UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Business Operations and Facilities Meeting September 22, 2016
2
Building Area A – South Classroom wing closest to Doe Run Road Area B – Administration Suite, Main vestibule Area C - Gymnasium, Cafeteria, Kitchen Area D – North Classroom Wing
3
Area A - South Classroom wing closest to Doe Run Road
All concrete slabs are poured. Structural Steel framing and decking is complete. Roofing started 9/20/2016 First floor CMU (Masonry) is complete. Second floor CMU starting . First Floor mechanical ,plumbing and electrical components are being installed. Second floor MPE components to start in a week. Area A – Classrooms 1st floor Area A – South Elevation Area A – North Elevation Through Gymnasium Area A – Looking down corridor of north wing
4
Area B – Administration Suite, Main vestibule
Footings are 100 % complete. Concrete SOG (Slab on Grade) is 100% complete. Structural Steel is presently being fabricated. Steel erection may be the last of the areas (A,B,C &D) to be done. Area B – Future administrative area. Area B – Main entrance looking at stage, cafeteria area. Area B – Future administrative and nursing area.
5
Area C - Gymnasium, Cafeteria, Kitchen
Footings are 100% complete. Piers and anchor bolts are 100% complete. SOG may happen in next two weeks. Structural steel is erected for the Gym, decking and detail work to follow. Basement Concrete Walls are complete and backfilled. Structural Steel over Basement has started and is 70% complete. Boilers and Main pumps are being installed in the Basement. CMU Foundations to finished first floor are 95% and should be completed in a week. Area C – Gymnasium looking at Stage area Area C – Serving and Kitchen area. Area C – Cafeteria seating area. Stage to left.
6
Area D – North Classroom Wing
Footings and Foundations are 100% complete. Interior Footings and Piers are 100% complete. Underground plumbing is 95% Complete. Underground Electrical is 98 % Complete. Prep. For SOG concrete will start within this week. SOG pour may happen in the next two weeks. Structural Steel will follow in a week and a half or two weeks.
7
The builder and contractors are working quickly!
Area A Taken on 7/7/2016 Taken today, 9/22/2016 Area C