The University of Massachusetts Building Authority
Boston-Access & Opportunity Committee Bi-Monthly Report January 19, 2016 Patricia A. Filippone, Executive Director
2
UMBA Staffing Director of Capital Projects – Joe Naughton
Capital Projects Coordinator – Sean Regan Compliance Analyst – Maggie Drouineaud
3
UMass Boston Project Labor Agreement Projects
University Hall Stage: Construction Estimated Construction Cost: $105 M OPM: Joslin, Lesser + Associates CM: Gilbane, Inc. Steve Duvel, Senior Project Executive Jim Driscoll, Senior Project Manager Danielle Skilling, EEO Compliance Officer Utility Corridor and Roadway Relocation Stage: Bidding/Construction Estimated Construction Cost: $148 M CM: BOND Bob Mischler, Project Executive Mike Spodek, Senior Project Manager Elio DiBiase, Project Manager Samantha Bond, Assistant Project Manager
4
Workforce Utilization Snapshot
GAB 1 UCRR TOTALS Total Hours 404,275 hours 207,220 hours 611,495 hours Female (10%) 24,491hours 15,430 hours 39,921 hours 6% 7% Minority (25%) 120,954 hours 48,853 hours 169,807 hours 30% 24% 28% Resident (50%) 139,457 hours 60,055 hours 199,512 hours 34% 29% 33% Veterans (10%)* 19,820 hours 5,669 hours 25,489 hours 5% 3% 4% *Veterans goal was not established in the PLA and is measured on a “Best Faith Efforts” basis.
5
MBE/WBE Construction Business Participation
GAB 1 UCRR Totals Committed-to-Date $105,000,000 $123,682,871 $228,682,871 MBE $7,074,368 $11,017,117 $18,091,485 7% 9% 8% WBE $6,064,330 $6,726,566 $12,790,896 6% 5% M/WBE (10.4%) $13,138,698 $17,743,683 $30,882,381 12% 14% 13% # M/WBE Firms 16 17 % Contracts Awarded-to-Date 100.0% 97.39% *Some firms are both M and WBE.
6
University Hall Project – to – Date M/WBE Update Boston Residents 34%
Minority 30 % Female 6% Veterans 5% M/WBE 13% Percentage of Contracts Awarded-to-date – 100 %
7
University Hall Results by Contractor- December 2015
8
University Hall Results by Contractor- Project to Date
9
General Academic Building 1 Results by Trade- December 2015
10
General Academic Building 1 Results by Trade –Project to Date
11
GAB 1 Workforce Diversity December 2015
Project-to-Date Residents – % Minority – % Female – % Veterans – % June 2015 Residents – % Minority – % Female – % Veterans – %
12
GAB Project – M/WBE Construction Business Detail
13
Utility Corridor & Roadway Relocation Project
Project – to – Date M/WBE Update Boston Residents 29 % Minority 24% Female 7% Veterans 3% M/WBE 14 % Percentage of Contracts Awarded-to-date 97%
14
Utility Corridor and Roadway Relocation Results by Contractor – December 2015
GOAL - 50% GOAL - 25% GOAL - 10% MONTHLY: December VETERAN RESIDENT MINORITY FEMALE Monthly Workforce CONTRACTOR Total Hours Number of Hours Monthly Percentage 10 Acme Waterproofing 556 0% 64 12% 2 BOND 374 100% 184 49% 3 Cannistraro 120 80 67% 1 Chapman Construction Group (sub to Fischbach) 152 Federal Concrete (sub to Marguerite) 60 17 Fischbach and Moore 1760 1058.5 60% 548.5 31% 228 13% 8 JDC Demo (sub to Derenzo) 178 66 37% 86 48% 5 J Derenzo 677 177 26% 4 Marguerite Concrete 28 SimplexGrinnell 128 54 TOTALS: 4033 1642.5 41% 1034.5 405 10% MONTHLY PERCENTAGES:
15
UCRR Results by Contractor – Project to Date
Boston Plan Subcontractor Totals: Project: UMASS BOSTON UCRR BI-MONTHLY ACCESS & OPPORTUNITY MEETING Dec-2015 GOAL - 50% GOAL - 25% GOAL - 10% PROJECT-TO-DATE: VETERAN RESIDENT MINORITY FEMALE PTD Hires CONTRACTOR Total Hours PTD Hours PTD Percentage PTD Hours PTD Percentage 12 Acme Waterproofing 619 0% 67 11% 70 3 Atlantic Contracting (sub to JF White) 60 4 7% 45 Beacon Piping (sub to J Derenzo) 35710 5115 14% 8016 22% 3315 9% BOND 8651 7570 88% 1568 18% 334.5 4% 84 Cannistraro 14468 5319 37% 3651 25% 500 3% 1 Chapman Construction Group (sub to Fischbach) 1376 100% 18 Chapman Waterproofing 992.5 442.5 45% 396 40% D & S Commercial Masonry 5 13 Federal Concrete (sub to Marguerite) 2290 675 29% 710 31% 30 Fischbach and Moore 18535 