Review of Implementation of Smart Cities Mission
CHENNAI- TAMIL NADU Review of Implementation of Smart Cities Mission December 23rd 2016
2
Human Resource - SPV Chennai Application received for appointment of CEO,CFO and CS on November 14th It is under process –TNUIFSL Programme Management Consultant – financial bid opened on and tender under process. L1 – PricewaterhouseCoopers Pvt Ltd.
3
Transfer of Funds GoI share of Rs. 188 Cr has already been transferred to SPV of Chennai on GoTN share of Rs. 200 Cr has already been transferred to SPV of Chennai on
4
Reforms Improvement of Revenue through Advertisement Tax – GCC has appointed the consultant for undertaking the feasibility study for augmenting the Revenue Sources of Corporation of Chennai by exploring Advertisements in Parks Municipal Tax and Fee Improvement- Improvement in property Tax Collections GCC - Tender to be called for – As part of Utility / Assets Mapping study – RFP is under preparation for Chennai and to be modified for other cities. Generating additional revenue through Value Capturing Financing Tools GCC - Tender to be called for
5
Traffic and Transportation
Projects – Chennai Smart City Sectors Action Plan Dec 2016 Jan 2017 Feb-2017 March -2017 April -2017 Water Supply and UGSS Conduct Utility Mapping and Assets Management Floating of Tender and Finalization of Consultant Appointment of Consultant Finalization of DPR Traffic and Transportation Design of 23 CC Roads Appointment of Architects/ Consultant to design the 23 Roads Finalize the Road Design Selection of Bids Award of Contract Execution of Project Pedestrianization of Pondy Bazar Area Draft DPR is under Preparation MLCP at T.Nagar Selection of Developer On-Street Parking Feasibility study is under progress
6
Traffic and Transportation
Projects – Chennai Smart City Sectors Action Plan Dec 2016 Jan 2017 Feb-2017 March -2017 April -2017 Traffic and Transportation Provision of Cycle Sharing System in the ABD area Introduction of battery operated vehicles Feasibility study, DPR and Transaction Advisory is under progress Transaction advisory for BoV Selection of Developer Award of Contract Execution of Project SWD Identification of Water logging & flooding area completed Rejuvenation of Mambalam and Nandanam canal Green Space Identified 8 Parks for Development Consultant appointed on DPR preparation is under progress. Selection of Bidders SWM Complete protocol for all forms of Solid Waste with focus on reduction. Entire sequence coupled with stakeholder identification Finalization of protocol and stakeholders identification Pilot Study Study Evaluation Partial Role out Energy Solar Roof Top RFP for Solar Roof top floated by TNUIFSL Study Period Conversion of Street light to LED Feasibility study, DPR under preparation
7
Projects – Chennai Smart City
Sectors Action Plan Dec 2016 Jan 2017 Feb-2017 March -2017 April -2017 PAN City CCTV surveillance DPR is under progress (Traffic Police) Selection of Developer Command and Control Center (CCC) CDAC is preparing the RFP for CCC Award of Contract Execution of Project Middle ware CDAC is preparing the RFP Intelligent Transport System Passenger Information System IIT has prepared the RFP. Finalization of MTC up-gradation. Smart Living Information Center Site to be identified. Appointment of Architect for design SLIC Finalization of Design