Presentation is loading. Please wait.

Presentation is loading. Please wait.

Liaison Council Meeting

Similar presentations


Presentation on theme: "Liaison Council Meeting"— Presentation transcript:

1 Liaison Council Meeting
May 1, 2006

2 Welcome Meeting purpose: Present Draft Biennial Budget
Project load projections Discuss Tri-Party MOA amendments Obtain Liaison Council input/thoughts on draft MOA amendments

3 Meeting process: Biennial Budget Presentation
Questions MOA Amendments Presentation Liaison Council Input/Thoughts Captured

4 December 14, 2005 Liaison Council Meeting
EEP Planning Cycle: Dec 05/Jan06 Coastal RFPs Feb-Mar 06 Operational Strategic Plan Mar 06 Second wave FDP RFPs Apr 06-Jun 06 Award of Oct 05 RFPs Mar-Apr 06 Biennial Budget Jul 06- Aug 06 First wave SFY 07 RFPs Aug-Sep 06 Annual Report

5 Business Model: Continuous Improvement
Evaluate existing assets Calculate the net remaining need Design strategies to satisfy need Contract work Evaluate progress/ quality Make adjustments Assemble requests for mitigation

6 Impact Projections (Time Frames)
7 -Year NCDOT TIP 7 Years 2 3 4 1 5 6 7 Year NCDOT TIP Impact Projections 6 Years 3 months July 2005 Feb 2006 Oct 2011 EEP Receipt of Impacts Feb 2006 Year NCDOT TIP Mitigation Permit Projections April 2011 5 Years 3 months Effective Mitigation Projection Projected date that last TIP project may be permitted

7 SFY 07/08 Biennial Budget Breakdown
Admin= $11.2 M Restoration= $115.7 M HQP= $29.8 M Proj. Dev.= $3.5 M Total $160.2 * Based on MOA schedules

8 Implementation Programmed (two years) Breakdown $115.6 M
$ 73.6 M FDP (64%) $ 42.0 M DBB (36%)

9 HQP $29.7 M budget $25.1 M land Projected to be compete QTR1 SFY 07/08
Completes land transactions on options Titles Surveys Legal fees HB 933

10 Project Development $3.5 M Includes
Cost to complete 13 active WS plans Initiate 4 new WS plans Initiate 6 abbreviated WS plans

11 Historical & Projected

12 Budget Questions?

13 “We have had a productive transition and are still learning how to make EEP work better”
Secretary Bill Ross Address to the Liaison Council December 14, 2005

14 Tri-party MOA: Core principles and goals remain the same
Necessity for amendments Section adjustments

15 Tri-party MOA- What is not changing
Advance mitigation based on impact prediction 1:1 restoration to replace lost functions (preservation will not be used as sole method of mitigation) Concerted effort to effectively restore and replace lost aquatic functions Clean Water Act standards for no net loss

16 Necessity for MOA amendments
Technical adjustments to original assumptions Impact projections not far enough in advance Clarification of responsibilities Complexity of metrics and reporting To align processes and timing

17 MOA adjustment themes Challenging CUs and alternative mitigation
Accountability Flexibility Sequencing and communication between EEP-DOT-USACE Compliance metrics

18 Amendment Sections: IV.F VI. B. 4 VI. B. 6 X

19 Section IV.F Why: Build some level of flexibility
What: NCDOT ability to propose to use alternatives- in-lieu fee program, other Discussion: Means and methods for DOT to propose alternative mitigation when/if NCDENR is unable to provide

20 Section VI.B.4 Why: to clarify responsibilities
What: A clear definition of who USACE holds accountable for mitigation at what points in time Discussion: To clearly define that EEP is responsible party at time of permit decision,

21 Section VI.B.6 Why: To align processes and timing
What: A clear definition of sequencing DOT requests and EEP acceptance for mitigation to ensure that mitigation delivery is in the correct timing with permit requirements and a protocol to address unanticipated impacts. Discussions: Centering around USACE developing protocol

22 Section X Why: Complexity
What: To develop a clear and concise definition and metrics for evaluating compliance, reporting, and directing the program Discussion: USACE proposes metrics that are compatible with proposed CFRs and simplifies the reporting system.

