1
Common Projects Status
ATLAS RRB-T Common Projects Status ATLAS RRB, 22 October 2001 Marzio Nessi
2
List of Common Projects (annex 10 MoU)
Barrel Toroid Magnet End-cap Toroid Magnet Solenoid Common Magnet Infrastructure LAr Barrel Cryostat LAr End-cap Cryostats (2) LAr Cryogenic Plant Parts of Trigger, DAQ and Controls Radiation Shielding Parts of Experimental Infrastructure 10/22/2001 ATLAS RRB-T
3
9m long B0 model coil achieved 20 kA, July 01
B0, short prototype coil 9m long B0 model coil achieved 20 kA, July 01 10/22/2001 ATLAS RRB-T
4
B0, short prototype coil Common effort of CEA, INFN-LASA and CERN :
to provide focus for the BT design to exercise all production steps to implement in BT production to exercise testing and to verify the design construction by CEA and LASA, test by CERN Construction completed : delivered to CERN in Sep 00 last minute change of stops sliding interface (May 01) 1st test campaign completed nd test campaign started on 2nd Oct 01 B0 test result : vacuum vessel is tight (no repairs done) cooling down in 2 wks, all test station cryogenics works 20.5 kA achieved without quench in coil, so the coil design works cold leak in thermal shield circuit, stops sliding OK, tie rods OK 19 kA quench in coil-lead connection due to conductor movement next campaign is in stability, propagation, losses etc. 10/22/2001 ATLAS RRB-T
5
B0, short prototype coil Examples of impact on BT construction :
the early B0 design brought collaborative spirit and focus to the magnet lab conductor: early qualification and testing improved conductor cleaning improvement to coil winding tolerances drastic improvement to impregnation (4 month extra work!) change of coil casing welding technique: EB->MIG cold mass integration: bladder technology and tooling cooling lines: less welds, line testing of whole circuits thermal shield: less welds, Al alloy, gap between panels tie rods: optimization: reshaping, testing stops: redesign, new sliding surfaces superinsulation: blanket layout and assembly instrumentation: change of sensors, thermalization etc. vacuum vessel assembly, use of frame cryostat integration: increase of clearance, procedures, many details of conductor bending, avoid turnovers, cooling pipe testing and gluing cryoring: conductor movements 10/22/2001 ATLAS RRB-T
6
1st integration in Jan 02, 1st delivery to CERN in Mar 02
Barrel Toroid Magnet Engineering & CEA, INFN-LASA,CERN BT conductor (32 units x 1730 m) : 23 units done, on time for coil winding, not critical. Coil Casings (8 units): welding on CC-1 completed, machining started on 8 Oct 01 first casing delivery by 18 Dec 01, last one in Apr 03 Double Pancakes (16 units) 6 DPCs made, 5 accepted, #9 is being wound 5 m float w.r.t. coil casing, fine ! Cold mass integration : tooling under construction, 4 Double Pancakes delivered 1st integration in Jan 02, 1st delivery to CERN in Mar 02 To CERN 10/22/2001 ATLAS RRB-T
7
Barrel Toroid Magnet Barrel cryostat during construction
First Coil casing ready for machining 10/22/2001 ATLAS RRB-T
8
Barrel Toroid Magnet (2)
Vacuum vessels (8 units) : delivery 1st vessel by FCM in Dec 01, all steel procured. Not time critical ! Radiation shield (8 SETS) : Contract ok! 1st delivery required by April/02. Delivery is on the critical path! Superinsulation (5000m2) : 1st batch delivery in Mar 02 Ti-Tie rods (64 units) : 64 rods forget, 6 machined. All Ti rods will be proof loaded at Kurchatov at 77 K 8 piece delivery by Mar 02 256 Stops shield sup. : tender completed, company selected contract under preparation, 1st bat by Apr 02 Coils Integration inside the cryostat: JNIR team at CERN, tooling under construction, delivery starts in Nov 01 Integration work starts in April 02 Warm support structure: design review passed, TIS approval awaited in Oct 01 forging work shall starts in Dec 01, large scale forging by Samara, all machining by JNIR For installation in the ATLAS Pit 10/22/2001 ATLAS RRB-T
9
End-Cap Toroid Magnet Integration inside the cryostat:
Engineering & RAL, Nikhef ECT conductor (32 units x 820 m) : 16 units done, not critical. Vacuum vessels (2 units) : 1st vessel ready, 2nd vessel ready by March 02 1st vessel being transported to CERN right now.arrives on 29 Oct Cold masses (2 units) full size dummy coil winding completed in Oct 00 at HMA serious problem with schedule and cost increases caused by company taken over by FKI. delivery will be late in 03 and 04, not yet a problem for installation as it is scheduled for May 05. Supports &Tie rods (64 units) : production has started, 1st batch delivery in Mar 02 Radiation shields (8 SETS) : Production has started,delivery of all shields together by May 02 Superinsulation : production starts in Sept 01, delivery in May-Aug 02 Integration inside the cryostat: by JNIR team at CERN in Hall 191, tooling under construction, work at CERN starts in Apr 02 integration management by RAL For installation in the ATLAS Pit 10/22/2001 ATLAS RRB-T
