1 PARLIAMENT OF THE REPUBLIC OF SOUTH AFRICA MID-YEAR REPORT (COVERING MID-TERM) 23 November 2016

2 STRUCTURE Part A: Brief Overview Part B: Strategy Overview
Part A: Brief Overview Part B: Strategy Overview Part C: Mid-term Review – Achievements, Performance Trends, Programme Performance, Challenges Part D: Way forward & Recommendations

3 PART A Brief Overview

4 PARLIAMENTARY BUSINESS CYCLE

5 PERFORMANCE IN CONTEXT

6 PERFORMANCE INFORMATION
PART B PERFORMANCE INFORMATION

7 MID-TERM OVERALL PERFORMANCE TRENDS
Re-aligned the work of Parliament to NDP and other regional instruments Reviewed Rules and Orders to reflect established practices in Parliament which contributed to providing coherence in policy implementation

8 MID-TERM OVERALL PERFORMANCE TRENDS
Implementation of zero-based budgeting aligned to the strategic plan, APP & operational plan Provided leadership to inform the amendment and passing of the FMPPLA & approval of SCM regulations for Parliament and Provincial Legislatures A Draft Legislative Sector Bill prepared

9 MID-TERM OVERALL PERFORMANECE TRENDS

10 MID-YEAR OVERALL PERFORMANCE TRENDS

11 PROGRAMME 1 PERFORMANCE INFORMATION
 Programme 1: Strategic Leadership and Governance Political leadership, governance and institutional policy, communication and co-ordination, oversee development and implementation of strategic plan, annual performance plan and budget, Parliamentary Budget Office and Office: ISD.

12 MID-TERM PROGRAMME PERFORMANCE OVERVIEW

13 PERFORMANCE TRENDS

14 PERFORMANCE TRENDS % of governance schedule implemented
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status % of governance schedule implemented - 100% % of governance documents tabled for referral (FMPPLA) 25% Number of analysis reports presented to the finance & Appropriation Committees in both Houses of Parliament 14 32 10 13

15 PROGRAMME 2: ADMINISTRATION
Strategic leadership support and management, institutional policy and governance, development programmes for Members, management and administration, internal audit and financial management, and the Registrar of Members’ Interests.

16 MID-TERM PROGRAMME PERFORMANCE OVERVIEW
2014/15 annual Re-orientated the work of the Administration towards the achievement of the goals of the NDP, regional, continental policy and developmental imperatives 2015/16 annual Improving implementation of the Members Capacity Building and Development Strategy. This includes progressively mapping-out a phased approach on the establishment of a Parliamentary Institute. Implementation of zero-based budgeting aligned to the strategic plan, APP and operational plans of Parliament in order to align envisaged outcomes and outputs to resource allocation, improving the strategic focus on achieving results 2016/17 mid-year Institutionalization of outcomes approach and zero-based budgeting. The implementation of efficiency and cost cutting measures gives effect to Parliament’s commitment to “ensure that resources are used effectively, efficiently and transparently” as stipulated in Section 7 (a) of the FMPPLA. Draft Legislative Sector Services Bill presented to the relevant stakeholders for consideration. .

17 MID-TERM PERFORMANCE OVERVIEW

18 MID-TERM PERFORMANCE TRENDS
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status Progress on implementation of Members’ Capacity Building and Development strategy - 80% 100% Strategy developed & implemented Completion rate measured on annual basis % of capacity building programmes executed % of Speakers’ forum and SALSA resolutions followed up and actioned 90% % cost saving of total budget 1% 0.77% n/a Annual target % compliance with prescripts and regulations 76%

19 OSTP PERFORMANCE OVERVIEW

20 PERFORMANCE ON CORE BUSINESS
 Programme 3: Core Business Procedural and legal advice, analysis, information and research, language, content and secretarial and legislative drafting services for meetings of the National Assembly, National Council of Provinces and their committees. Provide public education, information and access to support public participation. Provide analysis, advice and content support for parliamentary international engagement.

