PROPOSED TH-169 IMPROVEMENTS
W 16th St Access closure in St. Louis Park, Construct Visual Screen. Extend/Lengthen Acceleration & Deceleration Lanes at Cedar Lake Road in Minnetonka and St. Louis Park. Bridge Repair work on Cedar Lake Road over 169 – pier struts are in the project, and concrete surface repair. Bridge repair work on Mainline 169 NB bridge over the BNSF RR. Needs M&O, strip seal joint R&R, bearing & abutment repairs. Pavement Preservation from MN62 to MN55. CPR (concrete repair), Bit M&O, Drainage, Concrete Barrier, Plate Beam Barrier, Noisewall Replacement, Signals, TMS, & ADA Improvement, Nine Mile Creek Bridge Replacement – With that, we shall also replace the Approaches, Noise wall, Sign bridges, Lighting, Storm sewer & the Box culvert. Need to purchase property for a Water quality treatment pond & Flood plain mitigation Our Plan is to Have construction to be completed in 1 year. Requires to close TH 169 between Bren Road and 7th St. From November 2016 to November 2017. The Bridge Replacement is a Design Build. All projects will be let as one contract. With proposed letting date in July 2016.
3
PROPOSED TH-169 IMPROVEMENTS
4
MUNICIPAL CONSENT REQUIRED
Proposed water quality treatment ponds. Close-up of the proposed pond & bridge layout in this area..
5
TRAFFIC IMPACTS 2015 2017 2018 2019 Potential projects
I-494 general purpose lane Hwy 100 bridges (2-year project) Hwy 100 resurfacing & bridge repair I-94/7th Street ramp realignment 2017 5) Hwy 169 project A) Nine Mile Creek Bridge 6) I-35W construct managed lane 7) I-94 concrete pavement repair 2018 8) Hwy 47 resurfacing 2019 9) Rockford Rd bridge over I-494 10) Rockford Rd bridge over Hwy 169 11) 3rd Avenue bridge rehab 12) I-35W resurfacing 13) Hwy 55 bridges—redeck Potential projects B) Orange Line transit station C) Reconstruct I-35W/494 interchange I-494 CONSTRUCT GP LANE BETWEEN Hwy 55 & I-94/694, ADD AUX LANES, REPLACE BRIDGES, CONSTRUCT PONDS Hwy 55 I-94/694 Hwy 100 RECONSTRUCT HWY 100; CONSTRUCT BRIDGES 36th St 26th St $44,000,000 Completed 5/16/2014 July 2014 thru Nov 2016 Hwy 100 BITUMINOUS OVERLAY, DRAINAGE, GUARDRAIL, BRIDGES 36th St I-494 $16,000,000 Being Developed 6/5/2015 July 2015 thru Nov Paving done with weekend full closures; Barrier and bridge work require lane closure I-94 REALIGN WB I-94 EXIT RAMP FROM 5TH ST TO 7TH ST. CONSTRUCT NEW BRIDGE I-94 7th St $10,000,000 Being Developed 5/15/2015 July 2015 to June 2016 RECONSTRUCT I-35W, MANAGED LANE, TRANSIT STATION, BRIDGES, DRAINAGE, TMS, SIGNING, LIGHTING 42nd St I-94 $270,000,000 NEEDED 6/9/ to Nov Project staging scenarios being analyzed. Mesoscopic modeling effort will provide input into final project staging. MAJOR CPR & DIAMOND GRINDING, REPAIR ON 51 BRIDGES, SIGNING, GUARDRAIL, TMS, TUNNEL TILE REPAIR, FIBER WRAP BRIDGE BEAMS Nicollet Ave in Minneapolis Shingle Creek Pkwy in Brooklyn Center $34,000,000 NEEDED 11/18/2016 April 2017 thru Nov Project staging scenarios being analyzed. Mesoscopic modeling effort will provide input into final project staging. BITUMINOUS MILL AND OVERLAY, ADA, INTERSECTION REVISIONS East of I-494 West of Louisiana Ave $5,680,000 NEEDED 2/23/2018 Spring 2018 through fall periodic lane closures, possible overnight closures REDECK - ROCKFORD ROAD over I-494 IN PLYMOUTH Rockford Rd Rockford Rd $2,970,000 NEEDED 2019 Closure of Rockford Rd at I-494. Rockford Rd bridge closures over I-494 and Hwy 169 will be staggered so traffic doesn't freeze up on Rockford Rd BRIDGE REDECK - ROCKFORD ROAD over Hwy 169 IN PLYMOUTH Rockford Rd Rockford Rd $1,970,000 NEEDED 2019 Closure of Rockford Rd at Hwy 169. Rockford Rd bridge closures over I-494 and Hwy 169 will be staggered so traffic doesn't freeze up on Rockford Rd AVE BRIDGE-MAJOR REHABILITATION, RETAINING WALLS, RAILINGS, LIGHTING S. 1st St SE 2nd St $40,000,000 (Does not include north approach work … not fully funded) NEEDED 7/27/2018 Spring 2019 thru Fall Central Ave river crossing will be closed, project duration/staging to be further analyzed Hwy 55 REDECK HWY 55 RAMP 7TH ST & 8TH ST, & SB HWY 55 OVER FRANKLIN AVE 13th St Franklin Ave $4,500,000 NEEDED 7/21/2018 April 2019 thru Sept Anticipate ramp closures for approx 2 months. SB Hwy 55 to remain open, but lane restriction (1/2 deck at a time) B. CONSTRUCT KNOX AVE TRANSIT STATION (PART OF METRO TRANSIT - ORANGE LINE PROJECT) Hwy 13 - Burnsville Minneapolis $150,000,000 NEEDED 2017…not fully funded Approx 2 year construction, impacts on I-35W ramps . RECONSTRUCT I-35W & I-494 INTERCHANGE Richfield Bloomington phase1 - $50,000,000 NEEDED 2017 Phase-1 to be constructed simultaneously as the Met Council Orange Line BRT-Knox Avenue Station phase (planned underpass bridge).
