Presentation is loading. Please wait.

Presentation is loading. Please wait.

San Luis Potosi – New plant April 24th 2015

Similar presentations


Presentation on theme: "San Luis Potosi – New plant April 24th 2015"— Presentation transcript:

1

2 San Luis Potosi – New plant April 24th 2015
HOME San Luis Potosi – New plant April 24th 2015 Schedule and Description Process

3 HOME Schedule program

4 HOME 2016-February 1st Area of paint shop ready for paint shop erection Area between B-1 and E.5-4 •Status Progress expected • Watertight ( roof) above the defined area • Foundations of the paint shop completed : 100% of the main pit • Slab completed • Paintshop mezzanine civil work, slab, masonnery done • Pit and mezzanine stairs, hand rails on the mezzanine • Painting of the structure above this area • Sprinkler above this area installed • Lighting above this area installed • Walls and fences all around the site

5 2016-March 1st HOME Area of paintshop ready for paintshop erection
Area between A-1 and F-6 • Status- Progress expected • Watertight (roof) • Slabs in the area completed • Walls, cladding, doors : line 1, from A1 to A-5, from F-1 to F-6 • Paintshop trench/civil work completed • Crane gantry girders /rails completed with rails survey/dimensions • Painting, sprinkler, lighting completed above the area • Fire pumps room and tanks foundations • Outside utilities pads : silos, chillers pads, RTO pad

6 Paintshop and technical rooms - crane bay
HOME 2016-April 1st Paintshop and technical rooms - crane bay • Building and canopy watertight (roof) and building airtight ( walls, doors, louvers, …) • 100% of the building and canopies slabs • 3 docks in F-6 operational • All the rooms above and below the mezzanine completed including sprinkler, lighting, painting. • Raw material room and grinder room completed • Specified finishing of the paintshop rooms completed • Utilities rack in the crane bay ( line B ) • Fire pumps room, water tanks completed • Guard houses

7 2016-April 15TH HOME Utilities 2016
• All utilities connected ( water, natural gas, sewer) • Electrial power certified : at least temporary permit for the main building • Injection bay completed including sprinkler, painting, lighting • Server room civil work

8 2016-May 1st HOME • Fire protection / commissionning 2016
• Fire pumps room, water tanks completed • 95% of the sprinkler in main building, canopies, offices • Guard houses • Server room completed ( including painting, sprinkler, power ) • Punch lists for all the areas, utilities, activities • Commissionning of the equipement in the building scope : 60% done • Training : 50%

9 2016-June 1st HOME Delivery of the site 2016 – June 1st
• Final occupancy permit • Delivery of 100% of the buildings and offices • 100% of the commisionning of the building scope • Documentations, • Training : 100% done

10 New Plant Project


Download ppt "San Luis Potosi – New plant April 24th 2015"

Similar presentations


Ads by Google