U.S. CMS HL-LHC Project Report
Vivian O’Dell U.S. CMS HL-LHC Project Manager
2
Introduction CMS Upgrade PMG 20 September 2016
3
HL-LHC Timeline HL-LHC Upgrades: Installed during LS3
Shutdowns HL-LHC Upgrades: Installed during LS3 (CY 2024 – mid 2026) Vivian O’Dell CMS HL-LHC Upgrades 1/19/2016
4
Funding The U.S. Project is funded by both DOE and NSF
Construction funding is ~133M DOE / $75M NSF The total funding supports a scope ~ commensurate with the US participation in CMS i.e. the US is ~ 30% of CMS, and will pay ~30% of the scope of the CMS HL-LHC upgrade Our contribution is worked out (iteratively) by maximizing: CMS upgrade needs The interests and experience of the US CMS community The NSF and DOE scopes are (largely) separated This was a requirement for the MREFC process (see below) The DOE funding process follows the “normal” route for large projects Differs from the current (Phase 1) CMS upgrades in size – means additional Independent Cost Reviews before each CD step For the NSF, we (along with US ATLAS) will be pursuing a new (for HEP) form of funding The total we are proposing is $150M, split evenly between USCMS / USATLAS This has to go through the NSF MREFC panel and the National Science Board Note: we have successfully passed the “Conceptual Design” phase and have gotten the official go-ahead to proceed to the Preliminary Design Review Preliminary Design Review / Final Design Review will be in late 2017 / late 2019 respectively – both of these steps have to be signed off on by the NSB The earliest we can expect project construction funding is in FY2020 Vivian O’Dell CMS HL-LHC Upgrades 1/19/2016
5
U.S. CMS scope NSF DOE NSF NSF DOE NSF DOE NSF 3.8 CMS Upgrade PMG
20 September 2016
6
U.S. CMS Project Review Schedule
For the DOE, we are planning for the following dates ✔ CD-0: April 13, 2016 Lab review October/November leading to… ICR (Independent Cost Review): Feb – Jun 2017 (Also DOE/NSF Operations Program Review: January hosted by ATLAS. Only overlaps with Phase 2) Director’s review ~ May leading to: CD-1: June/July 2017 CD-3a: mid-CY2018 (allows buying long lead-time items) May ask for CD-3a for e.g. buying silicon for Outer Tracker – still firming up the schedule for this. CD-2 / CD-3: early - mid CY2019 (but before May 1 ish) This allows DOE $$ for the construction project in (late) FY19 For the NSF ✔ CDR passed (Delta review): April 19 ✔ July review of new CA for operations (contains Phase 2 R&D): July 14-15 Director’s review ~ September/October, leading to… PDR: Q4 CY17 (This is like a DOE CD-2 “lite” i.e. no EVMS) FDR: (when the $$ flow) Q4 CY19 (i.e. FY20) CMS Upgrade PMG 20 September 2016
7
U.S. CMS Project Funding: DOE
Note that for 2016, we got about $3M from the Operations Program for DOE scope For 2017, we can plan on only $1.5M from Operations, $2.5M additional new money (OPC) => $4M CMS Upgrade PMG 20 September 2016
8
U.S. CMS R&D Project Funding: NSF
Note that for 2016, there is a $1M supplement for NSF R&D / Project Planning The new CA for operations starts in FY17: This includes specific funding amounts for R&D Construction start is assumed to be in 2020 Note that the Operations Program part of the budget decreases in FY17/FY18 but increases after FY19 Actually project funds will come from an MREFC, with project funding starting in 2020. Total MREFC funds for USCMS HL-LHC project is $75M We have presented a plan (at the NSF Conceptual Design Review) with a budget of ~$50M + $25M contingency We are now in the process of working out a bottom-up cost and schedule CMS Upgrade PMG 20 September 2016
9
Now preparing for Independent Cost Review
