Download presentation
Presentation is loading. Please wait.
1
Introduction to Materials Management
Chapter 3 – Master Scheduling Use print copy for class
2
The Master Schedule is:
The formal link between production planning and actual production The basis for calculation of resources needed The driving force behind the material requirements plan The primary priority plan for manufacturing
3
Information Needed to Develop an MPS
Production Plan data Forecasts Actual customer orders Inventory levels Capacity constraints
4
Relationship to Production Plan
5
Objectives and Steps for the MPS
Maintain good customer service Make effective use of resources Maintain effective levels of inventory Accomplished by: Develop a preliminary MPS Check MPS against capacity and resources Reconcile any differences
6
MPS Example
7
Rough-cut Capacity Planning
Establishes whether critical resources are available Bottleneck operations Critical labor resources Critical material Often uses a resource bill for a single product
8
Example Resource Bill
9
Master Schedule “Focal Points”
Make-to-Stock – Limited end products, many components Make-to-Order – Many end products, fewer components Assemble-to-Order Many end products, combination of components and subassemblies
10
Example MPS Environments
11
Final Assembly Schedule
Assembly according to customer schedule Generally used in an Assemble-to-Order environment Many options Too many possible final configurations to forecast or master schedule MPS usually done at the option level
12
MPS, FAS and Other Planning Activities
13
MPS Planning Horizon Minimum time horizon over which the master schedule must extend to ensure complete planning Calculated as the longest end-to-end lead time of the product structure
14
EXAMPLE - Cumulative Planning Horizon
For this product – Minimum Planning Horizon 12 weeks
15
Delivery Promises MPS is a plan for what production can and will do
Sales delivery promises can be made from “Consumption” of forecasts – Projected available balance Available to Promise calculations MPS values for a given time period left after actual customer orders are subtracted.
16
Available to Promise Example
17
Projected Available Balance
Within demand time fence (forecast not taken into account) PAB = Prior period PAB + MPS – customer orders Outside of demand time fence PAB = Prior period PAB + MPS – greater of customer order or forecast
18
Example of MPS with ATP and PAB (Demand time fence at end of week 3)
19
Time Fences Points in the planning horizon to define the flexibility allowed in the MPS Frozen Zone (closest to current date) Capacity and materials committed to customer orders, forecast generally ignored Senior management approval for changes Slushy Zone Less commitment of materials and capacity Tradeoffs negotiated between marketing and manufacturing Liquid Zone – All changes allowed within limits of the Production Plan
20
Time Fences
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.