Presentation is loading. Please wait.

Presentation is loading. Please wait.

CLIC Civil Engineering Update

Similar presentations


Presentation on theme: "CLIC Civil Engineering Update"— Presentation transcript:

1 CLIC Civil Engineering Update
Matthew Stuart – John Osborne SMB-SE-FAS CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

2 Reminder – Summary From 05/05/2017
380GeV, 1.5TeV and 3TeV machine layouts drawings require updating. Develop new engineering drawing for the Klystron 380GeV machine. Update the existing IR layouts to show proposed changes. Continue CLIC-TOT development – Stage 1. Understand the difficulty's with both a single and double tunnel Klystron design. A detailed cost estimate for infrastructure to be produced and work together with ILC on areas of synergy CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

3 Civil Drawing Update Updates: 380 GeV Layouts and tables.
1.5 TeV Layouts and tables. 3 TeV Layouts and tables. IR Region plan and cross section. Shaft locations. 380 GeV Drive beam gallery. CLIC tunnel longitudinal section. Klystron Single tunnel section. TBM Single tunnel Section CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

4 Civil Drawings Update (380 GeV)
Reduced the length of the BDS to 1.9km Main Beam Turnarounds relocated. Shaft 2 and 3 relocated to the end of the 380 GeV tunnel. “Tunnel lengths” and “Site Lengths” updated. Extra shaft added to the IR service cavern and 2nd service cavern removed. only for 380 GeV First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

5 Civil Drawings Update (380 GeV)
Reduced the length of the BDS to 1.9km Main Beam Turnarounds relocated. Shaft 2 and 3 relocated to the end of the 380 GeV tunnel. “Tunnel lengths” and “Site Lengths” updated. Extra shaft added to the IR service cavern and 2nd service cavern removed. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

6 Civil Drawings Update (380 GeV)
Reduced the length of the BDS to 1.9km Main Beam Turnarounds relocated. Shaft 2 and 3 relocated to the end of the 380 GeV tunnel. “Tunnel lengths” and “Site Lengths” updated. Extra shaft added to the IR service cavern and 2nd service cavern removed. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

7 Civil Drawings Update (380 GeV)
Extra main beam turnaround added – total tunnel lengths increased by 4.5km 380 GeV: Reduced the length of the BDS to 1.9km Main Beam Turnarounds relocated. Shaft 2 and 3 relocated to the end of the 380 GeV tunnel. “Tunnel lengths” and “Site Lengths” updated. Extra shaft added to the IR service cavern and 2nd service cavern removed. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

8 Civil Drawings Update (380 GeV)
Reduced the length of the BDS to 1.9km Main Beam Turnarounds relocated. Shaft 2 and 3 relocated to the end of the 380 GeV tunnel. “Tunnel lengths” and “Site Lengths” updated. Extra shaft added to the IR service cavern and 2nd service cavern removed. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne Shafts renamed 1.1 and 1.2 – 12m service shaft added

9 Civil Drawings Update (1.5 TeV)
Main Beam Turnaround added. Shafts 4, 5, 6 and 7 relocated to eliminate “dead end” tunnel. “Tunnel lengths” and “Site Lengths” updated. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

10 Civil Drawings Update (1.5 TeV)
Main Beam Turnaround added. Shafts 4, 5, 6 and 7 relocated to eliminate “dead end” tunnel. “Tunnel lengths” and “Site Lengths” updated. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

11 Civil Drawings Update (1.5 TeV)
Extra main beam turnaround added 1.5 TeV: Main Beam Turnaround added. Shafts 4, 5, 6 and 7 relocated to eliminate “dead end” tunnel. “Tunnel lengths” and “Site Lengths” updated. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

12 Civil Drawings Update (3 TeV)
Shafts 8 & 9: relocated to reduce the distance to shafts 6 and 7. Distance is now more than 5km between some shafts. Distance between shafts now m First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

13 Civil Drawings Update (3 TeV)
Distance between shafts 8-10 & 9-11 is now m 3 TeV: Shafts 8 & 9: relocated to reduce the distance to shafts 6 and 7. Distance is now more than 5km between some shafts. First look at the proposed 380 GeV layout. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