23 MOA Timeline Technical Issues
Years Allowed to Complete Construction From Moment Impact Data Delivered 1 2 3 4 5 Transition Period Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Date Impact Projections Received 5 months to complete Watershed Planning, Site Identification, Acquisition, Design, and Construction

24 MOA Timeline Technical Issues
Years To Complete Acquisition in MOA From Moment Impact Data Delivered -4 -3 -2 -1 1 2 3 Transition Period Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 -3 Years 7 months Date Impact Projections Received

25 USACE Amendment Process:
Continue discussions between USACE, DOT and EEP Develop proposed draft amendment document Public comment

26 Liaison Council Questions/Input
May 1, 2006

27

28

29 Progress Report End of Transition Compliance Other ILF programs
Buffer Nutrient offset Fund Reports

30 Data Sources End of Transition Report Annual Report for FY 2004-2005
– follow links to Publications page

31 End of Transition Compliance - Overall
Streams = 98.70% Wetlands = 95.04% Highest level of compliance ever for NC’s ILF Programs Includes 5:1 return of HQ Preservation Permits for which 1:1 restoration has not been provided remain covered by 10:1 preservation WL – majority of non-compliance in CAT03 Illustrates increase in compliance levels Compliance increasing while demand increasing

32 EOT Compliance - Streams
Gross assets illustrate that we’re advancing mitigation prior to impact Looking ahead

33 EOT Status - Wetlands Here we have significantly more assets because DOT had built some large mitigation sites that were transferred into EEP – still shows progress toward advancement

34 High Quality Preservation
Eco-region Stream Feet Riverine Wetland Acres Non-Riverine Wetland Acres Central Piedmont 324,093.00 160.82 34.30 Northern Inner Coastal Plain 50,901.00 645.50 0.00 Northern Mountains 130,530.00 Northern Outer Coastal Plain 11,819.00 305.00 250.00 Southern Inner Coastal Plain 154,660.00 4,000.00 Southern Mountains 247,096.00 30.00 Southern Outer Coastal Plain 5,015.00 116.00 1,034.00 Southern Piedmont 116,434.00 1,477.30 TOTAL ALL ECO-REGIONS: 1,041,358.00 6,734.62 1,318.30

35 Project Delivery Mechanisms – current contracts
Full Delivery Contract value = $87,082,559 Design-Bid-Build Contract value = $39,612,933 Use of full-delivery to get mitigation in advance

36 Questions??

37 On the horizon: MOA adjustments Expansion of nutrient offset
Cost study – possible fee revisions GARVEE bonds Building Information Management System More training of construction contractors

38 Reports www.nceep.net Quarterly Reports Annual Report
End of Transition Report

39 Biennial Budget Steps Determine need based on new impact projections
Cash flow projections on active contracts Assemble document on two-year schedule (cash flow) Submit to DOT

40 Phase 1- Determine New Program Requirements
Receive and analyze DOT impact forecasts Compare impact forecasts with assets produced Calculate net-remaining need consistent with MOA timelines Design strategies to implement projects

41 Phase 2- Determine cost to complete active work
Compile active contracts and agreements Determine remaining contract value Determine anticipated cash flow Place projections into biennial/quarterly projection

42 Phase 3- Combine active and new starts
Assemble data in format as required under the two-party Administration Implementation DBB FDP HQP Project Development (Watershed plans)

43 Phase 4- Submit biennial budget to DOT

44 Key points about EEP Major administrative duties: manage funds
contract administration (Q/A) strategic planning programming work reporting leverage resources addressing compliance/new rules and regulations proposing strategies based on new science emerging technology

45 Key points about EEP Outsource majority of work, rely heavily on the private sector for production Design, Bid, Build Full Delivery Land Owner Contacts Watershed planning Monitoring Coordination and Guidance Program Assessment and Consistency Group Partnerships


Download ppt "Liaison Council Meeting"

Similar presentations


Ads by Google