Presentation is loading. Please wait.

Presentation is loading. Please wait.

PROVINCE OF THE EASTERN CAPE DEPARTMENT OF HOUSING LOCAL GOVERNMENT AND TRADITIONAL AFFAIRS DWAF PORTFOLIO COMMITTEE HEARINGS ON BUCKET ERADICATION PROGRESS.

Similar presentations


Presentation on theme: "PROVINCE OF THE EASTERN CAPE DEPARTMENT OF HOUSING LOCAL GOVERNMENT AND TRADITIONAL AFFAIRS DWAF PORTFOLIO COMMITTEE HEARINGS ON BUCKET ERADICATION PROGRESS."— Presentation transcript:

1 PROVINCE OF THE EASTERN CAPE DEPARTMENT OF HOUSING LOCAL GOVERNMENT AND TRADITIONAL AFFAIRS
DWAF PORTFOLIO COMMITTEE HEARINGS ON BUCKET ERADICATION PROGRESS Parliament of South Africa 10 October Presented By MEC T. Xasa

2 Presentation Content Provincial Overview Backlogs Funding Expenditure Key Challenges Support Critical Project Challenges

3 Provincial Overview, Sept 2007
05/06 Formal Backlog 05/06 backlog translated to R464m Total Eradicated, end Sept Completed Project Value R228m Remaining Backlog, end Sept 07/08 backlog translates to R236m 07/08 Available Funding R236m Eradicated in Sept Expected Monthly Rate 4577pm Upscale progress by 4 X times

4 Remaining Backlog, Sep 2007

5 2007/2008 Funding Streams 07/08 MIG Allocation: R148, 281, 000
07/08 MIG Additional: R49, 590, 000 (Additional available from dplg, mid Oct 2007) 07/08 DLGTA Allocation: R22, 991, 000 07/08 DLGTA Additional: R12, 613, 000 (Additional available from DHLGTA, end Oct 2007) 07/08 Municipal Reported: R2, 834, 841 (Funding Reported by municipalities) 07/08 Total EC: R236, 309, 841

6 2007/2008 Allocations / Expenditures
Municipality Total Allocations (incl. additional) Total Expenditure (incl. additional) % Expenditure Nelson Mandela B M 6, 650, 000 456, 000 7% Ukhahlamba DM 51, 500, 000 1, 043, 000 2% OR Tambo DM 3, 117, 000 2, 825, 000 91% Alfred Nzo DM 779, 000 401, 000 51% Chris Hani DM 73, 076, 000 14, 026, 000 19% Buffalo City LM 520, 000 100% Amathole DM 49, 203, 841 125, 000 0.3% Baviaans LM 9, 752, 000 2, 015, 000 21% Blue Crane LM 11, 029, 000 267, 000 2.4% Ikwezi LM 11, 200, 000 711, 000 6.3% Sundays RV LM 4, 705, 320 Makana LM 7, 827, 680 4, 867, 000 57% Kou Kama LM 6, 950, 000 0% EC TOTAL 236, 309, 841 38, 911, 320 16%

7 CONSTRAINTS / CHALLENGES RECOMMENDED SOLUTIONS
BEP Key Challenges CONSTRAINTS / CHALLENGES RECOMMENDED SOLUTIONS Community expectations (Water Borne) vs. tight time-frame (3 moths) Up-gradable (pre-cast) system: Political engagement with Communities to have buy-in.  Inadequate Technical & Project Management Capacity in the WSAs Roll-out Hands-on Support Initiatives (DWAF Engineers, Siyenza-Manje to WSAs  Absorption capacity to spend late transferred allocations, by Dec 2007 Provide more resources and encourage multi-contracts approach Projects still at pre-construction phase: Meeting the Dec 2007 target Adopt Business unusual approach by short-circuiting SCM processes to allow 3 to 2 months construction period

8 CONSTRAINTS / CHALLENGES RECOMMENDED SOLUTIONS
BEP Key Challenges CONSTRAINTS / CHALLENGES RECOMMENDED SOLUTIONS Environmental sensitive sites have delayed projects implementation EIA exemptions should be fast tracked through EC-DEAET and DEAT HOD’s involvement  Hard rocky sites, cause delay due to unforeseen financial escalations Rope-in other departments to provide machinery to avoid possible financial escalations  High Tendered Amounts vs. Projects Budgets, delay projects implementation For now, only financially stable contractors should be invited to tender to avoid re-tendering Termination of contracts due to poor performance also cause delays. Sub-contracting than terminations should be enforced through sessions

9 Hands on Support DBSA-Siyenza Manje Programme
Deployed DBSA Engineers = 11 Provincial MIG Support = 2 Municipal PMU support = 9 Young Technicians = 12 District Cluster Facilitators = 4 Municipal PMU Support = 8 DHLGTA-Project Consolidate Capacity Assessment Engineer = 1 MIG-PMU Experts / Engineers = 2 DWAF BEP Hands-on Support Deployed Technical Officials = 2 Contracted Engineers = 7 DPLG BEP US-AID Support Technical Experts / Engineers = 2