21 MID-TERM PERFORMANCE: CORE BUSINESS
Progress on the Core Business Programme for the reporting period included a remarkable improvement in the implementation of the Core Business Charter; and the development of a business case on the Oversight and Accountability Programme (see figure below).

22 MID-TERM PERFORMANCE: CORE BUSINESS

23 MID-TERM PERFORMANCE: CORE BUSINESS
ADD VALUE Members, Staff, Public MINIMIZE RISKS Financial, Legal, Operational, Reputational REDUCE COSTS Transactional, Process CREATE NEW REALITY Business Intelligence, Process (social, technological, political, business) 1 2 3 4 5 6 7 FOCUS AREA 1: KM MATURITY Knowledge centricity, KM integrated with and embedded in business processes and performance management system. FOCUS AREA 2: KNOWLEDGE GENERATION & SHARING Seminar programme, discussion forums, tacit to explicit knowledge, knowledge retention FOCUS AREA 3: DOCUMENTATION & RECORDS Classification, codification, central repository (uVimba), electronic access and dissemination (MyParliament App, alignment with Communications Strategy), reduced printing, paperless environment (alignment with ICT strategy) FOCUS AREA 4: PERFORMANCE MEASURES & INSTITUTIONAL BEHAVIOUR CHANGE Client satisfaction, learning and growth, quantitative and qualitative performance improvements

24 MID-TERM PERFORMANCE: CORE BUSINESS

25 MID-TERM PERFORMANCE: CORE BUSINESS
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status House Papers: % available on sitting days 100% % of procedural advice within 7 days 0% 85% 84% Legal advice: % within 7 day average - 83% % of policy advice within 7 days % research within time allocated 98% 99% Information requests: % within time allocated 96% % of minutes available in 3 days 66% % of reports within 8 days 77% 92% 91% Official Report (Unrevised Hansard): % within 5 days 39% 31% 95% 94% Interpretation: availability 75% 88% Translations: % within agreed time Documentation: % responses to PAIA requests within prescribed time

26 PERFORMANCE TRENDS: CORE BUSINESS SUPPORT
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status Phase of OVAC Model implementation - Not developed n/a Integrated: Oversight and Accountability Programme Phase of Legislative Model implementation Phase of Cooperative Government Oversight Mechanism implementation Phase of Public Participation Model implementation % Publication of tracking of document 100% Population having access to participate in parliamentary processes Annual target Population participating in parliamentary processes

27 MID-TERM PERFORMANCE: CORE BUSINESS SUPPORT

28 MID-TERM PERFORMANCE: CORE BUSINESS SUPPORT
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status % of International reports tabled 0% 85% 41% 100% % International agreements analysed 75% % Adherence to State Protocol at Parliament

29 Programme 4: Support Services
MID-TERM PERFORMANCE: SUPPORT SERVICES  Programme 4: Support Services Provide institutional communication services, human resource management, information communication technology, institutional support services and Members’ support services.

30 MID-TERM PERFORMANCE: SUPPORT SERVICES
REPUTATION MANAGEMENT & SUPPORT FOR CORE BUSINESS EXPANDED AND EFFECTIVE REACH TO ALL CITIZENS IN THEIR LANGUAGES DEVELOPMENT OF PARLIAMENT UNMEDIATED COMMUNICATIONS CAPACITY % IMPROVEMENT IN RESPECT OF THE AWARENESS OF PARLIAMENT EXCEEDED

31 MID-TERM PERFORMANCE: SUPPORT SERVICES

32

33 MID-TERM PERFORMANCE: SUPPORT SERVICES
PROJECT 1 Back to Basics PROJECT 2 Client satisfaction PROJECT 3 Media monitoring PROJECT 4 Seamless Integrated services strategy Handbook on Members’ Facilities

