Presentation is loading. Please wait.

Presentation is loading. Please wait.

TURBINE CRANES NEA36 Turbine Crane.

Similar presentations


Presentation on theme: "TURBINE CRANES NEA36 Turbine Crane."— Presentation transcript:

1 TURBINE CRANES NEA36 Turbine Crane

2 General System Diagram of Palo Verde Nuclear Generating Station
PLANT STATUS! 8 CONTAINMENT SPRAY Equipment Cooling Polishing Demineralizers Condensate Pump General System Diagram of Palo Verde Nuclear Generating Station Generator LP Turbine HP MSSS Bldg. ADVs MSIV MSSVs Refueling Water Tank Containment Building Turbine Building Z MTSV MTCV Auxiliary Feedwater System Safety Injection Systems Legend:: Main Steam System Main Feedwater System Main Condensate System Circulating Water System Reactor Coolant System Auxiliary Spray Pump Low Pressure Safety Injection Pump High Pressure Safety Shutdown Heat Exchanger Safety Injection Steam Pressurizer Control Rods Reactor Core Coolant From Feedwater Pumps Regulation Valve Main Feedwater (HP) Heaters (LP) Main Condenser Moisture Separator Reheaters Bypass Valves Circulating Water Pump Cooling Tower and Fans Transformer To Switchyard Containment Sump Turbine Crane PV Daily Status Report

3

4 Turbine Crane

5 Review instructions to ensure workable and adequate
Walk downs Review instructions to ensure workable and adequate Right Parts/materials/tools Permits Relevant Operating Experience Turbine Crane

6 Hazards identified AND what are actions are you taking
Pre Job Briefs Understand the Task Critical Steps identified and OE used AND what actions are being taken in reference to these two areas Two Minute Drills: Hazards identified AND what are actions are you taking Turbine Crane

7 Procedure Use & Adherence WO / procedure in hand & latest revision
Place keepers being used Sign steps as you go Follow & understand steps - STOP if can't or don't Turbine Crane

8 TURBINE CRANE Terminal Objective
Given references provided by the Instructor, the Plant Electrician will maintain Turbine Building Cranes as demonstrated by achieving a minimum of 80% on a written examination. Turbine Crane

9 . Turbine Crane

10 PRE-JOB BRIEF Identify Critical Steps Identify Error Precursors
Worst thing that can happen Error prevention defenses to be used Actions to assure proper configuration control Turbine Crane

11 TURBINE CRANE EO Discuss the Troubleshooting Techniques performed on the Turbine Building Crane including Fault Code identification.

12 Troubleshooting Methodology:
To effectively troubleshoot the Turbine Building Crane, you really need to observe the indications associated with the failure. The crane operator will usually be the best point of reference as to the degree and change of symptoms that are occurring or have occurred. The next level of indication will be the VFD and then PLC indications for the faults. Another level of indication is often times sensory. Turbine Crane

13 VFD Codes Alarm codes may or may not result in a Base Block.
All BE (BE1 – BE7) (BE= Brake or Torque alarms A Base Block (BB) will occur with all BE alarms with the exception of BE6 Base Block (BB) = The signal to the bases of the Insulated Gate Bipolar Transistors (IGBT) have been blocked or removed. This will prevent the transistors from “turning on” and conducting. Turbine Crane

14 VFD Codes Alarm Codes: No Reset function is required
An output will occur from the drive contacts M5/M6 Alarms BE1/BE2/BE3 are recorded in Fault History (U2-01, U2-02 and U3-01…) BE6 is not recorded Turbine Crane

15 VFD Codes All codes with the exception of BE (BE1 – BE7)
Fault Codes:  All Fault codes will result in a Base Block. All codes with the exception of BE (BE1 – BE7) A Reset function of some form IS required An output will occur from the drive terminals MA/MB/MC All Faults are recorded in Fault History (U2-01, U2-02 and U3-01…) and displayed on keypad. Turbine Crane

16 Common Faults **Typically a major fault (i.e. direct motor shorts)
2.5 X Drive rated current / 0min (instantaneous) **Typically a major fault (i.e. direct motor shorts) ***The OL1, OL2 & OC faults will have balanced output currents . Turbine Crane

17 Common Faults OL1 – Motor Overload Fault = 150%
1.5 X Motor FLA / 1min. (programmable) The higher the current, the shorter the time. OL2 – Drive Overload Fault = 150% 1.5 X Drive Ref. Current / 1min **95% of OL1 & OL2 faults are caused by due to mechanical Problems (i.e. brakes, load problems etc…) OL1 – Motor Overload Fault = 150% 1.5 X Motor FLA / 1min. (programmable) -The higher the current, the shorter the time. OL2 – Drive Overload Fault = 150% 1.5 X Drive Ref. Current / 1min **95% of OL1 & OL2 faults are caused by mechanical problems (i.e. brakes, load problems, etc…) Turbine Crane

18 Common Faults GF – Ground Fault = Sums are all phases should be 0
– ort Circuit Fault (typically motor short) LF – Output Phase Loss = looks for an open phase. OL1 – Motor Overload Fault = 150% 1.5 X Motor FLA / 1min. (programmable) The higher the current, the shorter the time. OL2 – Drive Overload Fault = 150% 1.5 X Drive Ref. Current / 1min **95% of OL1 & OL2 faults are caused by due to mechanical Problems (i.e. brakes, load problems etc…) Turbine Crane

19 Common Faults OV – Over-voltage = DC Bus voltage (typically 820Vdc for a 480Vac Drive) UV – Undervoltage = DC Bus voltage (typically 400V for 480Vac drive) OL1 – Motor Overload Fault = 150% 1.5 X Motor FLA / 1min. (programmable) The higher the current, the shorter the time. OL2 – Drive Overload Fault = 150% 1.5 X Drive Ref. Current / 1min **95% of OL1 & OL2 faults are caused by due to mechanical Problems (i.e. brakes, load problems etc…) Turbine Crane

20 Turbine Crane

21 Turbine Crane

22 Turbine Crane

23 Turbine Crane

24 Turbine Crane


Download ppt "TURBINE CRANES NEA36 Turbine Crane."

Similar presentations


Ads by Google