1 School Improvement Bond Projects
Update: April 26, 2016

2 Major Projects Schedule:

3 Cross High School Addition & Renovations Guaranteed Maximum Price (GMP): $3,027, Actual Construction Cost: $2,896, Project Savings: $128,766.75 Gym Renovations New Auditorium New Media Center

4 Goose Creek HS Additions & Renovations GMP: $26,742,675
Goose Creek HS Additions & Renovations GMP: $26,742, Project Budget: $33,247, Estimated Completion Date: August Add: 124,520 Square Feet Completion dates: A – Completed Oct 2015 B – Completed Feb 2016 C – Completed Aug 2015 D – Completed Jan 2016 E – Demo completed Feb 2016 F – Demolish existing buildings 500, 600, 300 and installation of new bus loop to be complete in Aug 2016. B C F D A F F E Ongoing key work items: A – Complete B – Complete, Exterior Punchlist in progress D – Complete E – Building removed F – Abatement complete, phased demolition began on 4/18/16 and will continue June 2016

5 Goose Creek HS Additions & Renovations
Building B – New Science Lab Building B – Exterior Elevation

6 Goose Creek HS Additions & Renovations
Abatement/Demo Schedule Abatement Start End Duration LA Cafeteria 3/12/2016 3/23/2016 11 600 4/5/2016 13 500 4/6/2016 4/18/2016 12 300 4/19/2016 4/26/2016 7 200 6/1/2016 6/3/2016 2 Demo 4/11/2016 4/25/2016 5/7/2016 5/30/2016 6/10/2016 6/13/2016 6/18/2016 5 Old 600 Wing Demolition Rooftop Demo View Old 600 Wing Demolition

7 Philip Simmons ES/MS Approved GMP : $38,249,567 Overall Project $45,000, Completion Date: August ,000 SF capacity of 1,400 students AC F D E B G Aerial photo dated Area A & C – Kitchen, Cafeteria/Multipurpose & Music Rooms Area B & G – Middle School Area D & E – Elementary School Area F - Gym

8 Philip Simmons ES/MS Ongoing Activities:
Area A- Wall & floor finishes are complete. Kitchen equipment installation ongoing. Area B, C, D & E – Terrazzo / VCT floor finish, casework, and door installation in progress. Area C- Ceiling grid & lighting installation complete. Painting in progress Area E & G- Drywall finishing and painting are in progress. Area F- Roof panel installation in progress. Site Work-Grading, stone base & curbing installation in progress at both parking lots. Area A Kitchen Equipment Installation Area A Kitchen Equipment Installation

9 Philip Simmons ES/MS Area F – Gym roof steel (Drone photo)
Area C – Multipurpose Room Painting North (front) elevation of Elementary school Area D-Bus Loop Area F – Gym roof steel (Drone photo) Area E – Media Room Sheetrock / Painting Area F-Gym Steel Framing

10 Philip Simmons ES/MS Ceiling grid, lighting and terrazzo completed in Area B corridors North, primary parking lot for the Elementary School stoned and prepared for curb and gutter. Cabinets and VCT flooring in Middle School Project Room-Area B

11 Philip Simmons High School Approved GMP: $69,472,615 Project Budget: $83,793,851 Completion Date: August ,000 SF with capacity of students Locker rooms Gym 9th Grade Academy Kitchen Cafeteria Entry Loop Administration Auditorium Academy Building Aerial dated

12 Philip Simmons High School
CMU installation and steel erection is ongoing in the 9th Grade Academy, Gymnasium & Cafeteria. Theater & Admin Area-Foundation footing preparation is in progress. Athletic field site preparations are in progress. Site infrastructure installation in progress that includes storm drainage and utilities. Area G- Gym Entrance Area E – Tech Forest Area F & G Kitchen / Gym

13 Philip Simmons High School
9th Grade Collaborative Space Area F- Cafeteria CMU Installation Area G- Gym Steel Roof Framing

14 Foxbank Elementary School Construction Budget: $16,474,597
Foxbank Elementary School Construction Budget: $16,474, Project Budget: $22,357, Completion Date: August ,000 SF capacity of 900 students Foxbank Elementary School site The elementary school in Foxbank Plantation is in progress of the due diligence phase. While jurisdictional wetland determination is in progress, surveying and geotechnical investigations are scheduled if not in progress The Pre-K through 5th grade school will begin schematic design for the 780 students as soon as these due diligence efforts are complete. The project is scheduled to be completed and opened August 2018.

15 Howe Hall Aims/College Park Middle School Roof Screening Projects Construction Cost: $474, Completion Date: April 2016 Infinger Bond project to provide architectural screening to conceal roof-top mechanical equipment. Both projects are complete and in punch list phase College Park Middle screen is perforated metal panels with a custom lettering and logo Total length of screen wall ≈ 370 feet (Left) Front view of school (Left) Front view of school (Right) Front view of school

16 Visitor / Staff Parking
Tanner Foster Creek Area Elementary School GMP: $26,742, Project Budget: $33,247, Estimated Completion Date: August Add: 124,520 Square Feet HGR H.G. REYNOLDS COMPANY, INC. Buffer Closed on property April 22nd. Nationwide permit submitted on March 18, 2016 30% SCDOT and OSF Site drawings are in progress Conceptual exterior elevations are in progress Property Line TOTAL ACREAGE = 21.44 Wetland = 2.16 Acres Buffer = 2.81 TOTAL Developed School Site = Acres School = Acres Easement = 1.11 Acres CAR LOOP Wetlands Future Residential Properties FD Access Visitor / Staff Parking Pre-k/K Play Drainage Easement 1st-5th Grade Play Wetlands Visitor Parking Lift Station BUS LOOP Buffer SERVICE Utility & Infrastructure Easement Detention Detention WILLIAMS LANE Widening