14 Central Injector Complex
Tunnels: Transfer line tunnels reduced as e- Pre DR no longer required. DL Tunnels no longer required Surface Buildings: e- DR hall removed DL hall removed. Detector 2 assembly hall no longer required and associated gas storage hall removed. Extra access shaft added to Detector 1 assembly hall. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

15 Central Injector Complex
Tunnels: Transfer line tunnels reduced as e- Pre DR no longer required. DL Tunnels no longer required Surface Buildings: e- DR hall removed DL hall removed. Detector 2 assembly hall no longer required and associated gas storage hall removed. Extra access shaft added to Detector 1 assembly hall. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

16 Central Injector Complex
Tunnels: Transfer line tunnels reduced as e- Pre DR no longer required. DL Tunnels no longer required Surface Buildings: e- DR hall removed DL hall removed. Detector 2 assembly hall no longer required and associated gas storage hall removed. Extra service cavern and shaft added to IR – surface building serving this shaft has now been added. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

17 Drive Beam Injector Section A-A: For 380 GeV a reduced building cross section has been shown: Minimum width possible for reduced cross section is 17m. Extension of a further 15m will be required for upgrades. Two cranes will be required for future upgrades. Initial cost saving due to decreased surface building size by approx. 40% Overall cost increase for upgrades. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT

18 Drive Beam Injector Section A-A: For 380 GeV a reduced building cross section has been shown: Minimum width possible for reduced cross section is 17m. Extension of a further 15m will be required for upgrades. Two cranes will be required for future upgrades. Initial cost saving due to decreased surface building size by approx. 40% Overall cost increase for upgrades. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT

19 Drive Beam Injector Increased Material and installation costs Section A-A: For 380 GeV a reduced building cross section has been shown: Minimum width possible for reduced cross section is 17m. Extension of a further 15m will be required for upgrades. Two cranes will be required for future upgrades. Initial cost saving due to decreased surface building size by approx. 40% Overall cost increase for upgrades. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT

20 Drive Beam Injector Section A-A: For 380 GeV a reduced building cross section has been shown: Minimum width possible for reduced cross section is 17m. Extension of a further 15m will be required for upgrades. Two cranes will be required for future upgrades. Initial cost saving due to decreased surface building size by approx. 40% Overall cost increase for upgrades. Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT

21 Drive Beam Injector Section A-A: For 380 GeV a reduced building cross section has been shown: Minimum width possible for reduced cross section is 17m. Extension of a further 15m will be required for upgrades. Two cranes will be required for future upgrades. Initial cost saving due to decreased surface building size by approx. 40% Overall cost increase for upgrades. 380 GeV 1.5 TeV 3 TeV Construction materials Initial material Reduction by approx. 40% No change Overall material increase by approx. 15% Module Cranes Required Initial Crane width reduced by 40% 2 Cranes and crane installations required 100% increase Construction schedule Man hours and plant hire reduced, (amount TBC) Man hours increased (amount TBC) and plant hire increased by 100% Central injection complex, located on CERN land in Prévessin, consisting of surface buildings and shallow underground galleries. This complex will be divided into several parts: The Main Beam injector complex: 10 x surface buildings, largest of which is approximately 400m x 7m x 3m. 11 x shallow cut and cover type tunnels of varying sizes. The Drive Beam injector complex: 3 x surface buildings, the largest of which will be approximately 2560m x 30m x 9m. 7 x shallow cut and cover type tunnels of varying sizes. Common transfer tunnel from junction point to separation point 277m x 6m x 3m and surface building 30m x 30m x 5m 2 x Final Transfer tunnels (from separation point). Experimental area surface buildings consisting of: 19 x surface buildings. 2 x gas storage areas. 1 x transformer switching yard. Access roads and a car park. RF Tunnel lengths/layout – to be discussed with Daniel – is the required for TOT Numbers are approximate and speculative Further more detailed study on the initial cost savings and the overall cost increase to be done

