1 The commissioning of Trailway Court
Robin James, Service Development Officer, Dorset CC The management of Trailway Court Debbie Eadie, Head of Extra Care, Aster Living A Care & Support perspective - results of residents survey Pauline Bain, Internal Audit Manager, SCA Group The value of Trailway Court Sarah Macbeth, Research & Development Officer, Dorset CC Dorset’s Older People’s Housing Plan Safe & Independent Living (SAIL) Sarah Moore, Dorset Fire & Rescue Service

2 Commissioning Trailway Court
South West Housing LIN Meeting Thursday 6th June

3 Archbishop Wake

4 Archbishop Wake William Wake 26 January 1657 – 24 January 1737 A priest in the Church of England and Archbishop of Canterbury from 1716 until his death in 1737.

5 Archbishop Wake School

6 Archbishop Wake School Site...
Available for development Publically owned Town Centre site

7 The enabling role.... Robin & Derek
both working at Purbeck District Council 2007: Derek – Head of Housing at North Dorset DC – looking for someone to develop the site Robin – Working for Synergy Housing Group looking for sites [2013 – both working for Adult and Community Services at DCC]

8 The enabling role.... Synergy Housing and North Dorset DC agree to work in partnership to seek to develop an Extra Care Scheme on the site 2008: DoH - Extra Care Bid Round Synergy, North Dorset and Dorset CC agree to partner

9 The enabling role.... November 2010: 1 week from completion
New tenants selected and packed up

10

11 April 2011 Trailway Court Opens Lessons learnt review:
Plan for main contractor to go into administration

12 Contracting Housing Related Support:
Commissioned by Dorset Supporting People Scheme Manager (18.5 hours) + Support Worker (18.5 hours) Open book pricing

13 Contracting Care and Support
Commissioned by Adult & Community Services Settling in and Health and Wellbeing programmes 24 hour emergency care cover + night time packages of care 1 dom care trained person – 7am to 10pm 1 dom care trained person – 10pm – 7am (awake) 1 dom care trained person – 10pm – 7am (sleeping)

14