NewCo’s Generation Overview
July 2000 Confidential & Proprietary Internal Presentation NewCo’s Generation Overview
2
NewCo Objectives To create a national generation company that will initally have: 6,865 MW’s of net operating capacity 4,798 MW’s in the latter stages of development 8,050 MW’s in turbines que spots 19,713 MW’s of total capacity NewCo will embody Enron’s “trading and marketing” expertise; FPL Energy’s “operational and asset management” expertise
3
Business Model Bring together the strengths of two well managed and respected energy companies Focus solely on the domestic electricity generation markets Maximize greenfield development of highly efficient, gas-fired generating technology and leverage a unique wind asset position Active risk management of asset and commodity positions Opportunistically pursue accretive acquisitions
4
NewCo’s Growth Strategy
NewCo’s growth strategy will be fueled by capitalizing on the significant opportunities creates in the deregulated power market. Through NewCo’s backlog of turbines, the primary means of growth will be the development of MW’s on a national basis The secondary means of MW growth will be through accretive acquisitions on a regional basis NewCo will maintain a focus on asset optimization to enhance the portfolio’s value
5
Strong Parent Company Sponsorship
Enron: FPL Energy:
6
NewCo Core Strengths Assets: Development Team Turbines
NewCo will control in excess of 6,865 MW’s with 4,798 MW’s in the latter stage of development and 8,050 MW’s in turbine que spots Development Team NewCo will have a development team comprised of developers and asset/technical experts from both parent companies Turbines NewCo will have 44 7FA GE turbines to be used in its development efforts
7
NewCo Strengths Sites: Regional Diversification:
NewCo will have over 2 dozen sites in various stages of the permitting and siting processes Regional Diversification: NewCo will have assets in the WSCC, SERC, ECAR, MAIN and Nepool regions Marketing and Trading: Risk Management
8
NewCo Portfolio Breakdowns
9
Location of NewCo’s Assets
FPL Energy Maine Assets: Hydro Units (373) Yarmouth (610) Wiscasset (101) Fort Fairfield (31) Total = 1,115 MW’s Everett, WA (248) Helix, OR (25) MAPP West Bend, WI (30) NPCC Clear Lake, IA (42) Sarnia (320) Bellingham, MA (150) Bellingham, MA (500) MAAC Manhattan (650) Providence, RI (500) WSCC MAIN Richmond, VA (665) Richmond, VA (171) Total = 836 MW’s SPP ECAR Wheatland (503) FPL Energy PJM Assets: Sayrevelle, NJ (150) Delaware Co, PA (50) Delaware Co., PA (MH) (750) Philadelphia, PA (750) Total = 1,700 MW’s Hurt, VA (32) Pastoria (750) LV Cogen (270) Gleason (533) Gaffney, SC (50) Brownsville (492) New Albany (391) Paris, TX (990) Caledonia (498) FPL Energy CA Assets: Harper Lake, CA (80) Calistoga, CA (40) China Lake, CA (4) Altamont Pass, CA (145) Tehachapi, CA (180) Total = 449 MW’s Pecan, TX (250) SERC ERCOT McCamey, TX (75) FPL Assets In Operation Under Construction Development
10
NewCo’s Development Expertise
Enron’s Development Expertise: Development and construction of first 1,431 MW’s was completed in eleven months Experienced development team focused on additional potential plant sites FPL’s Development Expertise: Broad geographic focus increases brown-field development opportunities Extensive power plant operational skills FPL will contribute 44 GE 7FA turbines for immediate and future development
11
Transaction Rationale
Unparalleled scale and scope Complimentary capabilities provides for world class GenCo Provides for multiple expansion and maximum value Creates national portfolio with good asset and fuel mix
12
Keys to Success + World class GENCO ENRON FPL
Capabilities Enron FPL NewCo National Power/Gas Trading and Marketing Technology Infrastructure Construction and development backlog Existing asset base Management/lead sponsorship Operations World class GENCO + ENRON FPL
13
NEWCO (20,000+ MWs) ENRON FPL LENDERS, DEBT HOLDERS INVESTORS
Peakers, Development Projects & Turbines (Total 5,000+ MWs) Sites, People, 3-year toll Projects, Development & Turbines (Total 15,427 MWs) Sites, People $/Note/Equity Services Agreements $/Note/Equity Services Agreements Shares NEWCO (20,000+ MWs) $ LENDERS, DEBT HOLDERS INVESTORS $ Notes
14
NewCo’s Development Sites
Enron Sites: SERC: 5 sites ECAR: 2 sites SPP: 6 sites MAIN: 3 sites NEPOOL: 1 site FPL Energy Sites:
15
Trading and Marketing Org. Chart
16
Construction Management Org. Chart
17
Comparables to NewCo