10 Situational Analysis OR Tambo DM No. of Projects 3 Initial Backlog 716
Eradicated Backlog 607 Remaining Backlog 109 Construction Stage 109 Tender Stage 0 Design Stage 0 KEY CHALLENGES SOLUTIONS Mhlontlo: Ponds construction Up-pace the construction Ntabankulu: Septic tanks overflows treat for new targets O&M should be prioritised to avoid creation of new targets Meeting the target? YES No remedy needed

11 Situational Analysis Amathole DM No. of Projects 6
Initial Backlog Eradicated Backlog 6 759 Remaining Backlog Construction Stage 3 804 Tender Stage 0 Design Stage 0 KEY CHALLENGES SOLUTIONS Newtown-Bhofolo: 1473 units remaining: Phase 4 to start soon. Multi-contract approach should be considered Bedford-Adelaide: 1522 units remaining: Construction experiences hard rock. Rope-in other departments to provide machinery to avoid possible financial escalations Meeting the target? The pace is too slow No Upscale the current construction pace at least 4 times.

12 Situational Analysis Chris Hani DM No. of Projects 12
Initial Backlog 8 700 Eradicated Backlog 5 915 Remaining Backlog Construction Stage 2 730 Tender Stage 55 Design Stage 0 KEY CHALLENGES SOLUTIONS Lady Free: 55 Units: Has been retendered more three times Only financially stable contractors should be invited to tender to avoid re-tendering Emalahleni: Indwe and Doodrecht, R81m, impossible spend within 3 to 2 months Up-gradable system only option: Political engagement with Communities to have buy-in. Meeting the target? Huge funds Absorption Capacity No Under construction: Up-gradable system and encourage multi-contracts approach

13 Situational Analysis Ukhahlamba DM No. of Projects 7
Initial Backlog 6 746 Eradicated Backlog 3 483 Remaining Backlog Construction Stage 1 251 Tender Stage Design Stage 432 KEY CHALLENGES SOLUTIONS Gariep: Steynsburg: 1580 at tender stage. No bulk water supply in place. VIP (up-gradable system) has been agreed with the communities, meanwhile bulk is under constr. Senqu: Barkley East: 1171 under construction. No bulk water supply in place. VIP with Pre-cast structure are temporally provided and will be upgraded to water-borne Meeting the target? Water-borne vs. Dec Target YES Community Buy-in to temporal arrangement.

14 Situational Analysis Cacadu DM No. of Projects 21
Initial Backlog 4 459 Eradicated Backlog 1 801 Remaining Backlog Construction Stage 2 558 Tender Stage 100 Design Stage 0 KEY CHALLENGES SOLUTIONS Makana: 768 backlog will: Archaeological site (60 units affected) No EIA exemptions is fast tracked through EC-DEAET and DEAT HOD’s involvement. Ikwezi: Janesville with 667 backlog: No funding (shortfall R6.6m) YES DHLGTA will avail the shortfall by end Oct 07, allowing for 2 months construction Baviaans with a shortfall of R6.01million for the bulk 3 projects

15 Situational Analysis Cacadu DM
KEY CHALLENGES SOLUTIONS Nelson Mandela Bay M: 93 units under construction YES Upscale the current construction pace at least 4 times. Kou-Kamma: 100 at tender stage and 26 at construction No Business unusual approach by short-circuiting SCM processes Sunday’s River Valley: 17 top-structure completed Bulk under construction Funding available, need to upscale the construction of bulk connector Blue Crane Route: 612 Units: Khanyiso construction (429 units) experiencing hard rock Funding available, Rope-in other departments to provide machinery to avoid possible financial escalations

16 Conclusion A higher level (Chief Directorate / DDG) forum has been established with all affected sector departments, in ensuring that there is optimal resourcing of the BEP and integration thereof. Linked to the forum is the Mayor/ Municipal Managers of the WSAs forum, that should sit fortnightly to monitor progress on the ground The Forum will also streamline Hands-On Support initiatives and ensure that DHLGTA strengthens its coordination role and WSAs capacity needs are prioritised. A Provincial Communication Strategy has also been developed, to ensure that, achievements, best practices are communicated to all stakeholders DHLGTA collaboration with EC-DWAF, and other sectors DHLGTA is committed in ensuring that bucket system in the Eastern Cape is eradicated within the set national target.

17 Thank You


Download ppt "PROVINCE OF THE EASTERN CAPE DEPARTMENT OF HOUSING LOCAL GOVERNMENT AND TRADITIONAL AFFAIRS DWAF PORTFOLIO COMMITTEE HEARINGS ON BUCKET ERADICATION PROGRESS."

Similar presentations


Ads by Google