Download presentation
Presentation is loading. Please wait.
Published byNoel Barrett Modified over 6 years ago
1
Status of LHC installation & New Installation Schedule
19 June 2007 Sylvain Weisz - LEMIC
2
Sector 1-2, 2-3 & Point 3 LSS1R Arc 1-2 & DS TI2 LSS2L LSS2R
Q1 & Q3 reparation on surface, transport and lowering of low-β scheduled CW27-29 Arc 1-2 & DS Interconnection in progress, global advancement ~35% TI2 Magnets (MQI/MBI) and TED in place, beam-pipe installation in progress last LHC Arc cryo-magnets in UJ22 (MB2311/SSS652/MB3390) in place LSS2L Short circuit tests in progress MKI not available, Alice ZDC installation CW24-25 Low-β repair & interconnection takes up to CW43 critical for completion of Sector 1-2 LSS2R Q3.R2 on surface, DFBAD HCM in place, LCM available July 4th Short circuit tests completed last week Arc 2-3 & DS Interconnection in progress: ~70% global advancement Q11.R2 has a short and will be replaced (SSS ready CW32) impact on interconnect activity LSS3L/R DSLC: leaky compensators on thermal shield lines, should be replaced Q6.L3 and DFBMD available, installation pending completion of DSLC Installation of last warm magnets postponed, pending DSLC installation Modification of power cabling in UJ33 scheduled CW23-27 Planning issue 19 June 2007 Sylvain Weisz - LEMIC
3
Low-β repair: conceptual drawing to implementation
Cartridge model for fixed point reinforcement Cartridge installation in Q1.R1 (done in Bld. 181)
4
Sector 1-2, 2-3 & Point 3 LSS1R Arc 1-2 & DS TI2 LSS2L LSS2R
Q1 & Q3 reparation on surface, transport and lowering of low-β scheduled CW27-29 Arc 1-2 & DS Interconnection in progress, global advancement ~35% TI2 Magnets (MQI/MBI) and TED in place, beam-pipe installation in progress last LHC Arc cryo-magnets in UJ22 (MB2311/SSS652/MB3390) in place LSS2L Short circuit tests in progress MKI not available, Alice ZDC installation CW24-25 ??? Low-β repair & interconnection takes up to CW43 critical for completion of Sector 1-2 LSS2R Q3.R2 on surface, DFBAD HCM in place, LCM available July 4th Short circuit tests completed last week Arc 2-3 & DS Interconnection in progress: ~70% global advancement Q11.R2 has a short and will be replaced (SSS ready CW32) impact on interconnect activity LSS3L/R DSLC: leaky compensators on thermal shield lines, should be replaced Q6.L3 and DFBMD available, installation pending completion of DSLC Installation of last warm magnets postponed, pending DSLC installation Modification of power cabling in UJ33 scheduled CW23-27 Planning issue 19 June 2007 Sylvain Weisz - LEMIC 4 4
5
Sector 3-4 & 4-5 Arc 3-4 & DS LSS4L/R Arc 4-5 & DS LSS5L
Interconnection in progress, global advancement ~95% 10 vacuum sub-sectors (out of 14) delivered to VAC, 7 leak tight and 3 under test Reparation on-going on 500 series SSS (Q7-Q11.R3), need to open cold masses hold completion of interconnect in arc 3-4 LSS4L/R All elements in place, NEG activation of straight section completed this week BGI detector damaged using wrong bake-out cycle! Klystron power tests in progress in UX45 Short to ground on MCB circuit in Q5.R4 reparation after 1st HW commissioning period of sector 4-5 Arc 4-5 & DS Interconnection completed, pressure test passed successfully on May 11-12th He flushing in progress Cryo instrumentation checks, ELQA at warm and polarity checks in progress Replacement of 28 Velan valve puppets end of this week Cool-down of Sector 4-5 starts CW26 (next week) LSS5L Low-β: DFBX/Q3/Q2/Q1.L5 back on surface for repair Cool-down 4-5 without low-β Power test of warm magnets (D1.L5) completed First Roman Pots station in place 19 June 2007 Sylvain Weisz - LEMIC
6
Sector 5-6, 6-7 & Point 7 LSS5R Arc 5-6 and DS LSS6L LSS6R
