Download presentation
Presentation is loading. Please wait.
1
PTS 3.3 C Portable Test System
2
PTS 3.3 C Portable Test System
Consists of: Precision reference meter with high accuracy in class 0.05 Voltage and current source in the range: 30 V V and 1 mA A Application: Verification of the entire measurement installation Meter error measurement Display of vector diagram of the supply conditions Automatic tests without PC Burden measurement of CT’s and PT’s
3
Particularities
4
PTS 3.3 C 3-phase portable Test system with Voltage and Current Source
Voltage source V Current source 1 mA A Integrated working standard accuracy class 0.05 % Measurement of all electrical values Vector diagram, Harmonic test, Data storage, Burden test Automatic test runs without external PC Options: High current cables up to 120 A Clamp-on CT´s 10 mA A CALSOFT II Software
5
Connections [1] Auxiliary supply connector [2] 10 A Current Outputs [3] 10 A Current Inputs [4] Fuses for current connections [5] 120 A Current Outputs [6] 120 A Current Inputs [7] Voltage output phase connector [8] Voltage output neutral connector [9] Fuses for voltage connections [10] Voltage input phase connector [11] Voltage input neutral connector
6
Connections [12] Compact flash card slot [13] Impulse output
[14] 100 A CTs connector [15] Impulse input [16] Serial interface RS 232 [17] Cursor keys and alphanumeric key pad [18] Connector for external keyboard [19] Turnable handling button [20] Graphical colour display
7
Operation Concept Symbols Display Control Elements
8
Software Reference - Main Menu First Row Meter Testing
Measurement Harmonics, Oscilloscope Energy Measurement Transformer Test Special Functions Installation (Setup) First Row
9
Software Reference – Error Measurement
10
Software Reference - Measurement of UI, PQS and UIPQS
11
Software Reference – Wave Form and Vector Diagram
12
Software Reference - Harmonic Analysis
13
Software Reference - Energy measurement and Register test
14
Software Reference - Burden measurement of PTs
15
Software Reference - Burden measurement of CTs
16
Software Source - Main Menu First Row Load Point Harmonics
Ripple Control Installation (Setup) First Row
17
Software Source – Load Points
18
Software Source – Harmonics
19
Software Source – Ripple Control Signals
20
Software Sequence – Create / Edit Test Sequence
21
Software Sequence – Automatic Test Run
22
Software Data Base - Main Menu First Row Administrative data
Meter data Transformer data Load point data View test result Basic settings First Row
23
Software Data Base – Administrative Data
24
Software Data Base – Meter Data
25
Software Data Base – Transformer Data
26
Software Data Base – View Test Results
27
Windows©-Software CALSOFT Selection of real time readout or
readout of sets of data from PTS 3.3 C memory
28
Windows©-Software CALSOFT Display of read data on PC monitor