Presentation is loading. Please wait.

Presentation is loading. Please wait.

UMCP Learning Objectives

Similar presentations


Presentation on theme: "UMCP Learning Objectives"— Presentation transcript:

1 Turning Renewal Needs into Opportunity: Campus Utility Plant and Master Plan

2 UMCP Learning Objectives
Case study of a combined utility master plan and condition assessment to identify long term costs Preparation of near and long term implementation plans and using continuous commissioning to ensure intended results Tools for condition assessments UMCP

3 University of Maryland College Park
6/4/2018 Campus Growth Existing campus ~13.5 million gross square feet Near term identified 17% increase in building area Energy Infrastructure Central Energy Plant (CEP) Combustion Turbines Heat Recovery Steam generator Boilers Steam distribution 13.8 kV Electrical distribution 13 District chilled water plants (SCUBs) UMCP

4 UMCP Background Development of the study Third Party Operates
2012: Developed Utility Master Plan (did not include assessment of infrastructure) 2014: Assessed major equipment in Energy Plant 2015: Assessed electrical and steam distribution Third Party Operates CEP Steam distribution Electrical distribution 1 of 13 SCUBs Current contract with third party will end by fiscal year 2019 Potential to extend contract an additional 5 years UMCP

5 Goals of Assessment and Studies
Determine upgrade needs for the next 25-year phase of operation Include campus growth Synchronize with campus goals Resiliency Minimized financial impact Sustainability UMCP

6 Agenda – Utility Master Plan
Steam System Review Current condition Potential future options Electrical System Review Chilled Water System Review

7 Steam Distribution Assessment
Manhole survey Thermal aerial flyover Piping segment age / general condition summary Renewal Piping & manhole Consequences Options (District Hot Water) Building steam use Energy savings for hot water loop Updated steam piping costs

8 Steam Manhole Survey Summary
Manhole C-125 Uninsulated / Flooded Manhole C-155 Uninsulated / Flooded Manhole STM-123 Structural Repair Manhole 510 Condensate Leak

9 Steam Manhole Survey Site
Capital Renewal Steam Manhole Costs: $~12 Million

10 Steam and Condensate Piping
Steam Piping Condensate Piping

11 Steam Piping Renewal Reactive Piping Replacement (0-5 years): $17.4 million Proactive Piping Replacement (6-15 years): $62.9 million Total Piping Costs: $80.3 million Manholes Upgrades Costs: $11.7 million Total Steam Distribution Costs: $92.0 million

12 Central Energy Plant Assessment
Combustion Turbine (not completed by RMF) Back Pressure Steam Turbine (not completed by RMF) Heat Recovery Steam Generators Boilers Deaerator Nos. 1, 2,3 Condensate Receiver No. 2 Fuel Oil Piping Polishers/ Softeners

13 Capital Renewal for Central Energy Plant

14 Existing Chilled Water SCUB Sites
Chiller Location Replacement Interval (age > 25 yrs) 0-5 yrs (Tons) 6-10 yrs 11-15 yrs > 15 yrs SCUB’s 5,120 10,490 --- 3,925 Buildings 2,600 250 5,200 Total 7,720 10,740 9,125 28% 39% 33%

15 Capital Renewal / Future Chiller
Total Replacement costs: $51.8 New costs: $8.9 Total costs: $60.7

16 Electrical Manhole Survey Summary
Total No. of Manholes: ~360 manholes Manholes Surveyed: Manholes Minor maintenance items identified

17 Building Transformers
62 Building Transformers (36 buildings surveyed) A.V. Williams South B Epply Physics

18 Splice Testing Modular Splice installations was concerning due to recent failures. RMF inspected 2 of the 5 locations in question Findings Installation Issues Deterioration of components Possible Failure Points Deteriorated splice components were replaced Entire splice assembly was tested and placed back into service. Feeder 4 still had low test results on Phase A.

19 Future Feeder Capacity

20 Base Option Recommendation

21 Alternative Considered
Steam Distribution Alternatives Energy Plant Alternatives Interconnect Existing SCUBs Islanding CEP from Utility System

22 Alternative to Steam: Building Steam Use

23 Hot Water Analysis

24 Hot Water Costs Comparison

25 Energy Plant Alternatives
Replace Existing Cogeneration with: Smaller units Same size units Larger Units

26 Energy Plant Recommendation
Larger cogeneration units More economical when compared to purchasing power Higher first cost Has a higher carbon footprint than purchasing “green power” Largest units may require SCR or Urea University Input Required

27 Chilled Water Interconnection
Base Option Interconnection of SCUBs Replacement cost: $36 M Distribution costs: $ --- M New chiller cost: $ 9 M Replacement cost: $36 M Distribution costs: $ 9 M New chiller cost: $ --- M Additional benefits include more efficient operation with part loading existing equipment Less maintenance required

28 Recommended Alternative

29 Simplified Heating Schematic

30 Potential Funding Opportunities
New Operating Agreement for Cogeneration system Bond for steam and hot water piping Energy savings from CHP and Piping Renewable Energy District or Renewable energy Controls Integration project Resiliency projects UMCP

31 University of Maryland Director, Engineering and Energy
Questions? Mary-Ann Ibeziako, PEM University of Maryland Director, Engineering and Energy (301) Andy Jones, PE RMF Engineering, Inc. Project Manager (800)


Download ppt "UMCP Learning Objectives"

Similar presentations


Ads by Google