Nodal Status Report: Program Controls Update

Similar presentations


Presentation on theme: "Nodal Status Report: Program Controls Update"— Presentation transcript:

1 Nodal Status Report: Program Controls Update
Janet Ply TPTF October 13, 2008

2 Baselined Schedule Weekly Cycle
PMO Controls Update Baselined Schedule Integrated Master Schedule baselined on Sept. 17 PMs formally update their project schedules weekly, following a standard process PMs produce weekly status reports Weekly Nodal program / project status meetings with focus on critical path tasks behind schedule, risks and issues Weekly Cycle Weekly Cycle Schedule Updates . Project / Program Reviews Status Reports October 13, 2008 Nodal Status Report - Program Controls

3 Integration Priorities
PMO Controls Update – 2 Program Critical Path Tasks Behind Schedule Milestone Report Risk/Issue Log Integrated Releases Integration Priorities Sample Reports / Tools PMO provides each week: Review of critical path at program and project level A report to the PMs of tasks behind schedule A milestone report for the next week and the next 30 days An updated program risk/issues log A review of integrated releases plans (“bucket list”) A review of integration priorities and status Requirements audit in progress Internal Quality Assurance project audits scheduled to start in November . October 13, 2008 Nodal Status Report - Program Controls