1
Normanton/Karumba WTP Upgrade
Matt Fanning Director TBG Pty Ltd
2
Normanton/Karumba Shire pop: 2100 (Wet season) Karumba residents: 600
Karumba tourists: 2,000 Industry: Mining, tourism fishing
3
Existing Scheme Normanton/Karumba Water Treatment Plant
1963 – Normanton Water Supply Established 1982 – New 300mm rising main and Clear water storage, 23km rising main Karumba connected 42km rising main 1999 – capacity upgrade (copied existing clarifiers), new storages both Normanton and Karumba Capacity of 3.5 ML/day, Storage Capacity 2.36ML Normanton, 5ML Karumba
4
Project Summary Normanton/Karumba Water Treatment Plant
2000 – Planning report – $1.68M 2003 – SCAP funding awarded - $3M grant 2004 – Glenore Weir raising investigation 2006 – Telemetry system implemented (basic automation, but mainly alarms and reporting) further investigations little traction October 2009 – Peer Review Hyder Consulting 2009 – Advised by State that SCAP Funding Withdrawn loss of $1M back to Government November 2009 – Design Awarded to BTO December 2010 – Works commenced June 2011 – Works completed
5
Scheme Issues High Operator costs – Manual processes
Difficult to operate – SCADA not full automation High risk of water quality failure Changing water quality guidelines Building required renewal Equipment out dated and high maintenance Upgrade could only occur during the wet season
6
Scheme Vision To implement a cost effective and reliable Water Treatment System for the towns of Normanton and Karumba.
7
Basic Principles of WTP
Pump water from source location
8
Basic Principles of WTP
Remove large particles in clarifier Coagulant
9
Basic Principles of WTP
Remove fine particles in gravity filter
10
Basic Principles of WTP
Apply disinfection – generally chlorine TO SUPPLY
11
Existing Plant Overview
Filter 6 Clarifier 5 4 3 2 1 Washwater Air Scour Raw Water Existing Building Res. #1 Res. #3 Res. #2 Dosing Points
12
Existing Plant Overview
13
Existing Plant Overview
14
State of WTP in 2009 WTP review (2009)
Catchment management issues leading to raw water contamination; Extremes of turbidity in the raw water difficult to treat; High filtered water turbidity leading to risk of pathogen shielding and breakthrough; Elevated iron levels leading to oxidant consumption and discoloured treated water; Compromised disinfection efficiency; Presence of Hydrogen Sulphide in Supply Sources; Tastes and odours in the treated water.
15
State of WTP in 2009 Existing chemical systems
Did not meet Workplace H&S standards Chemical make-up labour intensive Chemical quality open to human error Chemical dosing set by operator Dosing not proportional with flow
16
Dosing System
17
State of WTP in 2009 Existing Clarifiers
Poor performance at high flows Poor performance when high turbidity Problems de-sludging Odour problems Solids carry-over to filter
18
Clarifiers
19
Clarifiers
20
State of WTP in 2009 Existing Filters
Poor filtration (poor water quality) Manual washing; Labour intensive Damage to filter media
21
Poor filter Performance
22
State of WTP in 2009 Old Backwash system (used to clean filters)
Flow too low (poor washing of media) No standby pump Difficult to prime Labour intensive No NRV fitted to pump
23
Poor Backwash System Air Blower Backwash Pump
24
State of WTP in 2009 Old Air Scour (used to help wash filters)
Air flow too low (poor agitation of media) No standby blower Labour intensive
25
Poor Air Scour System
26
Poor Air Scour System
27
State of WTP in 2009 Chlorine dosing Not proportional to flow
No gas detection & alarm Labour intensive
28
Poor Chlorine Dosing System
29
State of WTP in 2009 General state of building Not cyclone rated
Termite damage Leaking Possible asbestos
31
Risk? Risk Assessment Risk Category Risk Item PROB CON Risk Score
Risk Rating Water Quality Protozoa 4 70 280 Very High Bacteriological Disinfection By-Products 3 10 30 Moderate Aesthetics (Taste, Staining) 5 50 High Water Supply Short Term Loss of Supply 200 Extended Loss of Supply 210 Health & Safety Building & Stairways Chemical Handling 150
32
Why Automate? Main reasons to automate the WTP
Reduce labour costs ($200k/yr) Improve quality of water Optimise chemical use (save $$$) Improve reliability of plant Accurate reporting and alarming
33
First Step? Options study 1 – Refurbish existing plant
2 – New clarifier & refurbish existing filters 3 – New clarifier & membrane filtration 4 – Membrane filtration only Include New intake at Glenore Weir
34
New Clarifier & Existing Filters New Clarifier & Existing Filters
Which Option? CAPEX Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only $ 2,401,000 $ 3,046,000 $ 4,346,000 $ 4,355,000 OPEX Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only $ ,000 $ ,000 $ ,000 $ ,000
35
New Clarifier & Existing Filters
Which Option? Estimated NPV Year Refurbishment Only New Clarifier & Existing Filters Clarifier & Membrane Membrane Only 15 $ 4,595,000 $ 4,986,000 $ 7,183,000 $ 7,106,000 20 $ 4,943,000 $ 5,305,000 $ 7,647,000 $ 7,558,000 25 $ 5,181,000 $ 5,522,000 $ 7,964,000 $ 7,865,000 30 $ 5,315,000 $ 5,644,000 $ 8,142,000 $ 8,039,000
36
Preferred Option New clarifier & refurbish existing filters
New air scour system New washwater system New chemical dosing New buildings Complete automation
37
Actiflo Clarifier
38
Implementation Construction issues
Operational plant (Normanton & Karumba) Remote location (Materials & skilled labour) Procurement (Australian & New Zealand) WEATHER! 4 phase construction
39
Construction Sequence 1
Filter 6 Clarifier 5 4 3 2 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 ACTIFLO
40
Temp chemical dosing systems
41
Demolition
42
Construction Sequence 2
Filter 6 Clarifier 5 4 3 2 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
43
Fabrication
44
Staff Induction Training!
45
Construction Sequence 3
Filter 6 Clarifier 5 4 3 2 1 Washwater Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
46
New pipe work and control valves
47
New Clarifier
48
Construction Sequence 4
Filter 6 Clarifier 5 4 3 2 1 Air Scour Raw Water NEW Building Res. #1 Res. #3 Res. #2 New Backwash Water New Air Scour ACTIFLO
49
New MCC Building
50
Filter Refurbishment
52
Filter Control
53
New chemical Dosing System
54
New WTP Building
55
New WTP Building
56
WTP Performance Old Performance New Performance
Raw water quality Turbidity = 50 NTU Old clarifiers Turbidity = 3 NTU After refurbished filters Turbidity = 1 NTU Maximum flow (3 filters) = 36l/s! New Performance After Actiflo clarifier Turbidity = 1 NTU After refurbished filters Turbidity = NTU Maximum flow (3 filters) = 50l/s!
57
WTP Performance
58
What Else? Additions to main contract Norman River PS
Karumba chlorination system upgrade Telemetry system upgrade Procurement Construction management Commissioning
59
Lessons Learnt? Keep it simple Appreciation of location
Supply of materials Available labour/contractors Weather Build as much off site as possible Good working relationship with client
60
Why Use BTO? Excellence in Water & Wastewater Engineering
They delivered on their promises: on time with clear reports & designs with staff / resources promised on budget BTO don’t just write reports – they get things done and deliver!
61
QUESTIONS???