9261.5 50% 5134.5 28% 2743 15% 32 JDC Demo (sub to Derenzo) 3534 1014 1076 30% 108 43 J Derenzo 48433 24% 8038 17% 2814.5 6% JF White 9126 665 2763.5 827 930 10% 11 Marguerite Concrete 105 8 8% NewRoads Environmental (sub to Derenzo) 652 644 99% RM Technologies 437 210 48% Schneider Electric SimplexGrinnell 3740 136 544 Stateline (sub to Schneider) 1866 664 36% Sullivan & McLaughlin Co. (sub to Fischbach) 252 58 23% 13% 2 United Power Group (sub to Fischbach) 20 26 Algar (sub to McCourt) 2358.5 345 888.5 38% 128 5% 22 Allied Pile Driving (sub to JW Flett) 340 27% 456.25 107 Chapman Construction Group (sub to Mass Bay) 496 312 63% 6 Diversified (sub to RM Technologies) 484 2% 7 DON Martin Corp. (sub to McCourt) 31.5 57% Easton Concrete (sub to JW Flett) EJ Prescott (sub to JW Flett) FLA Transportation (sub to JW Flett) 1022 749 73% 439 43% 755 74% Frank Rounds Company (sub to Cannistraro) 361.5 Hamilton Nee (sub to JF White) 40 JW Flett 3133.5 6473.5 35% 5621 1455.5 K & K Acoustical 16 Lund Rebar (sub to JW Flett) 98 64 65% 20% 16% Manafort Brothers (sub to Manafort Precision) 257 Manafort Precision 913.5 121 28 Mass Bay Electrical 9185 2157 2185.5 488 29 McCourt 13618 5531.5 41% 3859 1749.5 McCusker Gill (sub to Cannistraro) 688 192 120 McDonough Electric (sub to Fischbach) 24 MON Landscaping (sub to McCourt) MoreTrench (sub to McCourt) 798.5 149 19% New England Insulators (sub to Cannistraro) 4629 393 207.5 1457 445 Northern Land Clearing (sub to JW Flett) 47.5 9 PJ Spillane (sub to McCourt) 460 83.5 Ramco (sub to McCourt) 14 S & F Concrete (sub to JW Flett) 126 Semper Diving (sub to JW Flett) 698 TOTALS: 206876 5669 15430 PROJECT-TO-DATE PERCENTAGES:
16
Utility Corridor and Roadway Relocation Results by Trade – December 2015
GOAL - 50% GOAL - 25% GOAL - 10% MONTHLY: December VETERAN RESIDENT MINORITY FEMALE Monthly Workforce TRADE Total Hours Number of Hours Monthly Percentage 1 Carpenter 30 0% Cement Mixers 8 18 Electricians 1912 1058.5 55% 700.5 37% 228 12% 15 Laborers 853 440 52% 270 32% 137 16% 4 Operators 426 40 9% 5 Sprinklerfitters 248 80 10 Waterproofers 556 64 54 TOTALS: 4033 1642.5 41% 1034.5 26% 405 10% MONTHLY PERCENTAGES:
17
Utility Corridor and Roadway Relocation Results by Trade – Project to Date
Boston Plan Subcontractor Totals: Project: UMASS BOSTON UCRR BI-MONTHLY ACCESS & OPPORTUNITY MEETING Dec-2015 GOAL - 50% GOAL - 25% GOAL - 10% PROJECT-TO-DATE: VETERAN RESIDENT MINORITY FEMALE PTD Hires TRADE Total Hours PTD Hours PTD Percentage PTD Hours PTD Percentage 5 Bricklayers 280.5 0% 25 Carpenters 1126.5 104 9% 203 18% 48 4% 6 Cement Finishers 40 73 Electricians 31765 664 2% 37% 9209 29% 3536 11% 23 Insulators 4680 393 8% 211.5 5% 1461 31% 445 10% Ironworkers 954 64 7% 161 17% 394 41% 219 Laborers 309.5 43% 27% 6247.5 8 Masons 284 12 81 Operators 3573 5519.5 14% 274.5 1% 19 Piledrivers 1176 340 316.5 107 153 Pipefitters 665 11566 22% 12118 23% 4416 Plumbers 4615.5 1596.5 35% 96 356 2 Sheetmetal 80 50% 14 Sprinklerfitters 4068 344 688 28 Waterproofers 1227 338 28% 698 TOTALS: 206876 5669 3% 24% 15430 PROJECT-TO-DATE PERCENTAGES:
18
Utility Corridor & Roadway Relocation Project
Project-to-Date Boston Residents – % Minority – % Female – % Veterans – % Month of June Boston Residents – % Minority – % Female – % Veterans – 0% *Graph courtesy of Policy Group on Tradeswomen Issues (PGTI)
19
Utility Corridor & Roadway Relocation Project WMBE
20
Upcoming UMBA Projects at UMass Boston
Renovation of Existing Academic Buildings Stage: Schematic Design Construction Commencement – Temporarily on hold Project Budget = $75 million OPM: Hill International Architect: Cannon Design Energy Producing Facility Stage: Entering Design Development Construction Commencement – Summer 2016 Project Budget = $32 million OPM: Jacobs Architect: Cambridge 7 CM: Gilbane Parking Garage Stage: Study Project Budget = $45 million OPM: Skanska Residence Hall Project Budget = $120 million