Operations and Service Concept
2
The L Line concept is an implementation of the Central Rail Extension (CRE) operations plan without construction of the extension to 38th & Blake Station Helps improve system reliability and on-time performance More efficient use of vehicles miles Increased flexibility for future service
3
L Line Proposal Fits With Other Light Rail Changes
C Line replaces the D Line as base service for the Southwest Lines Helps with DUS connections, CU A Line service: every rail corridor has a one-transfer connection Special service to CPV events would be covered with regular service: Rockies, Broncos, etc E Line midday service increase to 15-minutes
4
D and L Line Change Proposals
L Line replaces D Line between downtown and 30th & Downing L Line is scheduled to offset Route 43 times, providing even service during off-peak
5
C and D Line Change Proposals
C Line becomes the base route for Southwest C Line increases to 15-minute base frequencies most of the day, every day D Line turns into peak-oriented (similar to F Line)
6
E and F Line Change Proposals
E Line midday service increased to 15-minute frequencies Keeps up with E Line growth, consistent service throughout the week, and CU A Line connections
9
L Line trains in context with other trains in the downtown loop
10
Peak Hour, Peak Direction Southwest Corridor Throughput
Current Proposed 30th & Downing 1,200 162 400 Downtown and DUS I-25 & Broadway 2,400 2,500 1,587 324 600 1,800 1,263 1,000 1,500 Littleton-Mineral Jan16 Peak hour load Peak hour capacity Jan16 Peak hour load Peak hour capacity
11
Peak Vehicle Requirement
Proposed Current C/D Lines 5 trains X 3 cars = 15 LRVs D Lines 7 trains X 3 cars 21 LRVs 36 total peak LRVs C Lines 1 trains X 3 cars + 4 trains X 2 cars = 11 LRVs D Lines 4 trains X 4 cars 19 LRVs L Lines 3 trains X 2 car = 6 LRVs 36 total peak LRVs
12
Operations and Maintenance Cost Summary
Existing: $1.3 to $3.4 million In annual savings Proposed: 3 L Line Options Based on Cars Per Train Plus Estimated Special Event Savings: 12,510 revenue car hours 309,490 revenue car miles $2,066,572 annual fully-allocated total route costs
13
Signal Work Required for 14th & Stout Intersection
Two additional rail signals for switch movement Traffic signal for loop trains for transit signal phase Additional train to wayside communication (TWC) loop at 15th Street
14
Next Steps Approval of PUC Application (by end of June) Continued coordination with the City and County of Denver for signal work (July-August timeframe) Public outreach in advance of runboard process (this month) August 2017 service change public hearings (June)