10
End-Cap cryostat during construction
End-Cap Toroid Magnet End-Cap cryostat during construction 10/22/2001 ATLAS RRB-T
11
Magnet Infrastructure
He refrigerator & distribution: re-use of 6 kW CERN machine, agreed contract for 2nd refrigerator system awarded. Proximity cryogenics : design completed by RAL, tender in Feb 02 Vacuum System : predesign completed by RAL, implementation studied Magnet Power System : final design and production of common system by LASA Magnet Safety and Control Systems : CERN is defining a common system with standardized hardware, will be built and installed by CERN tender completed, company selected 10/22/2001 ATLAS RRB-T
12
Solenoid Successful excitation test, Dec 00 {Toshiba} :
Cooling down, excitation up to 8.0 (nominal field) and 8.4 kA (+10%) 2 training quenches at both end flanges (classical) Results accepted by ATLAS, test completed Delivered to CERN on 3 rd Set , 2001 : Acceptance test by KEK and Toshiba Solenoid provisional accepted 10/22/2001 ATLAS RRB-T
13
LAr Barrel Cryostat The Barrel cryostat arrived at CERN :
Cryostat was leak-tested at CERN A leak has been discovered on the warm bulkhead "A", in the region of the "bulge“ KHI, BNL and ATLAS agreed on the provisional acceptance with reserve on the flange A, where the source of the problem was identified KHI and BNL will take actions for the repair to be done by the end of February The cover can be repaired in parallel to the integration work without delay on the agreed integration schedule Integration work has started : Cryostat fully opened Sept. 28th First Signal Feedthrough in place Oct. 8th Now 8 Feedthroughs are installed, welded and leak checked ~50% of all Feedthroughs are constructed 10/22/2001 ATLAS RRB-T
14
LAr Barrel Cryostat Cryostat @ CERN Feedthrough installation
10/22/2001 ATLAS RRB-T
15
LAr End-Cap Cryostats (2)
~ 30% of Feedthroughs constructed Assembly of Cryostat C has been completed : An Hydraulic test was performed on Sept. 18th and failed because of an excessive deformation on the large Omega seals. Cryostat was leak-tested A set of modifications have been proposed and successfully implemented New milestones: Pressure test: Oct. 22nd 2001 Cold test(finished): Nov. 8th 2001 Delivery at CERN: Dec. 3rd 2001 Cryostat A : Delivery at CERN expected for April 3rd, 2002 10/22/2001 ATLAS RRB-T
16
End Cap cryostat C assembled at Simic
LAr End-Cap Cryostat End Cap cryostat C assembled at Simic 10/22/2001 ATLAS RRB-T
17
LAr Cryogenics Plant External cryogenics : Proximity cryogenics :
First liquid nitrogen dewar will be delivered end of October The 2nd dewar and the 2 liquid argon storage tanks will be delivered June 2002 Storage tanks in the pit in July 2003 Refrigerator, ordered by BNL. The commissioning is planned in January 2004 Cryogenic lines, tendering procedure in progress Proximity cryogenics : Expansion vessels and valve boxes contracts signed. Delivery foreseen middle of Needed for the cold tests in 2003. Work on flexible Ar lines and transport system under progress, prototyping done. Vacuum material delivery has started, diffusion pump already used for the barrel acceptance test. Process control: Agreement concerning the hardware, ready for signature. Development station already delivered. Need to finalize choices for the software, within UNICOS; agreement for this part should be ready before end 2001. 10/22/2001 ATLAS RRB-T
18
Radiation Shielding JD shieding : JF shieding : JT shieding :
Redesign done (mech., cost) Final design review Nov. 2001 Start procurement phase spring 2002 JF shieding : Redesign under way (cost, noise, mech.) Final design review Feb. 2002 Start procurement phase spring 2002 JT shieding : New concept approved by EB Redesign under way (cost, noise, mech.) Final design review Apr. 2002 Start procurement phase summer 2002 10/22/2001 ATLAS RRB-T
19
Parts of Experimental Infrastructure
Feet & Rails : PPR review done Firm selected and qualified Contract circulating before signature Procurement of material by Feb 2002 External rails (trucks): Design review done Firm selected, possible IK from Poland PPR in Feb 2002 Major infrastructure procurements: Cranes (surface,underground) : contract F-420 done, on schedule Area Cooling&Ventilation (CERN) : contract F-405 done, on schedule Metallic structures : contract done, on schedule 10/22/2001 ATLAS RRB-T