PERT & GANTT CHARTS An Introduction
2
Program Evaluation & Review Technique (PERT) -
Is used in planning & organising phase of a project. Uses task times & dependencies to determine the sequence of events & how they control how long the project will take – critical path. Booz Allen Hamilton 1958 – Working on US Naval Contract
3
PERT Diagram - Purpose Purpose
To determine the overall project cumulative elapsed time To determine ways to allocate resources to reduce project cumulative elapsed time
4
PERT DIAGRAM - Process Step 1 – Task Table
Step 2 – Diagram & Dependencies Step 3 – Task Execution Times Step 4 – Cumulative Elapsed Time Step 5 – Critical Path Step 6 – Reduce Project Time
5
PERT STEP 1 – Task Table TASK ID DEPENDENCIES UNITS (DAYS) A Start 2 B
4 C 6 D 5 E C,D 3 F G E,F Finish
6
PERT Step 2 – Diagram & Dependencies
B F START FINISH A C E G D
7
PERT Step 2 – Diagram & Dependencies
B F START FINISH A C E G D
8
PERT Step 2 – Diagram & Dependencies
B F START FINISH A C E G D
9
PERT Step 2 – Diagram & Dependencies
B F START FINISH A C E G D
10
PERT Step 3 – Task Execution Times
B4 F4 START FINISH A2 C6 E3 G2 D5
11
PERT Step 4 Cumulative Elapsed Time
B4 F4 START FINISH A2 C6 E3 G2 D5
12
PERT Step 4 Cumulative Elapsed Time
B4 F4 START FINISH A2 C6 E3 G2 2 D5
13
PERT Step 4 Cumulative Elapsed Time
6 B4 F4 START FINISH A2 C6 E3 G2 2 D5
14
PERT Step 4 Cumulative Elapsed Time
6 B4 F4 8 START FINISH A2 C6 E3 G2 2 D5
15
PERT Step 4 Cumulative Elapsed Time
6 B4 F4 8 START FINISH A2 C6 E3 G2 2 7 D5
16
PERT Step 4 Cumulative Elapsed Time
6 B4 F4 10 8 START FINISH A2 C6 E3 G2 2 7 D5
17
PERT Step 4 Cumulative Elapsed Time
6 B4 F4 10 8 START FINISH A2 C6 E3 G2 11 2 7 D5
18
PERT Step 4 Cumulative Elapsed Time
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
19
PERT Step 4 Cumulative Elapsed Time =13
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
20
PERT Step 5 - Critical Path
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
21
PERT Step 5 - Critical Path
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
22
PERT Step 5 - Critical Path
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
23
PERT Step 5 - Critical Path
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
24
PERT Step 5 - Critical Path
6 B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
25
PERT Step 6 – Reduce Project Time
B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
26
PERT Step 6 – Reduce Project Time
B4 F4 10 8 13 START FINISH A2 C6 E3 G2 11 2 7 D5
27
PERT – Stochastic PERT B 3-4-5 F 2-4-6 START FINISH A 1-2-3 C 5-6-7
10 8 13 START FINISH A 1-2-3 C 5-6-7 E 2-3-4 G 1-2-3 11 2 7 D 3-5-7
28
D 3-5-7 PERT – Stochastic PERT B 3-4-5 F 2-4-6 START FINISH A 1-2-3
10 8 13 START FINISH A 1-2-3 C 5-6-7 E 2-3-4 G 1-2-3 11 2 7 D 3-5-7 D 3-5-7
29
D 3-5-7 PERT – Stochastic PERT B 3-4-5 F 2-4-6 START FINISH A 1-2-3
10 8 13 START FINISH A 1-2-3 C 5-6-7 E 2-3-4 G 1-2-3 11 2 7 D 3-5-7 Optimistic D 3-5-7
30
D 3-5-7 PERT – Stochastic PERT B 3-4-5 F 2-4-6 START FINISH A 1-2-3
10 8 13 START FINISH A 1-2-3 C 5-6-7 E 2-3-4 G 1-2-3 11 2 7 D 3-5-7 Optimistic Normal D 3-5-7
31
D 3-5-7 PERT – Stochastic PERT B 3-4-5 F 2-4-6 START FINISH A 1-2-3
10 8 13 START FINISH A 1-2-3 C 5-6-7 E 2-3-4 G 1-2-3 11 2 7 D 3-5-7 Optimistic Normal Pessimistic D 3-5-7
32
Gantt Chart Shows planning schedule of the tasks for the project
Shows progress to date First Used by Henry Gantt 1910
33
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
34
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
35
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
36
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
37
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
38
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
39
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
40
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
41
Gantt Chart B4 F4 START FINISH A2 C6 E3 G2 D5 6 10 8 13 11 2 7 1 2 3 4
8 13 START FINISH A2 C6 E3 G2 11 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G
42
Gantt Chart – C halved B4 F4 START FINISH A2 C3 E3 G2 D5 6 10 5 12 10
5 12 START FINISH A2 C3 E3 G2 10 2 7 D5 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Days TASKS A B C D E F G