34 PERFORMANCE TRENDS: SUPPORT SERVICES

35 PERFORMANCE TRENDS: SUPPORT SERVICES
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status % Progress on implementation of stakeholder management plan 0% SMP developed Not developed n/a Stakeholder mapping done % Client satisfaction level - 75% 84% Annual target % Phase of strategy implementation Strategy approved Draft strategy Comprehensive media monitoring Media monitoring & analysis activated Communication training for managers conducted Not held % of population who are aware of business of Parliament 100% % of universal access to web -based and mobile platforms 50% 54% % Client satisfaction level - satisfied with service levels 65% 60% % Increase in talent management index 4% 11%

36 MID-TERM PROGRAMME PERFORMANCE
 Programme 5: Associated Services Provide travel, communication and other facilities for Members of Parliament to fulfil their duties as elected public representatives. Provide financial support to political parties represented in Parliament, their leaders and constituency offices.

37 MID-TERM PROGRAMME PERFORMANCE

38 2016/17 QUARTER 2 PERFORMANCE ON CORE BUSINESS
Indicators 2014/15 annual actual 2015/16 annual target 2015/16 annual actual 2016/17 Mid-year target 2016/17Mid-year actual Status Phase of integrated strategy implementation - N/A Business case developed Average number of days to reimburse members 2.7 days 2.6 days 2.77 days Handbook published by 31 October Draft Handbook developed Number of payments made in compliance with policy 65 60 100% 100% (36)

39 2016/17 Mid-Year Performance:
CONCLUSION 2015/16 Annual Performance: 46.9% 2016/17 Mid-Year Performance: 52% WAY FORWARD: Implementation of a results based and outcomes oriented integrated approach to strategic planning to ensure the achievement of the outcome-oriented goals and objectives of Parliament.

40 Summary 1 Programme 1: Executive Authority provided strategic leadership in ensuring implementation of the NDP HLP established to assess the impact of legislation Programme 2: Institutionalization of outcomes approach and zero-based budgeting. Good progress in supporting members’ capacity as well as sector coordination

41 Summary 2 Programme 3: Good progress in provision of information and advisory support in the core business environment Efforts are being made to improve timely provision of House & Committee Meeting Reports

42 Summary 3 Programme 4&5: Support services is implementing several initiatives aimed at enabling and efficient administration Media Monitoring Tool, My Parliament APP as well as Back to Basics Project Work in progress to provide seamless support to Members of Parliament

43 CONCLUSION Strengthen the institutionalization of Parliament’s Outcomes Framework Leverage and optimise on institutional resources and capabilities Focus on efficiency & cost cutting measures Focus on Leadership & talent management Focus on ICT and Knowledge Management Conducive environment

44 Branch April - September 2016 actuals against budget
April to September 2016 Annual Budget R’000 Expenditure spent % Available Projections Variance Strategic Leadership & Governance 54 660 49 775 91 4 885 Administration 95 947 76 554 80 19 393 Core Business 86 39 389 Support Services 26 199 Associated Services 100 1 484 (10 526) TOTAL 90 91 350 Direct Charge 81 49 998 72 850 88 62 324 Parliament has spent 88% of its budget for the first six months of 2016 as per the original annual performance plans which will be revised upon completion of the current reprioritisation by branches. There is an underspending of R49m on direct charges and indications are that there will be an underspending of R73m at the end of the financial year, which will be surrendered to the National Revenue Fund in terms of Section 23(4) of the FMPPLA. Indications are that Associated Services will have an overspending of R7m at the end of the financial year, which relates to transfers to political parties represented in Parliament, which must be addressed during the adjustment budget.

45 Economic classification: April – September 2016
April to September 2016 Annual Budget R’000 Expenditure spent % Available Projections Variance Compensation of Members 81 49 998 72 850 Compensation of employees 94 27 526 Goods and Services 75 64 497 Capital 14 502 11 866 82 2 636 29 004 Transfers 102 (3 310) (10 526) TOTAL 88 62 324 Parliament has spent 88% of its budget of R million for the first six months of the financial year. The amount allocated to Parliament by National Treasury for compensation of employees (R778,816m) had to be augmented by R142,646m from retained earnings, which is now depleted. The allocation for compensation of employees was based on filled positions as at the end of February 2016, and no allocation was made for vacant positions.

