LIU & MME ACTIVITIES Fabrication Alessandro DALLOCCHIO on behalf of the EN-MME Workshop 09-03-2017 LIU & MME ACTIVITIES – Fabrication A. Dallocchio.

Similar presentations


Presentation on theme: "LIU & MME ACTIVITIES Fabrication Alessandro DALLOCCHIO on behalf of the EN-MME Workshop 09-03-2017 LIU & MME ACTIVITIES – Fabrication A. Dallocchio."— Presentation transcript:

1 LIU & MME ACTIVITIES Fabrication Alessandro DALLOCCHIO on behalf of the EN-MME Workshop 09-03-2017
LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

2 SUMMARY OF LIU ONGOING FABRICATION ACTIVITIES Q1 2017
~41 JOBS for internal fabrication corresponding to ~1,86MCHF LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

3 ONGOING FABRICATION ACTIVITIES
Leir – linac2 – linac4 – LIU-IONS All jobs are under fabrication or under preparation, no warning. L4 LEM is in fabrication fabrication under tight schedule (by May), fabrication of concerned beam line supports to be launched ASAP (waiting for information). LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

4 ONGOING FABRICATION ACTIVITIES
LIU-PSB - PSB All jobs are under fabrication or under preparation, no major warning. PSB Finemet cavities: Fabrication ongoing within the scheduling so far. (A. D’Andrea - fellow - half paid by LIU on Finemet B.C. working on this huge contract.) PSB H- Inj. : delay cumulated end 2016 due to difficulties in final welding and cleaning as well as due to some re-design and assembling issues. Re-scheduling in agreement with TE-ABT. Prototype for new fast WS in preparation: delivery request August 2017 probably difficult but MME is confident for a delivery in September (no issue from BE-BI side). Concerning WS series production: MS + IT ongoing in collaboration with BE-BI (within scheduling so far). LIU & MME ACTIVITIES – Fabrication A. Dallocchio 09/03/2017

5 ONGOING FABRICATION ACTIVITIES
LIU-PS – PS LIU-SPS – SPS All jobs are under fabrication or under preparation, no major warning. LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

6 Upcoming jobs Upcoming jobs for which we have information from the design office…some of them seem to be on the critical path with respect to provisional deadlines. LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

7 Upcoming jobs SPS ZS INTERCONNECTS (PLAN 10334)
Client : B.Balhan (TE-ABT), Pilote BE : B.Riffaud Disponibilité plans : fin février 2017. Drawings under finalization Delivery date rescheduled with project engineer. Long lead materials to be procured starting from next week. LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

8 Upcoming jobs PS LONGITUDINAL DAMPER (PLAN 10921)
Client : M.Haase (BE-RF), Pilote BE : B.Riffaud Disponibilité plans : mi-mars 2017 (support amplificateurs), fin mai 2017 (porte mobile) Date de livraison souhaitée : fin mai 2017 (support amplificateurs), fin aout 2017 (porte mobile) Support amplificateurs Porte mobile LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

9 Upcoming jobs PS INTERNAL DUMP (PLAN 10025)
Client : F-X.Nuiry (EN-STI), Pilote BE : D.Steyaert Disponibilité plans : fin juin 2017 Date de livraison souhaitée : November 2017. Tight Scheduling? LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

10 Upcoming jobs LINAC3 FARADAY CUP FOR ITF LINE (PLAN 11197)
Client : F.Roncarolo (BE-BI), Pilote BE : D.Steyaert. Disponibilité plans : Fin mai 2017. Date de livraison souhaitée : Fin novembre 2017. Tight Scheduling? Tank + Faraday Cup, similar to ISOLDE design LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

11 Upcoming jobs PSB SEM MONITOR FOR INJECTION MATCHING (PLAN 10071)
Client : C.Vuitton (BE-BI), Pilote BE : D.Steyaert Depart etude: en attente! Disponibilité plans : Fin mai 2017. Date de livraison souhaitée : Décembre 2017. Tight Scheduling? SPECIFICATION BE-BI IN PROGRESS LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

12 Upcoming jobs PS INJECTION SEPTUM/BUMPER 42 (PLAN 10130)
Client : M.Hourican (TE-ABT), Pilote BE : B.Riffaud Description : 3 ensembles complets selon tableau ci-joint. Disponibilité plans : Juin 2017. Date de livraison souhaitée : voir tableau ci-joint. TIGHT SCHEDULING for some sub-assemblies! LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

13 Upcoming jobs SPS TPSC4 (PLAN 10335)
Client : M.Hourican (TE-ABT), Pilote BE : B.Riffaud Description : 2 ensembles complets selon tableau ci-joint. Disponibilité plans : juin 2017. Date de livraison souhaitée : voir tableau ci-joint. TIGHT SCHEDULING for some sub-assemblies! LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

14 Upcoming jobs SPS TPSG6 (PLAN 10336)
Client : l (TE-ABT), Pilote BE : B.Riffaud Disponibilité plans : disponibles. Preparation of the fabrication: to be started. Date de livraison souhaitée : décembre 2017. LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

15 Upcoming jobs vacuum chambers + supports for ETL line (LEIR LIU-IONS)
Client : R. Scrivens / I. Hansen. Info: L. Dassa Description : 10 chambres simples + supports pour installation de 5 nouveaux “pickup” Disponibilité plans : non (l’activité va commencer mi-février) Date de livraison prévue : pas définie (avant Décembre 2017). Tight scheduling??? LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

16 Upcoming jobs PSB SCRAPER/ABSORBER (PLAN 11119)
Client : EN-STI, Pilote BE : N.Chritin Disponibilité plans : Q Date de livraison souhaitée : 2018 (à préciser). TIGHT SCHEDULING? LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

17 Upcoming jobs PS SUPPORTS BT/BTP
Client : K.Hanke (BE-OP), Pilote BE : B.Riffaud Description : plusieurs tables de support pour équipements divers, jacks type LINAC4. Traitements : détentionnement pièces longues. Tests/métrologie/contrôle : métrologie des tables et rainures de positionnement. Disponibilité plans : Q2/Q Date de livraison souhaitée : S (Q3 at the latest). LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

18 Upcoming jobs PS BTV MU41 – Fabrication AP à confirmer par BE-BI
Client : S.Burger (BE-BI), Pilote BE : B.Riffaud Disponibilité plans : Fin août 2017 Date de livraison souhaitée : Décembre 2017. LIU & MME ACTIVITIES – Fabrication A. Dallocchio /03/2017

19 THANK YOU FOR YOUR ATTENTION
Voilà, je vous remercie.


Download ppt "LIU & MME ACTIVITIES Fabrication Alessandro DALLOCCHIO on behalf of the EN-MME Workshop 09-03-2017 LIU & MME ACTIVITIES – Fabrication A. Dallocchio."