The LHCb Installation Story
February 2002 – August 2008 Slides by R.Lindner EDMS
2
February 2002 Cavern ready for detector installation
3
May 2002 August 2002
4
January 2003 Start of the LHCb installation with the dipole magnet
5
June 2004 Start of Muon filter assembly
6
October Magnet assembled
7
November 2004 Additional rails for the Calorimeter system
8
February 2005 Cavern before Calorimeter installation
9
March 2005 Piling up ECAL modules
10
April 2005 First HCAL module installed
11
May 2005 RICH 1 shielding approaches finial position
12
June 2005 Electromagnetic , Hadronic Calorimeter & Muon Filter
13
July 2005 Calorimeter just before completion
14
November 2005 RICH 2 moves into its position
15
December 2005 Installation of Muon towers
16
May 2006 VeLo tank moves in
17
Spring 2006 PS/SPD installation
18
June 2006 Installation of OT bridge
19
June 2006 Installation of OT bridge
20
June 2006 RICH 1 gas enclosure
21
October 2006 Installation of Inner Tracker frames
22
October 2006 Start of Outer Tracker installation
23
November 2006 First Muon chambers on the wall
24
December 2006 Start of Trigger Tracker installation
25
February 2007 Beam pipe installation
26
June 2007
27
April 2008 VELO detector installation October 2007 VeLo detector halves
28
February 2008 TT Module installation
29
July 2008 Closing the detectors
30
August 2008
31
and all of you who made it happen !!!
Experimental Area Team Many Thanks and all of you who made it happen !!!