1
Gas system Commissioning procedures and status
S. Haider PH/DT1
2
Gas system commissioning Dec 2006 S.Haider PH/DT1
Overview What is commissioning for us Status Alice Atlas Plans for 2007 Conclusions Gas system commissioning Dec S.Haider PH/DT1
3
Production cycles of the gas system hardware
Construction Installation Commissioning Running-in Leak + functional test Verification (pipes+cables) 10 5 Gas system commissioning Dec S.Haider PH/DT1
4
Production cycles of the gas system software
Collect options Production of code Installation Lab tests 60 Gas system commissioning Dec S.Haider PH/DT1
5
Commissioning steps (1/2)
In general Commissioning is a Verification of functionality (hardware + software debugging phase) Installation of PLC, WebMas and PVSS software Test Profibus and CANbus lines from PLC to field nodes Cable check from control racks to gas racks With control interface we take output objects into manual mode and operate them (valves, pumps, MFCs, LEDs,…) For input devices we: Take off the device-connector in the rack and observe the state change on the control interface Provoke a reading with a change of pressure or flow in an other part of the system. Gas system commissioning Dec S.Haider PH/DT1
6
Commissioning steps (2/2)
Activate first set of parameters Verify new functionality (where applicable) Eg MDT mixer with liquid injection,- or RPC humidifier Verify chamber pressure interlocks Verify leak tightness of inter-area piping Run gas through chambers 1) computers 2)+3) cable IO check 4) 1st parameters 5) New functionality 6) interlocks 7) Leak tightness 8) Gas to chamber Gas system commissioning Dec S.Haider PH/DT1
7
Gas system commissioning Dec 2006 S.Haider PH/DT1
Status The following slides do not take into account: Purifiers Membranes Liquifiers Analysis modules Only racks installed up to NOW are considered Gas system commissioning Dec S.Haider PH/DT1
8
ALICE commissioning status
Dec 2006 100% ok 1 rack of 2 ok not applicable to be done 1/2 n/a TPC HMP PMD CPV Track Trigg TOF TRD Computers Cable + IO check 3/6 9/11 1st parameters 50% 30% New functionality n/a Interlocks Pipe Leak tightness Gas to chamber Gas system commissioning Dec S.Haider PH/DT1
9
ATLAS commissioning status
Dec 2006 all installed ok 1 rack of 2 ok not applicable to be done 1/2 n/a RPC MDT CSC TRT TGC ID Computers 90% Cable + IO check 9/11 14/18 1/3 30% (2/8) 1st parameters 60% New functionality 80% n/a Interlocks Pipe Leak tightness Input line ok Gas to chamber 6/128 channel 4/274 channel Gas system commissioning Dec S.Haider PH/DT1
10
Most commonly found mistakes
Cable + pneumatic lines Swapped Wrong labeled Come to wrong rack in UX Cut BUT: - “Whatever can be fixed within one day is not considered a mistake !” - MDT has 304 pneumatic lines of which only ~ 15 were wrong !!! Gas system commissioning Dec S.Haider PH/DT1
11
Commissioning Estimate vs reality up to now
days S all ~ 60!!! ……….ATLAS………. …CMS… ……………ALICE…………….. ……..LHCb…….. Gas system commissioning Dec S.Haider PH/DT1
12
Gas system commissioning Dec 2006 S.Haider PH/DT1
Commissioning plan for 2007 2007 Jan Feb Mar Apr May Jun Jul Aug Sep IT/CO software Installation work Commissioning LHCb IT/CO software Installation work Commissioning CMS IT/CO Analysis, updates, etc… Purifier+Membrane instal. Commissioning of Purif+Membr. ATLAS BIG Wheels TOTEM Gas system commissioning Dec S.Haider PH/DT1
13
Gas system commissioning Dec 2006 S.Haider PH/DT1
Conclusions Commissioning procedures are very well tuned by now. The teams ( ours + IT/CO) work extremely efficiently ALICE and ATLAS systems will be ready to deliver gas to chambers by end Jan 2007 (installed racks only) By about July 07 all gas systems (but TOTEM) will/should be commissioned No “show stoppers” in sight so far (let’s keep fingers crossed…) Gas system commissioning Dec S.Haider PH/DT1