22 Interaction Region Plan Section 2nd detector hall removed
New service cavern: 120x20x15 and Connection corridors to main tunnel. Plan 2nd detector hall removed Safety passage reduced Second moveable shielding wall removed Service Cavern and shaft has been added for access. Section Assembly & testing surface hall removed Second machine shaft and hall removed CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

23 Interaction Region Plan Section 2nd detector hall removed
New Service shaft and associated surface building added. Plan 2nd detector hall removed Safety passage reduced Second moveable shielding wall removed Service Cavern and shaft has been added for access. Section Assembly & testing surface hall removed Second machine shaft and hall removed CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

24 CLIC-TOT - Reminder Reminder from the last update
CLIC TOT will allow us to optimise the position, depth, and angle of the tunnels. CLIC TOT will allow us to optimise the position of the surface Injection complex and relate this to the position of the main tunnel. Meeting to be held to discuss the geological data requirements and the user inputs and functionality of the tool. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

25 TOT Timeline The proposed programme task completion dates are as follows, assuming a project commencement at the end of April 2017: Task 1 Establish Project Setup and Technical Basis June (mid) Task 2 Data and Functionality Prioritisation June (end) Task 3 Specifications and TOT-CLIC architecting/wireframing (Concept Stage) July (mid) Task 4 Data Integration and TOT-CLIC (beta) development Task 5 Finalised TOT-CLIC Development Sept (end) Task 6 Troubleshooting and Technical Support - CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

26 Data & Functionality Prioritisation
Datasets: Rotation of the machine tunnel in both the vertical and horizontal plane in 0.1 degree increments. A max gradient of 6%. Adjustable shaft locations – Aiming for one shaft per 5km. A maximum shaft depth of 300m – inclined tunnels a possibility if required. Central injection complex input as a separate file. Task 1 Establish Project Setup and Technical Basis June (mid) Task 2 Data and Functionality Prioritisation June (end) Task 3 Specifications and TOT-CLIC architecting/wireframing (Concept Stage) July (mid) Task 4 Data Integration and TOT-CLIC (beta) development Task 5 Finalised TOT-CLIC Development Sept (end) Task 6 Troubleshooting and Technical Support - CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

27 CLIC Study Boundary Study Area
Position of CLIC between the Jura and Lake Geneva Karstic Limestone present below Jura – geological fractures and aquifers present. Complex moraines beneath the lake bed. Two depressions containing complex moraines – Gland and Allondon. Southernmost Jura region within the study area – extreme elevations and expected Karstic Limestone. Potential to keep the first stage In France. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

28 CLIC Study Boundary Study Area
Avoid Jura to reduce tunnelling through Karstic limestone Study Area Position of CLIC between the Jura and Lake Geneva Karstic Limestone present below Jura – geological fractures and aquifers expected. Complex moraines beneath the lake bed. Two depressions containing complex moraines – Gland and Allondon. Southernmost Jura region within the study area – extreme elevations and expected Karstic Limestone. Potential to keep the first stage In France. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

29 CLIC Study Boundary Study Area
Position of CLIC between the Jura and Lake Geneva Karstic Limestone present below Jura – geological fractures and aquifers present. Complex moraines beneath the lake bed. Two depressions containing complex moraines – Gland and Allondon. Southernmost Jura region within the study area – extreme elevations and expected Karstic Limestone. Potential to keep the first stage In France. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

30 CLIC Study Boundary Study Area
Position of CLIC between the Jura and Lake Geneva Karstic Limestone present below Jura – geological fractures and aquifers present. Complex moraines beneath the lake bed. Two depressions containing complex moraines – Gland and Allondon. Southernmost Jura region within the study area – extreme elevations and expected Karstic Limestone. Potential to keep the first stage In France. Gland Allondon CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

31 CLIC Study Boundary Study Area
Position of CLIC between the Jura and Lake Geneva Karstic Limestone present below Jura – geological fractures and aquifers present. Complex moraines beneath the lake bed. Two depressions containing complex moraines – Gland and Allondon. Southernmost Jura region within the study area – extreme elevations and expected Karstic Limestone. Potential to keep the first stage In France. Inclined Tunnel an option here. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

