1 FORSYTH COUNTY SCHOOLS 2014 CAPITAL PROGRAM TIMELINE LOCATION
LOCATION CONSTRUCTION PROJECT ARCHITECT A/E START GC/CM OPEN SUMMARY STATUS HIGH SCHOOL ADDITIONS AND MODIFICATIONS North Forsyth H.S. Stadium visitors concession and restroom BRPH Done Charles Black Certificate of Occupancy issued 8/14/14 Additions & Cafeteria FSF Barton Malow FM Certificate of Completion issued 5/31/16 , Furniture installed Gymnasium FM Certificate of Occupancy issued 6/24/16 Renovations (Classrooms,Band,Choral) Aug-17 In progress Forsyth Central H.S. Additions CPL Parrish FM Certificate of Occupancy issued 5/17/16 , Furniture installed Renovations (STEM labs) South Forsyth H.S. MSSA Balfour Beatty FM Certificate of Occupancy issued 6/2/16 FM Certificate of Completion issued 6/8/16 , Furniture installed Renovations (Classrooms, Culinary) Lambert H.S. Additions- 19 classrooms , band FM Certificate of Completion issued 5/27/16, Furniture installed Renovations (Engineering & Health Labs) FM Certificate of Completion issued 7/27/16, Furniture installed Artificial Turf Field (IGA $ , not bond) Breedlove Shaw West Forsyth H.S. Additions - Performing Arts (Band,Choral) Started Cooper & Co Apr-17 foundations in progress Renov's (Art,Computer,Engineering Labs) Denmark H.S. Denmark HS New Construction Jun-18 sitework , foundations in progress Alliance Academy Alliance Academy New Construction GC Submit Permit and Final Dwgs to DOE 8/19/16 9 Prequalfied General Contractors , 9/2 RFP release

2

3

4

5

6

7

8 MIDDLE SCHOOL ADDITIONS AND MODIFICATIONS
Liberty M.S. Modify front entrance for security James Buckley Done Complete Modifications cafeteria Sep-15 Kevin Price Aug-17 Cafeteria renovations to be completed Expand Band Classroom Band Addition to be complete 11/1/16 Little Mill M.S. Modify front drive entrance McFarland Dyer Sep-16 Mar-17 North Forsyth M.S. Media center , band , team room Band , Media Renovations completed, Adds 11/1/16 HVAC replacement / modification CGE Capital City Aug-15 HVAC completed Otwell M.S. Expand engineering lab , band Band Renovation completed , Adds 11/1/16 Piney Grove M.S. Front Drive sidewalk in progress Modify technology lab Tech Lab Renovation to be completed South Forsyth M.S. 23 Classroom Addition RaLin FM Certificate of Completion issued 5/24/16, Furniture installed Expand Media Ctr ,Cafeteria, Modify PA Expansions completed 8/2/16 Riverwatch M.S. 24 Classroom Addition FM Certificate of Completion issued 5/19/16, Furniture installed Expand band room Band Renovation to be completed 8/1/16 Vickery Creek M.S. Expand Media Ctr , Engineering Lab Addition foundations in progress DeSana MS MS #10 New Construction Evergreen FM Certificate of Occupancy issued 6/15/16 , furniture installed Middle School #11 MS #11 land purchase search, due dilligence options in progress

9 ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS
Brandywine ES Brandywine ES New Construction LPBC Done Charles Black Certificate of Occupancy issued 6/9/16 , furniture installed Midway ES Sanitary sewer service CEC Started MidSouth Completed 7/12/16 Daves Creek HVAC replacement / modification CGE Waters Aug-15 HVAC completed Settles Bridge Capital City General security,media ctr, partitions, parking TBD