Conducted by the DOE PMOA Covers cost and schedule i.e. complete BOEs / P6 / contingency / risk Iterative process culminated by a site visit – drill down exercise Similar to the NSF CDR drill down In fact, Ivan Graff who led the NSF CDR review will be back at DOE, at PMOA. The NSF level of drill down is what we should expect! We are planning to start the process in Jan/Feb, site visit ~ May/June? Must be completed before the “Independent Project Review” (CD-1) in ~July This workshop is a checkpoint as to where we are, but not a formal review We are clearly not ready to trigger the FNAL OPSS review that will preceed the ICR We would like to get “course corrections” and feedback in order to move towards final BOEs / P6 project implementation We do not yet have a final roll-up from our bottom-up estimate – our last full rollup was done before the NSF CDR The single largest part of the project for NSF is the FPIX (~$40M) For the DOE, it is the Outer Tracker (~$50M) and the Endcap calo (~$40M) CMS Upgrade PMG 20 September 2016
10
Backup CMS Upgrade PMG 20 September 2016
11
International CMS Update
CD0 CDR CD1 PDR CD3a CD2/3 FDR International CMS schedule CMS Upgrade PMG 20 September 2016
12
U.S. CMS Project Organization
DOE scope HL-LHC CMS Detector Upgrade Project Project Office Project Manager V. O’Dell Deputy PM: A. Ryd Project Scientist: C. Hill CMS HL-LHC liaison: J. Spalding ESH&Q Coordinator: G. Snow Project Controls: W. Freeman Project Finance (DOE) J. Teng (DOE), M. Bogart (NSF) Risk Manager: L. Taylor Project Electronics Engineer TBN Project Mechanical Engineer TBN NSF scope DOE or NSF scope (TBD) OT L2 Managers: (G. Bolla) + TBN Barrel Cal. L2 Manager: C. Jessop Endcap Cal. L2 Manager: J. Mans Endcap Muons L2 Manager: A. Safonov Trigger/DAQ L2 Managers: J. Berryhill + TBN FPIX L2 Managers: J. Alexander, K. Ecklund Sensors L3M: U. Heintz ECAL L3M: B. Hirosky CSC L3M: D. Wood Cal Trig L3M: W. Smith Sensors/Modules L3M: N. Akchurin, M. Paulini Sensors/ROCS L3 Manager: S. Wagner Electronics L3M: Y. Gershtein, A. Canepa Cassettes L3M: J. Strait, Z. Gecse Muon Trig L3M: D. Acosta HCAL L3M: A. Belloni GEM L3M: D. Salzberg Modules L3 Manager: M. Jones Modules L3M: M. Narain, L. Spiegel Track Correlator Trig L3M: R. Cavanaugh BH Active L3 Manager: TBN Electronics L3 Manager: A. Ivanov Mechanics L3M: S. Gruenendahl, R. Lipton Electronics and Services L3 Manager: T. Kolberg TT L3M: P. Wittich Mechanics / Assembly L3 Manager: J. Conway Integration DAQ L3M: R. Mommsen CMS Upgrade PMG 20 September 2016 12
13
Now preparing for Independent Cost Review
Old roll-up (with old WBS) – rough costing Total w/Contingency DOE NSF 402.00 Totals 203.6 133.6 70.0 402.01 Project Office 26.9 21.4 5.5 Project Management 17.5 13.9 3.6 Common Infrastructure 9.4 7.5 1.9 402.02 Tracker 98.5 51.2 47.3 FPIX 39.6 Outer Tracker Track Trigger 7.6 402.03 Barrel Calorimeter 14.0 4.2 9.8 ECAL Barrel HCAL Barrel 402.04 Endcap Calorimeter 41.2 402.05 Muon Systems 402.06 Trigger 13.8 402.07 DAQ 1.7 CMS Upgrade PMG 20 September 2016
14
Comparison with Phase 1 Phase 1 (US CMS Detector Upgrades)
Phase 2 (US CMS HL-LHC Upgrades) Total Project $44.7M $240M DOE TPC $33.2M $155M NSF Construction $11.5M $75M (+$10.25M R&D) (MREFC) Upgrade list Outer Tracker N/A ~25% U.S. Scope (DOE) Barrel Calorimeter HCAL electronics HCAL scintillator (DOE), ECAL electronics (NSF) Endcap Calorimeter Front Hadronic active area (Si) (DOE) Endcap Muons CSC / GEM electronics (NSF) Trigger/DAQ L1 Calorimeter (50%) / endcap muon trigger L1 Calorimeter (50%)/endcap muon/L1 Track Finder (50%)/L1 Correlator Trigger (50%) (NSF/DOE) Forward Pixel Full Forward Pixel upgrade Full Forward Pixel upgrade (NSF) CMS Upgrade PMG 20 September 2016