32 CLIC Study Boundary Study Area
Position of CLIC between the Jura and Lake Geneva Karstic Limestone present below Jura – geological fractures and aquifers expected. Complex moraines beneath the lake bed. Two depressions containing complex moraines – Gland and Allondon. Southernmost Jura region within the study area – extreme elevations and expected Karstic Limestone. Potential to keep the first stage In France. Does the Injection Complex need to be on Prevessin? CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

33 Klystron Single Tunnel - TBM
Extraction located above false ceiling 2.6m2 1.5m TBM Tunnel 10m TBM required to achieve required surface width within tunnel. A lot of space below the floor – potential to have a split level tunnel. (example for Tunnel Mont-Sion) Backfill from tunnel excavation to be utilised. (example for Tunnel Mont-Sion) 3.2m 9.9m Same structure design? Consistent layout with drive beam proposed layout Compatible for both klystron and drive beam upgrades 2.2m Intake located below floor level. 4m CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

34 Klystron Single Tunnel - TBM
TBM Tunnel 10m TBM required to achieve required surface width within tunnel. A lot of space below the floor – potential to have a split level tunnel. (example for Tunnel Mont-Sion) Backfill from tunnel excavation to be utilised. (example for Tunnel Mont-Sion) Klystron rack may not be required Same structure design? Consistent layout with drive beam proposed layout Compatible for both klystron and drive beam upgrades CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

35 Klystron Single Tunnel - TBM
TBM Tunnel 10m TBM required to achieve required surface width within tunnel. A lot of space below the floor – potential to have a split level tunnel. (example for Tunnel Mont-Sion) Backfill from tunnel excavation to be utilised. (example for Tunnel Mont-Sion) Same structure design? Consistent layout with drive beam proposed layout Compatible for both klystron and drive beam upgrades New proposal could reduce the width of the modulator tank by up to 800mm. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

36 Klystron Single Tunnel - TBM
TBM Tunnel 10m TBM required to achieve required surface width within tunnel. A lot of space below the floor – potential to have a split level tunnel. (example for Tunnel Mont-Sion) Backfill from tunnel excavation to be utilised. (example for Tunnel Mont-Sion) Same structure design? Consistent layout with drive beam proposed layout Compatible for both klystron and drive beam upgrades Can the accelerator structure be moved closer to the wall? CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

37 Klystron Single Tunnel - TBM
12m Diameter tunnel TBM Tunnel 10m internal diameter TBM required achieve required surface width within tunnel. A lot of space below the floor – potential to have a split level tunnel with services located in the lower level. (example for Tunnel Mont-Sion) Backfill from tunnel excavation to be utilised. (example for Tunnel Mont-Sion) Reinforced platform to provide stable upper level. Same structure design? Consistent layout with drive beam proposed layout Compatible for both klystron and drive beam upgrades CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

38 Klystron Single Tunnel - TBM
TBM Tunnel 10m TBM required achieve required surface width within tunnel. A lot of space below the floor – potential to have a split level tunnel. (example for Tunnel Mont-Sion) Backfill from tunnel excavation to be utilised. (example for Tunnel Mont-Sion) Backfill to reuse some of the excavated material Same structure design? Consistent layout with drive beam proposed layout Compatible for both klystron and drive beam upgrades CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

39 Klystron Single Tunnel - Roadheaders
Crane requirements for klystron module cavern to be determined? Roadheader Tunnel Single tunnel layout – 10m width, similar to the ILC potential for the same space reductions as the TBM tunnel. Approx. 11km of mined tunnelling can be expensive and time consuming. Must be compatible with TBM drive beam upgrades. What services will be required? Waveguides every 1m or 2m! Second tunnel to be located slightly above the Accelerator tunnel to avoid beam dumps with waveguide connections. (Machine Design is for presentation purposes only and is subject to change) CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