17 1st – 5th Playground / Playfields
HGR H.G. REYNOLDS COMPANY, INC. An Educational Campus at the: NEW TANNER / FOSTER CREEK AREA ELEMENTARY SCHOOL Hanahan, South Carolina STAIR Multi-Purpose, and Cafeteria/Kitchen Prominent Location High Bay Space Secure After-hours Access and Outdoor Areas Dining Room to seat 1/3 of Ultimate Student Population Locate for Arrival and Dismissal Access to Nearby Outdoor Play Areas Service Bus Entry Kindergarten Play Yard Central Services Sp.Ed. Speech KITCHEN Teach Wk. STAIR Food Prep Serving F. 1st – 5th Playground / Playfields M. Music and Art Art Classroom with Access to Outdoor Space Music Located near Performance Platform 1st GRADE ACADEMIC WING DINING Operable Wall MUSIC KINDERGARTEN WING Administration, Clinic, & Guidance Readily Identifiable Front Door Secure and Controllable Entry Points Prominent View and Visibility PMD/ ED SC MULTI-PURPOSE Kindergarten Play Yard OPEN COURTYARD MUSIC PMD/ ED SC Platform CLINIC Porch Main Entry SRO Security Vestibule Elev. Central Stair Pre-K / Kindergarten Wing & Special Education (6) Kindergarten Classrooms, (2) Pre-K Classroom, (1) Teacher Work Room Exterior Storage at Kindergarten Play Yard Special Education – (2) Self Contained Classrooms, (1) ED Sp. Ed., (1) Speech Computer Media Center Prominent and Central Location to Academics Located for Secure After-hours Access (1) First Floor Computer Lab, (1) Second Floor Computer Lab ART Security Vestibule ART Wk. Rm. ADMIN./Guid. MEDIA CENTER First Grade Academic Wing (7) 1st Grade Classrooms, (1) Classroom Flex 1st Grade Classroom with Individual Toilets Teacher Work Rooms and Distributed Admin. Stair and Elevator Location Outdoor Art Conf. Car Pick-up / Drop-off OVERALL FIRST FLOOR PLAN

18 HGR H.G. REYNOLDS NEW TANNER / FOSTER CREEK AREA ELEMENTARY SCHOOL
COMPANY, INC. An Educational Campus at the: NEW TANNER / FOSTER CREEK AREA ELEMENTARY SCHOOL Hanahan, South Carolina STAIR 4th – 5th GRADE WING Teach. Wk. STAIR Sp. Ed SC Teach. Wk. 2nd – 4th GRADE ACADEMIC WING OPEN COURTYARD (Below) Central Stair Sp. Ed SC Second Grade Academic Wing (5) Classrooms, near Group Toilets Located Near Stairs and Elevator Teacher Work Rooms and Distributed Admin. Elev. Computer Resource AP Third, Fourth, and Fifth Grade Academic Wing (5) Classrooms per Grade Level Group Toilets Teacher Work Rooms and Distributed Admin. Stair and Elevator Location (2) Special Education Classroom, Self-Contained (1) Resource Room OVERALL SECOND FLOOR PLAN

19 Berkeley Education Center – Phase 1 Stabilization Project Estimated Stabilization Budget: $2,084, Estimated Completion Date: August 2017 Building Study Determinations: Existing structural elements do not meet life-safety code distribution criteria. Existing stairwells do not meet the required fire separation rating. Exterior walls need mortar repointing & full cleaning. Existing interior masonry walls require vapor barrier treatment for moisture control. New sprinkler system installation required to meet building code occupancy requirements. New fire alarm system installation required to interface with new sprinkler system. All spaces including entry/exits and restrooms require upgrades to meet ANSI requirements. Front Entry

20 Berkeley Education Center – Phase 1 Stabilization Project
Architect’s Recommendation is to move forward with stabilization to prevent continued deterioration of the building by the following: Demo existing site utilities and re-route new site utilities including water for fire service Demo unusable rear additions Selective demolition of interior to fully expose structure Salvage and restore any significant interior materials Masonry restoration Roofing replacement Window replacement Fire protection line and riser Minimal temporary power Site surveys, hazardous surveys and abatement design Intent is not to occupy the building, but to stabilize the building Women’s Restroom Window condition Staff Toilet 1st Floor Corridor

21 Berkeley Education Center – Phase 1 Stabilization
Demo Scope of Work: Interiors of existing building demolished back to bare studs, ceiling joists, and floor sheathing Existing stairwells to be demolished with new shaft walls constructed for 1-hour separation All existing doors and windows replaced with exception of front entry New entry stairs and ramps Repoint 100% exterior masonry New mineral batt insulation Remove existing roof down to deck, install new barrier and metal standing seam roof Provide new gutter and downspouts along rear of building

22 Berkeley Education Center – Phase 2 Upfit Project
Scope of Work: 1st Floor Separate secured entry 5 Head Start Classrooms Administrative Area Health Room Multipurpose Room with small catering kitchen Conference Room to serve as Committee or Executive Session area 2nd Floor Elevator to second floor 6 adult classes Group toilets Break/Vending Area ADULT ADULT ADULT ADULT ADULT ADULT BREAK KITCHEN HEAD START MULTIPURPOSE CONF. HEAD START HEAD START WORK ENTRY ENTRY HEAD START HEAD START RECEPT. ADMIN

23 @ Webinars & Live Events Questions? Questions? Questions?
Extend the life of valuable content @ Invitations Webinars & Live Events Questions? Questions? Questions?