6
AREA PROJECTS Oak Ridge Rd Improvements (Between 494 & Essex)
Blake Road Reconstruction Louisiana Ave (south of Minnetonka Blvd) SWLRT Short description of what those projects area What are the names of the projects for #3 and their descriptions.
7
HOPKINS ROAD NETWORK 11St Street N Excelsior Blvd County Rd 61
Smetana Rd Bren Rd Primarily the traffic will shift to the west , Shady Oak Road (CR 61, Excelsior Boulevard, State Highway 7 for non-freeway routes. 11th street is NS but Hopkins staff has recommended not advertising it as a detour route Work with each of the cities and counties and develop traffic management plan, this process will involve identifying need for signal timing optimization trail blazing signage ect. Temporary traffic signals may be an option too.
8
LOCAL NETWORK CONSTRAINTS Excelsior Blvd @ 11th Ave
9
LOCAL NETWORK CONSTRAINTS 11th Ave @ Railroad Bridge
Content
10
LOCAL NETWORK CONSTRAINTS 11th Ave @ Smetana Rd
11
STAKEHOLDERS Stakeholder support Prepare for construction Construction
(now to November 1, 2015) Prepare for construction (November 1, 2015 to November 1, 2016) Construction (November 1, 2016 to November 1, 2017)
12
OUTREACH PLAN & SCHEDULE
The first open house is scheduled for August 19 at the Hopkins Arts Center (what time?) Mailings will go out early August for this event. The first open house is scheduled for August 19 at the Hopkins Arts Center. Mailings will go out early August for this event. Formal and informal meetings, as early as this week, will take place with small businesses, residents, office parks, and the larger corporations. (names of the business or associations identified in Hopkins) Next summer, as we get closer to construction, the outreach will involve attending multiple local festivals and other popular events. Outreach to date has involved MnDOT’s communication to the cities and regulatory agencies.
13
POSSIBLE OPEN HOUSE CONCEPTS
Lunch time open house – host for 1-2 hours close to any of the business parks during the weekday lunch time for either a brown bag session or partner with food trucks to have them locate near the meeting Evening open house – partner with a local business to provide refreshments and seating or host the open house at a local community center for a more formal meeting presentation
14
PROJECT INFORMATION SHEET http://www. dot. state. mn
15
MnDOT PROJECT UPDATES Questions…
I know this is a lot information to take in in one go.. We still plan to share these maps with City Staff.. Working/Living document with possibility of dates changing as project development continues. Thank you once again.
16
PROJECTS IN HENNEPIN COUNTY
Current 494 third lane project – from I-394 to I-94. Substantial completion in Minor work (potential off-road work in spring 2017) HWY 610 connection to I-94 in Maple Grove. From County Road 81 to I year project expected to be completed in Fall of 2016. I-394 Road Resurfacing. From Hwy 100 in Golden Valley to I-94 in Minneapolis. Expected to run from this month (June 2015 ) to October 2015. I-35W Reconstruction, Lake Street-Transit Station, Bridge Repairs, reconstruct interchange ramps. Project is from 42nd St to I-94 major construction spring 2018, potential work in 2017 I-94 Pavement Preservation including Bituminous Overlay, some CPR – concrete work in some segments, & Bridge repair work. from south of the tunnel to I-694 – 2017. HWY 62 Road Resurfacing. From Tracy Avenue to HWY 212. Scheduled for 2018. South West - LRT through the cities of Minneapolis, St. Louis Park, Hopkins, Minnetonka & Eden Prairie (passing in close proximity to Edina)– Major construction in Planned to be in service by 2020. Bottineau – LRT project – through the cities of Minneapolis, Golden Valley, Robbinsdale, Crystal and Brooklyn Park, Major construction in Passenger operations in 2021.