46 Strategic and Leadership Governance
April to September 2016 Annual Budget R’000 Expenditure spent % Available Projections Variance Office of the Speaker 25 680 21 817 85 3 863 51 360 Office of the Chairperson 18 493 18 256 99 237 36 986 Joint Services Treasury Advisory Office 550 1 549 1 100 Parliamentary Budget Office 7 140 6 898 97 242 14 281 Office of the Institutions Supporting Democracy 2 797 2 803 100 (6) 5 593 TOTAL 54 660 49 775 91 4 885 The branch has spent 91% of its monthly budget and is in line with the projections. Spending on compensation of employees to date is 98% while goods and services has spent 70%.

47 Administration April to September 2016 Annual TOTAL 95 947 76 554 80
Budget R’000 Expenditure spent % Available Budget R’000 Projections Variance Secretary’s Office 10 360 9 595 93 765 20 720 Finance Management Office 27 929 23 488 84 4 441 54 632 Internal Audit 6 673 7 876 118 (1 203) 13 345 Strategic Management & Governance 7 869 6 295 80 1 574 15 739 Registrar of Members Interest 1 771 1 547 87 224 3 542 Legislative Sector 21 221 13 347 63 7 874 42 442 Projects 17 124 14 360 2 764 34 248 Events 3 000 46 2 2 954 6 000 TOTAL 95 947 76 554 80 19 393 The branch has spent 80% of its monthly budget of R95.9 million. Spending on compensation of employees is 92% while goods and services is only 68%.

48 Core Business April to September 2016 Annual 176 70 40 106 353 2 150
Budget R’000 Expenditure spent % Available R’000 Budget R’000 Projections Variance Office of the Deputy Secretary Core Business Branch 176 70 40 106 353 Youth Parliament 2 150 3 207 150 (1 057) 4 300 Woman’s Parliament 750 1 500 National Assembly 19 158 16 800 88 2 358 38 316 National Council of Provinces 26 829 18 081 67 8 748 53 657 International Relations and Protocol 19 783 15 707 79 4 076 39 566 Core Business Support 85 19 375 Knowledge and Information Services 85 390 80 357 94 5 033 TOTAL 86 39 389 The branch has spent 86% of its monthly budget of R286million. Spending on compensation of employees is 93% while goods and services is 64%.

49 Support Services April to September 2016 Annual 1 526 1 468 96 58
Budget R’000 Expenditure spent % Available R’000 Budget R’000 Projections Variance Office of the Deputy Secretary Support Services Branch 1 526 1 468 96 58 3 052 Human Resources 37 409 21 971 59 15 438 71 092 Parliamentary Communication Services 30 919 23 403 76 7 516 61 838 Information Communication and Technology 42 625 46 301 109 (3 676) 85 251 Members Support 4 490 4 581 102 (91) 10 207 Institutional Support Services 67 728 60 774 90 6 954 TOTAL 86 26 199 The branch has spent 86% of its monthly budget of R185million. Spending on compensation of employees is 94% while goods and services is 63%.

50 Associated Services April to September 2016 Annual 112 485 107 738 96
Budget R’000 Expenditure spent % Available Projections Variance Members Facilities 96 4 747 Transfer to Political Parties 102 (3 263) (10 526) TOTAL 100 1 484 Associated Services has spent 100% of its monthly budget of R305 million for the period April to September and indications are that there will be an overspending of R10.5 million at the end of the financial year.

51 Direct Charges April to September 2016 Annual 264 899 214 901 81
Budget R’000 Expenditure spent % Available Projections Variance Members’ remuneration 81 49 998 72 850 TOTAL Spending on direct charges at the end of September is 81 percent of the budgeted expenditure for the period April to September. Indications are that there will be an underspending of R72,8m at the end of the financial year. The reason for the low spend is due to the fact that higher budget was allocated on an incremental bases since The unspent funds will be surrendered to National Revenue Fund in terms of section 23 (4) of the FMPPLA.