Presentation is loading. Please wait.

Presentation is loading. Please wait.

Squamish Neighbourhood Energy Utility: Final Feasibility Presentation

Similar presentations


Presentation on theme: "Squamish Neighbourhood Energy Utility: Final Feasibility Presentation"— Presentation transcript:

1 Squamish Neighbourhood Energy Utility: Final Feasibility Presentation
Prepared for: District of Squamish and Project Sponsors Prepared by: Compass Resource Management Ltd. June 15, 2010

2 Study Overview Demand forecast (five target areas)
Analysis of business as usual (BAU) Screening of many supply options Detailed analysis of short-listed scenarios Area A + expansion scenarios (Waterfront and Oceanfront) Biomass, ocean heat, and natural gas co-generation Staging and sensitivity analysis

3 Demand Forecast – Focus Areas and Phasing

4 Demand Forecast – Phasing

5 Supply Screening – Shortlist
Biomass Abundant local resource One of lowest cost options in screening and greatest GHG emission reductions Ocean Heat Potentially slightly higher cost than GX but more available resource Best heat pump option for this location Some further optimization may be possible with cooling service to commercial loads Natural gas cogeneration BC Hydro is interested in systems which also produce electricity Best commercial electricity production option at this scale. Natural gas cogeneration is a stepping stone to biogas cogeneration GHG emissions depend on whether we use provincial perspective or regional trade perspective.

6 Summary Results – Base Case
No Grants, Private Financing, Property Taxes Included

7 Total Capital Costs by Demand and Supply Scenario
($,000)

8 Sample Phasing of Capital (All Three Service Areas)

9 Sample Cashflows - Municipal Financing

10 Summary Results - GHG Reductions
 Demand Scenario Biomass Ocean Heat Cogen (BC Perspective) Cogen (Regional Perspective) tonnes / year change at build out Area A Only (1,300) (1,100) 1,100 (900) Area A + Waterfront (3,000) (2,200) 3,700 (1,800) Area A + Oceanfront (5,000) (4,100) (3,500) Area A + Waterfront + Oceanfront (6,600) (5,200) 6,100 (4,300) % change at build out Area A Only  (74%) (62%) 62% (51%) Area A + Waterfront  (79%) (58%) 97% (47%) Area A + Oceanfront  (81%) (67%) 60% (57%) (80%) (63%) 74% (52%)

11 Summary Results – Gas and Electricity System Impacts
 Demand Scenario  Biomass Scenario Ocean Heat Scenario NG Cogen Scenario Area A + Waterfront + Oceanfront Incremental gas increase (reduction) (35,300) (28,500) 38,400 Incremental electricity increase (reduction) (9,200) (1,000) Additional electricity production - 26,900

12 Summary Results - Grant Requirements
Grant required to achieve competitive rates and target return on investment. Municipal financing scenario assumes 100% debt financing and no property taxes. Biomass Ocean Heat Cogeneration Private Financing Scenario 8,600 13,800 18,500 % of total capital 30% 41% 50% Municipal Financing Scenario 1,900 8,300 13,400 7% 24% 36%

13 Summary Results – Conclusions
All options require some level of grants to achieve competitiveness and break-even requirements. Biomass is least cost option in all demand scenarios and has the highest total GHG emission reductions and greatest reliance on local resources. All options exhibit economies of scale. Competitiveness increases as total system size increases. Securing a large service area is critical to success. Under a municipal financing model and excluding property taxes, the larger biomass system starts to approach BAU costs, even before taking into account grants.

14 Possible Optimizations (Design Phase)
Solar DHW Alternate siting of energy centre Multiple energy centres Distribution layout Actual sizing and staging of capital items Specific technology / vendor selection

15 Key Implementation Risks for District Energy
Securing loads Marketing Relationship building Policy / bylaw support Minimizing installed capital costs Technology selection Coordination with other infrastructure Competitive tendering Performance contracting Phasing of equipment relative to loads Just in time capital where possible Build in flexibility Optimize staging and siting Ensuring optimal building performance Developer design document Design and commissioning support Retrofit support

16 District Vision / Policy Support District or Community Ownership
Paths Forward District Vision / Policy Support District or Community Ownership District or Community Responsible for Design, Build, Own, Finance and Operate (some outsourcing). Decisions on ownership structure and governance required Private Ownership District find third party owner and negotiate infrastructure agreement. Third party DBFOO. P3 District find third party to lead or share Design, Build, Finance, Operate and/or Own (split assets)

17 District Policy Role Establishing target core service area boundaries
Cultivating community support Developing measures to promote/require interconnection Establishing commitment to interconnect municipal buildings Creating mechanisms to support efficient planning/installation of linear infrastructure Establishing policies and programs to encourage/facilitate access to energy resources Facilitating the selection of site(s) for energy center(s) Establishing policies for property taxes and franchise fees


Download ppt "Squamish Neighbourhood Energy Utility: Final Feasibility Presentation"

Similar presentations


Ads by Google