Agency.”
3
CONSIDERATIONS APPROPRIATE CHAPTER 105 PERMIT(S) PROJECT SCHEDULING
Obtained from DEP (or Delegated CCD) Designs shall Adhere to Permit Conditions PROJECT SCHEDULING Low Flow Seasons BASE FLOW DIVERSION Minor Stream Channels (Normal Flow Width < 10’) Major Stream Channels (Normal Flow Width > 10’) PROJECT STABILIZATION EQUIPMENT STAGING Top of Bank Temporary Crossing / Causeway MATERIAL STAGING / STOCKPILING Outside Channel Floodway PUMPED WATER Filtered Prior to Discharge into Surface Waters
4
PROJECT SCHEDULING LOW FLOW SEASONS??
5
PROJECT SCHEDULING LOW FLOW SEASONS!!
6
BASE FLOW DIVERSION BYPASS CHANNEL WITH NON-EROSIVE LINING
Figure 3.9 RIGID OR FLEXIBLE PIPE FLUME THROUGH A WORK AREA Figure 3.10 TEMPORARY COFFERDAM AND PUMP BYPASS AROUND IN-CHANNEL WORK AREAS Figure 3.11 IN-STREAM COFFERDAM DIVERSION Figure 3.12
7
BYPASS CHANNEL WITH NON-EROSIVE LINING
FIGURE 3.9, PAGE 44 TEMPORARY BYPASS CHANNEL SHALL BE LINED WITH A GEOTEXTILE PROTECTIVE LINING (MINIMUM) < 3 DAYS, NORMAL BASE FLOWS > 3 DAYS, BANK-FULL FLOW CONSTRUCTED DOWNSTREAM UPWARD
8
BYPASS CHANNEL WITH NON-EROSIVE LINING
THE GOOD…
9
BYPASS CHANNEL WITH NON-EROSIVE LINING
THE BAD…
10
…THE UGLY
11
RIGID OR FLEXIBLE PIPE FLUME THROUGH A WORK AREA
FIGURE 3.10, PAGE 45 SIZING: NORMAL FLOW DEPTH IN PIPE (d) < OR = ½ DIAMETER OF PIPE (D)
12
RIGID OR FLEXIBLE PIPE FLUME THROUGH A WORK AREA
13
TEMPORARY COFFERDAM AND PUMP BYPASS AROUND IN-CHANNEL WORK AREAS
FIGURE 3.11, PAGE 46 < 2 WEEK DURATION PUMP INTAKE Coffedam Constructed to Impound Water NO Excavation for a Sump Area Within the Stream Channel
14
TEMPORARY COFFERDAM AND PUMP BYPASS AROUND IN-CHANNEL WORK AREAS
15
TEMPORARY COFFERDAM AND PUMP BYPASS AROUND IN-CHANNEL WORK AREAS
16
IN-STREAM COFFERDAM DIVERSION
FIGURE 3.12, PAGE 47 VARIOUS TYPES Sandbag Diversion Dam / Cofferdam Jersey Barrier Cofferdam CONFORM TO MANUFACTURER’S SPECIFICATIONS
17
IN-STREAM COFFERDAM DIVERSION
18
PROJECT STABILIZATION
ALL DISTURBED AREA(S) WITHIN CHANNEL SHALL BE STABILIZED PRIOR TO BASE FLOW BEING RETURNED TO CHANNEL
19
EQUIPMENT STAGING WHEREVER POSSIBLE, EXCAVATIONS SHALL BE DONE FROM TOP OF BANK… EXCEPTION: If Mature Trees Need to be Removed to Access Channel
20
EQUIPMENT STAGING …NOT FROM WITHIN CHANNEL
NOT POSSIBLE, TEMPORARY CROSSING / CAUSEWAY MAY BE USED
21
TYPICAL CAUSEWAY FIGURE 3.8, PAGE 43 PROJECT COMPLETION Removed
All Channel Entrances Restored to Pre-Construction Configurations Stabilized
22
TYPICAL CAUSEWAY
23
MATERIAL STAGING / STOCKPILING
ALL EXCAVATED CHANNEL MATERIALS STOCKPILED OUTDE CHANNEL FLOODWAY APPROPRIATE SEDIMENT BARRIER SHALL BE INSTALLED / CONSTRUCTED BETWEEN STOCKPILE AND STREAM CHANNEL
24
PUMPED WATER SHALL BE FILTERED PRIOR TO DISHARGE INTO SURFACE WATERS
Pumped Water Filter Bag Sump Pit Other Sediment Trapping Best Management Practice (BMP)
25
Q&A / PROGRAM EVALUATION
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.