Download presentation
Presentation is loading. Please wait.
1
Col. Pike Multimodal: About the Project
The goal of the Columbia Pike Multimodal Street Improvement Project is to transform this main thoroughfare into a “Complete Street” designed and operated to enable safe, attractive, and comfortable access and travel for all users: Pedestrians Bicyclists Transit riders Motorists In addition to visible improvements to the road, extensive work is occurring below the roadway to replace aging and leak-prone water and sewer pipes and to relocate existing overhead utilities underground.
2
Proposed Improvements – Design Considerations
Balance between pedestrian, bicycle, transit, and vehicle spaces 56-ft street cross section Include left turn lanes/medians Eliminate right turn lanes and bus pull-outs Behind curb line: Wider sidewalks, transit shelters, street trees, planting strips, bicycle accommodations Drainage Utilities Existing overhead lines will be relocated underground Aging underground infrastructure will also be replaced/upgraded Infrastructure upgrades support on-going revitalization of Columbia Pike Additional ROW Requirements
3
Proposed Near-Term Typical Plan
4
Columbia Pike - Multimodal Street Design & Construction Segments
H & I Next G Complete F Future E C & D B A Segment Limits Status H & I County Line to Four Mile Run Design Completion Summer 2016 & Constr. Early 2017* G Four Mile Run to S. Wakefield St Completed Summer 2015 F S. Wakefield St. to S. Oakland St Design Completion Fall 2016* E S. Oakland St. to S. Garfield St Completed Fall 2009 C & D S. Garfield St. to S. Quinn St Design Completion Early 2017* B 27/244 Interchange (VDOT) Completed Summer 2015 A S. Orme St. to S. Joyce St Orme to Oak – Design Completion Early 2017* *Subject to Obtaining Property Rights
5
Current Status of the West End (Segment H/I)
DESIGN Final plan submission in July 2016 Approval anticipated September 2016 RIGHT-OF-WAY 14 properties requiring easements 6 properties remaining Nearing completion on 5 of the remaining properties Bidding/Notice to Proceed Can’t begin until plans are approved and all permanent easements are acquired Requires Washington Gas relocations to be completed prior to construction. 4-5 months to notice to proceed from release of invitation to bid.
6
What to Expect During Construction
Sidewalks blocked Bus stops relocated Noise Traffic disruptions Limited night work for center of intersections
7
Construction Duration/Sequence
Construction Duration anticipated to be 30 Months Specific Construction Sequence Varies depending on contractor’s means and methods Specific schedule to be submitted by the contractor at kick-off meeting Anticipated Construction Priorities 1st Priority: Utility ductbank construction 2nd Priority: Dominion Virginia Power, Verizon, and Comcast undergrounding cables into ductbanks 3rd Priority: All other items
8
Significant Utility Work
9
Street Improvement Plan
10
Street Improvement Plan
Regrading of Columbus and Dinwiddie
11
Street Improvement Plan
12
Street Improvement Plan
13
Street Improvement Plan
14
Street Improvement Plan
15
Street Improvement Plan
16
Columbia Pike Street Improvements & Bike Boulevards
Visit our project webpage:
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.