40 Klystron Single Tunnel - Roadheaders
ILC – CLIC Comparison What services will be required? Roadheader Tunnel Single tunnel layout – 10m width, similar to the ILCpotential for the same space reductions as the TBM tunnel. Approx. 11km of mined tunnelling can be expensive and time consuming. Must be compatible with TBM drive beam upgrades. Waveguides every 1m or 2m! Second tunnel to be located slightly above the Accelerator tunnel to avoid beam dumps with waveguide connections. (Machine Design is for presentation purposes only and is subject to change) CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

41 Klystron Single Tunnel - Roadheaders
Mined 380 GeV H. Mined Excav. cost (EUR/m3) (Approximate) (likely to increase) Tunnel length (m) 13568 Tunnel Cross sectional area. (m2) 43 Total Volume (m3) 583500 Roadheader Tunnel Single tunnel layout – 9.5m width, potential for the same space reductions as the TBM tunnel. Approx. 11km of mined tunnelling can be expensive and time consuming. Must be compatible with TBM drive beam upgrades. Waveguides every 1m or 2m! Second tunnel to be located slightly above the Accelerator tunnel to avoid beam dumps with waveguide connections. More detailed study required to determine geology and cost of supporting the mined tunnel where required. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

42 Klystron Single Tunnel - Roadheaders
Roadheader Tunnel Single tunnel layout – 9.5m width, potential for the same space reductions as the TBM tunnel. Approx. 11km of mined tunnelling can be expensive and time consuming. Must be compatible with TBM drive beam upgrades. 5.6m Tunnel diameter for the Drive beam machine. Waveguides every 1m or 2m! Second tunnel to be located slightly above the Accelerator tunnel to avoid beam dumps with waveguide connections. Consider tunnelling past the end of each energy stage? CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

43 Summary Klystron Machine Future Study - Roadheader or TBM Tunnel
Compatibility with a smaller single tunnel upgrade requires further study. Failure rate of klystron modules is high – what are the access requirements for maintenance and is this possible with 1.5m shielding wall? 11km roadheader tunnel is expensive and time consuming. Wasted space below the floor slab – can this be utilised for services or can a dual level tunnel be constructed (see Mont-Sion tunnel for an example). Cost and schedule comparison to be provided for the different tunnel options. CLIC TOT Initial “test” Lattice files to be produced to allow a beta version of the tool to be tested. Geological layers to be produced by the consultant from the boundary maps provided. Further define the constraints to enhance the possibility of a machine learning tool – automatic optimisation of the positioning. Civil Drawings Understand the surface building requirements for the klystron machine to allow a layout drawing to be produced. Produce 3D schematics of the “baseline CLIC machine” for both the klystron and drive beam option. Understand the required services (especially for the klystron machine) and the HVAC systems to allow the cross sections to be updated. Continually update the drawings as and when new information is acquired. CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

44 Thank You For Your Attention
Thank you to all contributors (John Osborne, Paolo Serafino, Giampiero, Emilie Ter Laak etc…) CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

45 Upcoming Meeting 21st of July 01st of September 13th of October
24th of November 15th of December CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

46 Summary 3 different energy stages: 10km, 27km and 48km
380 GeV Klystron design compatible with upgrades. Double tunnel or single tunnel required. Tunnel Optimisation Tool kick off meeting to be held on the 22nd of May Civil Drawings are to be produced by Civil Draughtsmen - new drawings to be produced for the Klystron design and existing drive beam design drawings to be changed. Next meeting on the 21st of July. TO BE CONFIRMED WITH DANIEL CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne

47 Low energy Klystron Klystron Layout
Double tunnel – one for the accelerator and one for the klystrons. Accelerator tunnel How does this change? Are the connections between the tunnels compatible with the current design? ID of the accelerator to be 5.6m not 3m Klystron tunnel – 4.5m ID Section through tunnels Which Caverns will be required? Waveguide connections Klystron Tunnel Accelerator tunnel – How has the layout changed Accelerator tunnel – 5.6m ID Access for second tunnel? TOT for double tunnel? Surface buildings for Klystron machine remain the same except no drive beam requires No turnarounds for initial stage? CEIS Working Group Meeting 16/06/2017 – Matthew Stuart & John Osborne


Download ppt "CLIC Civil Engineering Update"

Similar presentations


Ads by Google