Reparation of low-β fixed points scheduled CW27-33 critical path for completion of Sector 5-6 Power test of D1.R5 completed, test of low-β wire based alignment system in progress Interconnect Q4/Q5/Q6-DSLE and Q7-DFBAJ in progress Arc 5-6 and DS Interconnection in progress, global advancement ~90%, 5 vacuum sub-sector completed LSS6L DFBAK: HCM, LCM and LEJL connection cryostat in place Special configuration of DFBAK Proximity Equipment requiring extra ELQA (TP2) in place MKD tests in progress, difficult co-activity with dump line installation dump line completion resumes after August 15th LSS6R Installation of MKD and MKB tests in progress DFBAL HCM and LCM in place, ELQA (TP2) on-going with proximity equipment in place Arc 6-7 & DS: Interconnect in progress, global advancement ~55% LSS7L/R Preparation for warm magnet tests in progress (alignment smoothing done) - tests scheduled CW25-28 Collimator supports in place, collimator installation starts CW29 after warm magnet tests 19 June 2007 Sylvain Weisz - LEMICC
7
Sector 7-8 Temperature stabilisation and Power tests
Cryogenics conditions are now very stable below λ point Ice accumulation problems on current leads have been solved with the installation of dry air bags D2, Q4 & Q5 (4.5K magnets) have been powered to their nominal current (6 kA) Main arc circuits (MB & QF/QD) and correctors chains have been qualified at cold Quench protection systems and associated heaters have been validated Tests of Powering Interlock Controller are almost complete Powering of the arc magnets is imminent … But repairs in sector 7-8 (replacement of 1055, PIMs, bus-bar on SSS 500, etc…) start early August Need 4 weeks for warm-up, power tests have to stop prematurely 19 June 2007 Sylvain Weisz - LEMIC
8
Sector 8-1 LSS8R Low-β: HX reparation completed, interconnect (H pieces) completed, fixed point strenghtening (cartridge installation) CW25-31 critical path for completion of Sector 8-1 Test of LHCb warm compensators (MBXW) completed Y vacuum chamber available: D1-D2 vacuum installation in progress Arc 8-1 Interconnections completed Pressure test passed with success on June 9-10th LSS1L Interconnection of DFBLA to DSLA completed Installation of D1-D2 vacuum chamber in progress 19 June 2007 Sylvain Weisz - LEMIC
9
Installation Summary Interconnections:
Completed in Sectors 7-8, 8-1 & 4-5, pressure tests Ok 92% of magnet to magnet electrical connections done, 51% of W closures completed Expect closure of sector 1-2 (arc & DS), incl. leak tests, by end of September Uncertainties and delays from repair of Serie 500 bus-bar insulation Preparation for short circuit tests: Tests in progress in Point 2L (14/15 power station tested) Preparation for tests in Point 1R on schedule Tests in UJ33 will be re-done after modification of power cables routing Installation of warm beam pipes in long straight sections: Components procurement Ok, ~200m/wk installed and activated Advancement below expected rate, perturbed by: Area not available: LSS3L/R or UJ62-63 (for dump line) Co-activities: Point 6 (with kicker), Point 8R (with warm magnet tests) Uncertainty on equipment installation: collimators in LSS7L/R 19 June 2007 Sylvain Weisz - LEMIC
10
Installation rate of LSS warm beam pipe
Courtesy of Miguel Jimenez 25 May 2007 Sylvain Weisz - ICC
11
LHC Construction and Installation General co-ordination Schedule
LHC project Document N° LHC-PM-MS rev. 4.0 CERN Dep./Group/Contractor Document N°. TS/IC EDMS Document N°. 102509 12 June 2007 12 23 34 45 56 67 78 81 Mar. Apr. May Jun. Jul. Aug. Oct. Sep. Nov. Dec. Jan. Feb. . Consolidation Operation testing of available sectors Machine Checkout Beam Commissioning to 7 TeV Interconnection of the continuous cryostat Global pressure test &Consolidation Warm up Leak tests of the last sub-sectors Flushing Powering Tests Inner Triplets repairs & interconnections Cool-down Prepared by Katy Foraz
12
New Installation Schedule - General Features
Sector 4-5: Arc & DS ready cool-down without low- Sector 3-4: Delays with DSLC cool-down without DSLC Get experience with HW commissioning of 2 sectors in parallel Time window for fixes after 1st HW commissioning period Need for an extra warm-up/cool-down cycle Sector 7-8: Repairs scheduled Aug.-Sept. power tests stop early July Sector 8-1: Repair low- (8R & 1L) before cool-down Need to warm-up sector 7-8 before completion of first power tests program Cool-down and test low- as early as possible HW commissioning directly up to 7 TeV Need to commission many sectors in parallel Get ready for physics by summer 2008 19 June 2007 Sylvain Weisz - LEMIC
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.